Western Electric or Nelson rules: which SPC alarms to turn on

The reader questionWhich out-of-control rules should our SPC software alarm on, and what does each extra rule cost in false alarms?

A tiny worker at a wall panel of six large unmarked toggle switches, flipping some up and leaving others down beneath a small lamp.

Turn on Rule 1, a single point beyond the 3-sigma control limits, for every control chart, and add other rules only where you know what they cost and who will act on them. The NIST/SEMATECH e-Handbook puts the price plainly: with Rule 1 alone, an in-control chart gives a false alarm about once every 371 points on average, and adding the Western Electric rules raises that to about once every 91.75 points. Whether that is acceptable depends on how many points the chart plots per shift, whether consecutive points are independent, and whether each alarm leads to a written action.

This article compares the Western Electric rules and the Nelson rules, measures what each extra rule costs in false alarms and gains in detection speed, and turns the numbers into a rule set for each chart type and data source. It is written for the people who configure alarms in SPC software as much as for the engineers who read the charts.

What the Western Electric rules say

The Western Electric rules are usually given as four tests that flag a nonrandom pattern on a Shewhart control chart. They come from the Western Electric Company’s Statistical Quality Control Handbook of 1956, and they look for patterns that are about as unlikely as a point outside the control limits.

The tests divide the space between the center line and each control limit into three bands, each one standard deviation wide. The bands are usually called zones:

  • Zone C is within 1 sigma of the center line.
  • Zone B lies between 1 and 2 sigma.
  • Zone A lies between 2 and 3 sigma, out to the control limit.

“Sigma” here means the standard deviation of the plotted statistic: of individual readings on an individuals chart, or of subgroup averages on an X-bar chart. It is not the standard deviation of single parts when you plot averages, and it is never derived from the specification limits.

The NIST/SEMATECH e-Handbook of Statistical Methods lists the Western Electric Company (WECO) rules like this, for each side of the center line:

  1. “Any Point Above +3 Sigma” (or below -3 sigma).
  2. “2 Out of the Last 3 Points Above +2 Sigma” (or below -2 sigma).
  3. “4 Out of the Last 5 Points Above +1 Sigma” (or below -1 sigma).
  4. “8 Consecutive Points on This Side of Control Line”.

The same NIST page adds two “trend rules”: “6 in a row trending up or down” and “14 in a row alternating up and down.” Those two belong to the wider family of tests that Lloyd Nelson later numbered, which is one reason software menus and web pages disagree about what “the Western Electric rules” include. When someone on your team says “turn on the WECO rules,” ask whether they mean four rules or six.

The logic behind the zone rules is probability. NIST explains that for normally distributed data a point outside plus or minus 3 sigma has a probability of about 0.3 percent, and that two out of three points in a row between 2 and 3 sigma, or four out of five between 1 and 2 sigma, are “also about 0.3 %” events. Each rule on its own is about as rare as Rule 1. Taken together, they are not, and that combined cost is what this article measures.

The two-out-of-three and four-out-of-five rules count points on the same side of the center line. A point at +2.5 sigma followed by one at -2.5 sigma does not trigger the two-out-of-three rule, although two such points in a row would deserve a look at the measurement.

How the Nelson rules differ from the Western Electric rules

The Nelson rules are eight numbered tests for special causes that Lloyd S. Nelson published in the Journal of Quality Technology in 1984, in “The Shewhart Control Chart: Tests for Special Causes.” They keep the Western Electric zone rules, lengthen the run rule from eight points to nine, and add tests for trends, alternation and two kinds of stratification.

Statistical packages such as SAS/QC and Minitab use Nelson’s numbering. The SAS/QC documentation says its eight standard tests are “indexed according to the numbering sequence used by Nelson,” and the same page notes that these tests are also called runs rules, pattern tests and Western Electric rules. Minitab’s help on tests for special causes uses the same order and names the tests this way:

  1. Test 1: One point more than 3σ from center line.
  2. Test 2: Nine points in a row on the same side of the center line.
  3. Test 3: Six points in a row, all increasing or all decreasing.
  4. Test 4: Fourteen points in a row, alternating up and down.
  5. Test 5: Two out of three points more than 2σ from the center line (same side).
  6. Test 6: Four out of five points more than 1σ from center line (same side).
  7. Test 7: Fifteen points in a row within 1σ of center line (either side).
  8. Test 8: Eight points in a row more than 1σ from center line (either side).

Two differences matter most in practice. The first is the run rule. Western Electric signals on 8 points in a row on one side of the center line, Nelson on 9. Summarizing Nelson’s own comments, the SAS/QC guide’s notes on interpreting the tests say that using nine points “makes the chance of a false signal comparable to that of Test 1.” The same documentation notes that the Western Electric handbook discusses tests corresponding to Nelson’s Tests 1, 5, 6, 7 and 8, plus the eight-point run.

The second difference is that Tests 7 and 8 do not look for a shifted process at all. They look for a badly built chart. SAS describes both as indicators of stratification, where “observations in a subgroup have multiple sources with different means.” Test 7 fires when every subgroup mixes sources, so the limits are too wide and the points hug the center line. Test 8 fires when subgroups are taken from one source at a time, so the points avoid the center. Both are messages about the subgroup design, which is the subject of our article on forming rational subgroups.

Nelson also said which tests to use. As reported in the SAS documentation, Tests 1 to 4 “should be applied routinely,” and the combined chance of a false signal from one or more of them “is less than one in a hundred.” For variables charts, Tests 5 and 6 can be added “when earlier warning is desired,” and then “the chance of a false signal increases to two in a hundred.” He also warned that these probabilities “should not be considered to be very accurate,” because they rest on assumptions of normality and independence that real data may not meet, and that the tests “should be viewed as simply practical rules for action.”

PatternWestern ElectricNelson testWhat it usually points to
One point beyond 3 sigmaYesTest 1A large shift, a wider spread, or a single aberration such as a measurement error
Two of three points beyond 2 sigma, same sideYesTest 5A moderate shift in the mean
Four of five points beyond 1 sigma, same sideYesTest 6A small, sustained shift
Run on one side of the center line8 in a rowTest 2: 9 in a rowA small, sustained shift
Six points steadily rising or fallingListed with the trend rules on the NIST pageTest 3Drift, such as tool wear
Fourteen points alternating up and downListed with the trend rules on the NIST pageTest 4Two streams used alternately
Fifteen points in a row within 1 sigmaDiscussed in the handbookTest 7Mixed sources in every subgroup; limits too wide
Eight points in a row beyond 1 sigma, either sideDiscussed in the handbookTest 8Subgroups taken from one source at a time
The Western Electric rules and the Nelson tests compared. Sources: NIST/SEMATECH e-Handbook 6.3.2; SAS/QC 13.1 User's Guide, Standard Tests for Special Causes and Modifying Standard Tests; Minitab Support, Using tests for special causes in control charts. Checked November 2026.

What each extra rule costs in false alarms

Each rule you add shortens the average time between false alarms and also shortens the time to catch a real shift. The measure for both is the average run length (ARL): the average number of points plotted before the chart signals. The in-control ARL is the average wait for a false alarm. The out-of-control ARL is the average wait to detect a shift of a given size.

The NIST handbook gives the two anchor figures. For a Shewhart chart with 3-sigma limits and normal data, the chance of a point beyond the limits is 0.0027, so the in-control ARL is 1/0.0027 = 370.37, which NIST describes as a false alarm “each 371 runs.” Adding the WECO rules, NIST reports, “increases the frequency of false alarms to about once in every 91.75 points, on the average,” citing Champ and Woodall’s 1987 paper in Technometrics. When figures quoted elsewhere differ from these, check whether they mix rule sets, count per test rather than per chart, or report a probability per point instead of a run length.

To compare the other common combinations on the same footing, we simulated them for this article. The method:

  1. Generate independent, normally distributed points with control limits known exactly, not estimated.
  2. Run each rule set from a fresh start until its first signal, 100,000 times.
  3. Repeat with the process mean shifted by 1 and by 2 standard deviations of the plotted statistic.

The simulation reproduces the NIST anchors (370.3 points for Rule 1 alone, 92.1 for the four WECO rules) and NIST’s figure of about 44 points to detect a 1-sigma shift with Rule 1, so the other rows can be read with the same confidence.

Rule set Points per false alarm (in-control ARL) Points to detect a 1-sigma shift Points to detect a 2-sigma shift
Rule 1 only 370 44 6.3
Rule 1 + 9 in a row (Nelson Tests 1 and 2) 215 17 5.1
Rule 1 + 8 in a row 153 15 4.9
Nelson Tests 1 to 4 119 17 5.1
Four WECO zone rules 92 9.3 3.3
Nelson Tests 1 to 6 79 9.7 3.3
Nelson Tests 1 to 8 74 9.7 3.3
WECO zone rules + NIST trend rules 70 9.3 3.3

Three things stand out. A single run rule buys most of the gain for small shifts: Rule 1 plus nine in a row detects a 1-sigma shift in about 17 points instead of 44, while keeping false alarms to about one in 215 points. The zone rules (Nelson Tests 5 and 6, or the WECO set) bring detection down to about 9 or 10 points, but false alarms rise to roughly one in 80 to 90. Tests 7 and 8 add false alarms without speeding up shift detection at all, which fits their purpose: they diagnose stratified data, not shifts.

For a 2-sigma shift every set detects within a handful of points, and Rule 1 alone needs about 6. If the shifts that hurt your process are large, extra rules add noise for little gain. If the shifts that hurt are small and slow, the run rule is the cheapest addition.

Why not narrow the limits instead?

Some software lets you draw the limits at 2.5 sigma instead of 3, and it is tempting to do that rather than add rules. The SAS documentation lists tighter limits as one way to make a chart more sensitive, and also warns that “tightening the control limits increases the chances of falsely signaling an out-of-control condition.” The arithmetic shows how much. With limits at 2.5 sigma and normal data, a point falls outside them about once every 80 points while the process is in control, and a 1-sigma shift is caught in about 15 points. Rule 1 at 3 sigma plus eight in a row catches the same shift in about 15 points but gives a false alarm only once every 153 points. A run rule buys the same sensitivity for about half the false alarms, and it keeps the limits comparable with every other chart in the plant.

Points per false alarm Points to detect 1-sigma shift longer is quieter shorter is faster Rule 1 only 370 44 Rule 1 + 9 in a row 215 17 Rule 1 + 8 in a row 153 15 Nelson tests 1 to 4 119 17 WECO four zone rules 92 9.3 Nelson tests 1 to 6 79 9.7 Nelson tests 1 to 8 74 9.7 Average run lengths, independent normal data, known 3-sigma limits
Average run length for seven rule sets. Rule 1 and WECO in-control values match the NIST/SEMATECH e-Handbook (371 and 91.75 points); the other values come from a simulation run for this article (100,000 runs per cell, independent normal data, known limits), checked November 2026.

These figures describe the ideal case. Real charts use estimated limits, and the NIST handbook warns that when control limits are not computed from a large amount of data, “the actual properties might be quite different from what is assumed.” Treat the table as a ranking of costs, not as a promise about a particular chart.

Points per shift decide how noisy a chart feels

An ARL is counted in points, but operators experience alarms per shift. To convert, divide the number of points a chart plots per shift by its in-control ARL. A chart that plots 8 points a shift and alarms falsely once per 92 points gives one false alarm about every 11 or 12 shifts. A chart that plots 480 points a shift with the same rules gives about five false alarms every shift.

The table below does that arithmetic for an 8-hour shift at several sampling rates, for illustration. It assumes independent points and that the rule counts restart after each alarm.

Points plotted per 8-hour shift Rule 1 only Rule 1 + 9 in a row Four WECO zone rules Nelson Tests 1 to 8
8 (one subgroup an hour) 1 every 46 shifts 1 every 27 shifts 1 every 11.5 shifts 1 every 9 shifts
32 (every 15 minutes) 1 every 11.6 shifts 1 every 6.7 shifts 1 every 2.9 shifts 1 every 2.3 shifts
96 (every 5 minutes) 1 every 3.9 shifts 1 every 2.2 shifts 1.0 per shift 1.3 per shift
480 (every minute) 1.3 per shift 2.2 per shift 5.2 per shift 6.5 per shift
2,880 (every 10 seconds) 7.8 per shift 13 per shift 31 per shift 39 per shift

A manual plan of one or two subgroups an hour gives 8 to 16 points a shift, which is why the textbook rule sets were tolerable on paper. An inspector who records five parts every hour can live with all eight Nelson tests, because a false alarm arrives about once every nine shifts. Automatic gauges and controller tags change the arithmetic. The same rules applied to a reading every minute produce several false alarms per shift, and alarms that arrive that often invite acknowledgment without a look.

NIST notes that “some users add the WECO rules, but take them ‘less seriously’” when it comes to troubleshooting. That is a reasonable stance for an engineer reviewing a chart once a day. It is a poor one for an alarm that interrupts an operator, because an alarm that is routinely ignored also gets ignored when it is real.

Example (fictional). A fictional beverage bottler’s Line 2 reads capper torque from the filler’s controller on every cycle. On the first shift the filler capped 41,212 bottles, so the controller produced 41,212 torque readings. Plotted one by one with all eight Nelson tests, that is about 559 false alarms a shift even if every reading were independent, and roughly 111 with Rule 1 alone. Instead the quality engineer forms a subgroup of five consecutive readings every 5 minutes of run time: 75 subgroups in the shift’s 375 running minutes. Torque averages 16.5 in-lb with a within-subgroup standard deviation of 0.8 in-lb, so the X-bar chart’s limits sit at 16.5 ± 3 × 0.8 ÷ √5, which is 15.43 to 17.57 in-lb. With Rule 1 alone the chart would give one false alarm about every 4.9 shifts; with Rule 1 plus nine in a row, about one every 2.9 shifts; with the four WECO rules, about 0.8 per shift. The engineer picks Rule 1 plus nine in a row on the averages, Rule 1 only on the ranges, and writes both choices into the data dictionary. A shift of one standard error (0.36 in-lb in the average) is then caught in about 17 subgroups, roughly 85 minutes of running.

The rules assume independent data, fixed limits and sound subgroups

Supplementary rules are only as good as three assumptions behind them: consecutive points are independent, the limits are fixed, and each subgroup captures only common-cause variation. Break any of the three and the false-alarm figures above no longer apply.

Independence

Run rules and zone rules count patterns across consecutive points, so they assume each point tells you nothing about the next. Minitab’s documentation says so directly when it explains why only Test 1 runs on time-weighted charts: “The other seven tests assume that the points are independent.” Nelson’s caution about normality and independence, quoted above, makes the same point.

Data read automatically at a high rate often breaks this assumption. A temperature, a pressure or a torque read every few seconds is often autocorrelated: each reading resembles the one before it. The NIST handbook’s introduction to time series notes that data taken over time “may have an internal structure (such as autocorrelation, trend or seasonal variation) that should be accounted for.” Lag-1 autocorrelation is the correlation between each reading and the one before it: 0 means no carryover, values near 1 mean each reading mostly repeats the last.

Autocorrelation hurts in two ways. Moving ranges between neighboring readings are small compared with the real spread, so limits computed from the average moving range come out too tight. And the points wander in long runs, so run rules fire even when the limits are right. We extended the simulation above to readings with lag-1 autocorrelation of 0.3, 0.5 and 0.7:

Lag-1 autocorrelation Rule 1, limits from average moving range WECO rules, limits from average moving range WECO rules, limits from the true spread
0 (independent) 370 points per false alarm 92 92
0.3 85 25 43
0.5 34 13 27
0.7 15 7.8 18

Even modest autocorrelation of 0.3 cuts the interval between false alarms for Rule 1 from 370 points to about 85 when the limits come from moving ranges, which is how an individuals chart usually computes them. The run and zone rules suffer even with correct limits. Before you enable supplementary rules on automatic data, plot the readings in time order, compute the lag-1 correlation, and if it is clearly above zero, space the readings further apart, chart subgroup averages, or treat the series with the time-series methods in NIST section 6.4.

Fixed limits

SAS notes that “all eight tests were developed for use with fixed 3σ limits.” Software that recalculates limits every time a point arrives quietly changes the rules, because the limits chase the data. The NIST handbook advises that “changing the control limits frequently would negate any usefulness” and gives valid reasons to recalculate: at least 30 more data points with no known process change, a major process change, or a known, preventable event that changed how the process behaves. Freeze the limits, give them a version and a date, and apply the rules against that version.

Sound subgroups and a sound gauge

Zone rules read the spacing of points against sigma, so they are only meaningful when sigma is estimated from the right variation. A subgroup that mixes four mold cavities inflates the range and widens the limits, and the chart then trips Test 7 rather than catching shifts. A subgroup of five readings taken within one second may contain almost no variation, and then the limits are so tight that Rule 1 fires constantly. Our guide to rational subgrouping covers both failures. A gauge that cannot resolve the variation produces repeated values and zero ranges, which distorts sigma in the same way; check it with a gage R&R study before you start SPC.

Chart types with their own limits on rules

Not every rule suits every chart. Minitab offers only Tests 1 to 4 on R, S and moving range charts. For attribute charts, SAS recommends only Tests 1, 2, 3 and 4 for c, np, p and u charts, and says Test 2 “should not be used unless the process distribution is symmetric or nearly symmetric.” On a moving range chart, consecutive points share a reading by construction, so successive moving ranges are correlated, and run rules on that chart mislead.

Which rules to turn on, by chart and data source

The default that suits most charts is Rule 1 plus one run rule. Add zone rules only for a named characteristic where a small shift is costly and a named person will act within the hour. For high-rate automatic data, fix the data before you add rules.

Chart and data source Rules to alarm on Why
X-bar chart, manual subgroups once or twice an hour Rule 1 + 8 or 9 in a row; add Tests 5 and 6 for a characteristic where a small shift is costly Few points per shift, so extra rules cost little
R or S chart under an X-bar chart Rule 1 on the upper limit; optionally a run above the center line for a widening spread Minitab allows only Tests 1 to 4 on these charts, and spread statistics are skewed
Individuals chart, slow manual readings (batches, lab results) Rule 1 + 9 in a row; Test 3 where drift, such as tool wear or bath depletion, is the main risk Points arrive slowly, but check independence
Moving range chart Rule 1, or no alarm Successive moving ranges are correlated by construction
Subgroups built from automatic gauge data every 5 to 15 minutes Rule 1 + 9 in a row on averages; Rule 1 on ranges Dozens of points per shift; zone rules would alarm about once a shift
Every reading from a high-rate tag or gauge No run or zone rules; subgroup or space the readings first, or use an EWMA or CUSUM chart with its own limit Autocorrelation and point count make the textbook rules noisy
Attribute charts (p, np, c, u) Tests 1 to 4 at most; Test 2 only for a nearly symmetric distribution SAS documentation
New chart while limits are being set Tests 1, 2 and 7, as Minitab suggests Test 7 catches limits that are too wide; drop it once limits are fixed
Short-run or deviation-from-nominal chart Rule 1 + a run rule, read within each job See our article on SPC for short runs

Two of these rows need a word more. For high-rate data, the honest alternative to stacking rules is a chart designed for small shifts. The NIST handbook reports that analyzing ARLs for CUSUM charts shows they are better than Shewhart charts “when it is desired to detect shifts in the mean that are 2 sigma or less,” and that the EWMA procedure “can be made sensitive to a small or gradual drift in the process.” Both still assume the readings are independent, and Minitab runs only the beyond-limits test on them, so they replace the supplementary rules rather than adding to them.

The Phase I row reflects Minitab’s own suggestion: “you might try using Tests 1, 2, and 7 when you first establish the control limits based on your data.” Once the limits are established, “Test 7 is no longer needed.” This is a sound way to catch a mixed-stream subgroup design before you freeze limits that are too wide.

If a customer specifies the rules, the customer’s requirement wins. Automotive customers may refer to the AIAG SPC manuals; AIAG lists a joint AIAG & VDA SPC Manual as now available, and your quality team decides how it applies to your charts.

Pair every alarm with an out-of-control action plan

An alarm without a written response becomes noise. An out-of-control action plan (OCAP) is a short checklist or flowchart that tells the person who sees an alarm what to check first, what they may adjust, when to stop or contain product, and what to record. ASQ’s guidance on control charts puts the minimum this way: when a signal is identified, “mark it on the chart and investigate the cause. Document how you investigated, what you learned, the cause and how it was corrected.”

A practical OCAP has four parts:

  1. Trigger. The chart, the characteristic and the rule that fired, with the time.
  2. First checks, in order. Measurement first (gauge, fixture, data entry), then recent events (changeover, material lot, tool change, maintenance), then the process setting.
  3. Decision. Adjust, stop and contain, or continue with closer sampling, and who may decide each.
  4. Record. A cause code from a short list, the action taken, the person and the time.

Different rules point to different first checks. Nelson’s own notes, as reported by SAS, help here: Test 1 can mean a shift, a wider spread or a “single aberration in the process such as a mistake in calculation, an error in measurement, bad raw material, a breakdown of equipment.” Test 3 can come from “tool wear, depletion of chemical baths, deteriorating maintenance, improvement in skill.” Test 4 suggests “a systematic effect such as produced by two machines, spindles, operators or vendors used alternately.”

Rule that fired What it often means First checks
Test 1, point beyond a limit Large shift, wider spread, or one bad reading Remeasure the part; check the gauge and the entry; look for a stop, changeover or material change just before
Test 2, run on one side Small sustained shift What changed when the run started: lot, setup, offset, operator, ambient temperature
Test 3, steady trend Drift Tool wear, consumables, warm-up, a bath or coolant level
Test 4, alternation Two streams sampled in turn Which spindles, cavities, heads or gauges feed the chart
Tests 5 and 6, zone rules Moderate or small shift As Test 2, with the start of the pattern as the reference point
Tests 7 and 8, stratification Subgroup design problem How subgroups are formed; split the chart by stream

This is where machine data earns its place next to quality data. When the alarm time sits on the same timeline as the filler’s states, changeovers, stop reasons and material lots, the first check takes seconds instead of a search through logs. It is the reason our quality data service records measurements against the same line, shift and machine state as production. Where readings are still entered by hand, the check sheet design matters too; our article on digital check sheets covers the fields that make an entry traceable.

Example (fictional). On the fictional Line 2, the changeover to 1-liter bottles at 12:18 runs 38 minutes. After restart, two torque subgroups plot above the upper control limit of 17.57 in-lb, and Rule 1 fires on the second. The OCAP for capper torque sends the operator to three checks in order: confirm the torque reading against the handheld torque tester on five capped bottles, check the capper head setting for the new bottle size, and check the cap lot. The tester agrees with the controller, the head setting was left at the 500 ml value, and the operator corrects it. The operator records cause code “setting not changed at changeover,” the action, and the time on the shift’s check sheet. The next subgroup returns inside the limits. The weekly review adds the capper head setting to the changeover checklist.

Setting up the alarms in SPC software

Good alarm configuration is mostly about what happens after the rule fires. These settings decide whether operators trust the chart:

  1. Rules per chart, not per site. Store the rule set with each chart, including run lengths (8 or 9) and whether Tests 5 and 6 count one side or both. Two charts on the same line may need different sets.
  2. Limits with a version. Record the data period behind each set of limits, the date they were fixed and why they were last changed. Apply rules only against frozen limits.
  3. One alarm per episode. A run of 12 points above the center line satisfies the nine-point rule at points 9, 10, 11 and 12. Raise one alarm and hold the rest until it is acknowledged, or operators see four alarms for one event.
  4. Acknowledgment with a cause code. Require a short coded reason and the action taken. Free text can be optional. Coded reasons make the monthly review possible.
  5. Routing and escalation. Decide who receives which alarm, and what happens if nobody acknowledges it within an agreed time.
  6. Control limits are not specification limits. The NIST handbook draws the line clearly: control limits show whether the process is in statistical control, specification limits whether the product will function as intended. An out-of-specification reading is a separate alarm with its own containment steps.
  7. A change log. Every change to rules, limits or subgroup design goes into the data dictionary and change log, so an alarm count from March can be compared with one from June.
  8. Exportable history. Keep charts, limits, alarms and acknowledgments exportable in open formats, so the record survives a change of software. Our open data commitments describe how we handle this.

Review the alarms once a month. Count alarms per chart, the share closed as “no cause found,” and the time to acknowledge. A chart with many “no cause found” alarms has too many rules, limits that are too tight, or autocorrelated data. A chart that never alarms may have limits that are too wide.

Checklist before you switch on more rules

Use this list when you set up a new chart or review an old one:

  • Rule 1 is on for every chart, against frozen limits with a version.
  • One run rule is on (8 or 9 points), chosen deliberately and written down.
  • Zone rules (Tests 5 and 6) are on only for characteristics where a small shift is costly and someone acts within the hour.
  • Tests 7 and 8 are used while limits are being set, or as a periodic check of subgroup design, not as operator alarms.
  • You know how many points each chart plots per shift and the false alarms per shift that implies.
  • High-rate automatic data has been checked for autocorrelation before any run or zone rule is enabled.
  • The gauge has passed a measurement system check, and the subgroup design keeps streams apart.
  • Every rule that can alarm has an OCAP with first checks, decision rights and a cause-code list.
  • Alarms are deduplicated per episode and acknowledged with a coded reason.
  • The rule set, the limits and their history are in the data dictionary and can be exported.

Capability numbers come after stability, not before: once a chart has been in control against its frozen limits, the process capability calculator shows Cp and Cpk from the within-subgroup standard deviation. OpenGXT builds, hosts and maintains cloud software for manufacturers, including SPC charts whose rule sets, limits and alarm records are configured and documented with your quality team during the survey and configuration stages. If you want to test a rule set on one line first, you can plan a pilot line around the characteristics that matter most.