A fictional example, not a client: the Line 2 filler at a fictional beverage bottler, followed through all six stages from the first survey visit to the shift report and the pilot review.

For: Anyone who wants to see the work before planning a pilot line

A miniature green case-packing machine folding flat cardboard blanks into boxes beside a short stack of closed cases, with a tiny figure planting a small yellow flag next to it.

This page is a fictional example. The bottler, the line, the people and every number below are invented to show how OpenGXT works; they are not a client and not a result. The arithmetic is real, and the shift numbers match the default example in our OEE calculator, so you can check each figure yourself.

We follow one machine, the Line 2 filler at a fictional beverage bottler, through the six stages described on how we work: survey, connect, configure, pilot, roll out, and run and support.

The line and the question

Example (fictional). Line 2 fills and caps bottles and feeds a case packer. Shift results are written on a paper sheet, and the ERP books finished cases. The plant manager asks the same question every morning: “Why did Line 2 miss its count yesterday, and which stop cost the most?” The pilot covers first shift, 06:00 to 14:00.

Stage 1: Survey findings

Example (fictional). The survey report for Line 2 recorded:

  • The filler’s PLC has an OPC UA server. The plant’s controls engineer agreed to enable it with a read-only account. Machine state, good and reject counts, the active fault code, line speed and product temperature are available as tags without a program change.
  • The capper’s torque monitor has a Modbus TCP interface.
  • The line’s electricity meter supports Modbus TCP. The compressed-air flow meter on the line’s air drop supports Modbus RTU over a serial cable.
  • The filler’s main drive motor has no temperature sensor. The plant’s electrician can fit one and wire it to a small I/O module that the gateway reads.
  • Stops are written on the shift sheet in free text, and the same jam appears under several different names.
  • The changeover standard for a size change is 25 minutes. It is written on the changeover sheet but has never been compared with actual times.
  • The plant floor network is separated from the office network, and outbound traffic passes through a plant firewall.
  • Recommended pilot scope: the filler and capper, the two meters, and one shift report for first shift.

Signal inventory excerpt

Example (fictional). Ten rows from the Line 2 signal inventory. Stop reasons entered by operators on the shift board are one more row, recorded as manual entry.

Asset Signal Source address or node Protocol Unit and range Sample or trigger Used for
Line 2 filler Machine state ns=2;s=Filler.State OPC UA State code (mapped in the data dictionary) On change Run, idle and down time
Line 2 filler Good count ns=2;s=Filler.GoodCount OPC UA Bottles, running total Every 5 s Output, performance, quality
Line 2 filler Reject count ns=2;s=Filler.RejectCount OPC UA Bottles, running total Every 5 s Quality
Line 2 filler Active fault code ns=2;s=Filler.Fault OPC UA Code, 0 = no fault On change Stop reasons
Line 2 filler Line speed ns=2;s=Filler.Speed OPC UA Bottles per minute, 0 to 130 Every 1 s Slow running
Line 2 filler Product temperature at filler inlet ns=2;s=Filler.ProductTemp OPC UA °F, 0 to 100 Every 10 s Quality trend
Line 2 filler Main drive motor temperature I/O module, input 1 Hardwired I/O °F, 32 to 250 Every 10 s Maintenance alert
Line 2 capper Cap torque HR 40112 Modbus TCP N·m, 0 to 5 Every 1 s Torque trend and alarms
Line 2 Electricity, line meter HR 40001 Modbus TCP kWh, running total Every 1 min Energy per unit
Line 2 Compressed-air flow Unit 7, HR 40021 Modbus RTU scfm, 0 to 200 Every 10 s Air use while running and stopped

Stage 2: Connection plan

Example (fictional). The connection plan set out:

  • Gateway location: an existing enclosure next to the Line 2 control panel. The plant’s electrician provided power, and the IT/OT lead provided a network drop on the plant floor network.
  • Path out: one outbound connection from the gateway through the plant firewall to the hosted software, using MQTT with Sparkplug B over TLS. No inbound rule was added.
  • Controller access: OPC UA to the filler PLC with a read-only account created by the controls engineer, using the security policy and certificates the plant chose.
  • Other devices: Modbus TCP to the torque monitor and the electricity meter, Modbus RTU to the air flow meter, and the I/O module for the motor temperature.
  • Store and forward: the gateway buffers data while the internet link is down and sends it when the link returns.
  • Timing and rollback: first connection during a planned sanitation stop, with a rollback step for each change.

An excerpt from the per-signal test record:

Signal Checked against Result
Good count Filler HMI counter after a test run Match
Machine state Operator stopped and restarted the filler Down, then running, as seen at the machine
Active fault code Fault history on the filler HMI Codes and times match
Cap torque Torque monitor display First read 10 times too high; scaling corrected in the gateway mapping; retested, match
Electricity Meter display Match

Stage 3: Configured definitions and stop reasons

Before the first report, the supervisors and the plant manager settled the definitions. Each one went into the data dictionary.

Example (fictional). Definitions recorded in the Line 2 data dictionary:

  • Shift: 06:00 to 14:00, 480 minutes. Planned stop: break, 10:00 to 10:30.
  • Ideal rate: 120 bottles per minute. This example keeps one ideal rate for the whole shift to keep the arithmetic simple; in a real configuration each product has its own ideal rate.
  • States: the filler’s state codes map to running, idle (ready but starved or blocked), down (fault or changeover) and planned stop.
  • Threshold: a stop longer than 2 minutes asks the operator for a reason; shorter stops count as slow running.
  • OEE: availability × performance × quality, per the Lean Enterprise Institute definition.

The stop reasons, in two levels, written with the supervisors in their own words:

Category Reason How it is recorded
Equipment Bottle feed jam Fault code, confirmed by the operator
Equipment Capper fault Fault code, confirmed by the operator
Equipment Filler valve fault Fault code, confirmed by the operator
Material Caps not delivered Operator picks on the shift board
Material Bottles not delivered Operator picks on the shift board
Downstream Case packer blocked Operator picks on the shift board
Changeover Size change Operator picks; timed against the 25-minute standard
Changeover Flavor change Operator picks on the shift board
Quality Quality hold Operator picks on the shift board
Quality Fill level adjustment Operator picks on the shift board
People No operator available Operator or supervisor picks
Planned Break or sanitation From the shift schedule

Stage 4: Pilot, one shift on the timeline

Example (fictional). One first shift on Line 2, as the shift timeline showed it:

Time State What happened Minutes
06:00 to 07:41 Running Shift start 101
07:41 to 07:52 Down Bottle feed jam (Equipment, Bottle feed jam), fault code recorded 11
07:52 to 10:00 Running 128
10:00 to 10:30 Planned stop Break 30
10:30 to 10:41 Running 11
10:41 to 11:07 Idle Waiting on caps from the warehouse (Material, Caps not delivered) 26
11:07 to 12:18 Running 71
12:18 to 12:56 Down Changeover to 1-liter bottles (Changeover, Size change); standard 25 minutes, 13 over 38
12:56 to 14:00 Running Running 1-liter bottles 64

Running time adds up to 375 minutes. The three unplanned stops add up to 75 minutes.

The shift report

Example (fictional). The one-page report sent after the shift:

Measure Value
Shift length 480 min
Planned stops 30 min (break)
Planned production time 450 min
Unplanned stops 75 min (3 stops)
Run time 375 min
Total count 41,212 bottles
Good count 40,580 bottles (632 rejects)
Availability 375 ÷ 450 = 83.3%
Performance 41,212 ÷ (375 × 120) = 91.6%
Quality 40,580 ÷ 41,212 = 98.5%
OEE 75.1%

Where the time went: 75 minutes to stops, 31.6 minutes to slow running and 5.3 minutes to rejects, leaving 338.2 minutes of fully productive time out of 450 (75.1%).

Top stops: (1) changeover to 1-liter bottles, 38 minutes, 13 over the 25-minute standard; (2) waiting on caps from the warehouse, 26 minutes, idle because the filler was ready and the caps were not; (3) bottle feed jam, 11 minutes, with the fault code recorded.

Energy: the report lists the shift’s kWh from the Line 2 meter and energy per 1,000 good bottles (shift kWh ÷ 40.58), and compares compressed-air flow while running with flow during the stops. Energy figures are left out of this example; the energy per unit calculator shows the arithmetic.

The report leads with the changeover because it is the largest single loss and the only one with a standard to compare against. The caps wait shows as idle, not down: the filler was ready, so the fix belongs with the warehouse and planning, not with maintenance. To put a dollar figure on stops like these with your own rate and margin, use the downtime cost calculator.

What the pilot review checked

Example (fictional). The pilot plan listed six acceptance measures. The review checked each one against the pilot shifts:

Acceptance measure How it was checked Finding
Good and total counts agree with the filler’s HMI counter within 0.5% at the end of each shift Supervisor’s end-of-shift counter reading against the report Met on every pilot shift
States match what operators saw Supervisor’s shift log compared with the timeline, stop by stop Met; one stop relabeled, correction logged
Every stop over 2 minutes has a reason by the end of the shift Stop list in each report Met after two overlapping reasons were merged
The report reaches the named people after each shift Delivery record Met
No data is lost during an internet outage Uplink disconnected during a planned stop, then reconnected Buffered data arrived; no gap in the timeline
The report answers the plant manager’s question Review with the plant manager Met: the changeover and the caps wait named as the two largest losses

Decision: extend to Line 1 and Line 3 on the same data model and reason list.

Stages 5 and 6: Roll out, then run and support

Example (fictional). The rollout plan listed Line 1 and then Line 3, each with its own survey entries and connection tests, reusing the state map, threshold and reason list so the three lines could be compared. After go-live, the support log recorded requests such as adding “Cap chute blockage” as a reason at a supervisor’s request. Each monthly health summary listed data gaps and their causes, gateway status, changes made and open items.

Try it with your own line

When you know which line you would start with, plan a pilot line, or read how the four engagement types fit together.

Start with one line.

Tell us which line you want to understand and the question you ask after every shift. We reply with questions or a time to walk it with you.