Running a gage R&R study before you start SPC charts

The reader questionHow do we check that a gauge is good enough before its readings drive control charts and capability numbers?

Three tiny workers around a small wooden block on a bench, each measuring it with a different ruler.

Run a gage R&R study on each gauge before its readings set control limits or feed a Cpk. Measure at least 10 parts that span the process, with at least 3 operators, each part at least twice, in random order. Then compare the gauge’s variation with the process variation and with the tolerance. Under the AIAG guidelines, less than 10 percent of the process variation is acceptable, 10 to 30 percent may be acceptable depending on the application, and more than 30 percent needs improvement. Wheeler’s EMP classes judge the same data by how well a control chart can still detect shifts, and they are less strict.

The order matters more than the threshold. Settle the gauge first, then collect subgroups, then calculate control limits, then report capability. Every reading carries the gauge’s error with it, so a chart built on an unchecked gauge shows the gauge as much as the process. This article covers the study design, the two schools of acceptance, a worked example and what changes when gauges send data automatically. Subgroup design, alarm rules and short runs are covered in the sibling articles on rational subgrouping, Western Electric and Nelson rules and SPC for short runs.

Why the gauge study comes before control limits and Cpk

A gauge study comes first because control limits and capability indices are both calculated from the variation you observe, and the observed variation includes the gauge. If the gauge contributes a large share, the limits are too wide, capability looks worse than the process really is, and the chart misses shifts it should catch.

The arithmetic is simple. Variances add, standard deviations do not. As the SPC for Excel article on acceptance criteria for measurement systems analysis sets out, following Donald Wheeler, the total variance equals the product variance plus the measurement variance. So the observed standard deviation is the square root of the sum of the two squared standard deviations.

That one relationship has three practical effects:

  1. Control limits widen. Limits calculated from observed variation include the gauge’s variation, so a real shift in the process has to be larger before a point falls outside them.
  2. Capability is understated. Cp and Cpk divide by the observed standard deviation. A gauge with a large error makes a capable process look marginal, and can send engineers chasing process changes that are not needed.
  3. Some signals are not process signals at all. If one operator reads high and the next shift has a different operator, the chart can show a shift that lives entirely in the measurement.

The start-up sequence

For a new characteristic, the sequence that avoids these traps is:

  1. Check the gauge’s resolution against the tolerance and the process spread.
  2. Run the gage R&R study and act on its result.
  3. Collect subgroups under normal running, formed as the rational subgrouping article describes.
  4. Calculate trial control limits from those subgroups.
  5. Confirm the process is stable before trusting the limits.
  6. Only then calculate Cp and Cpk.

The NIST/SEMATECH e-Handbook describes control limits as “chosen so that almost all of the data points will fall within these limits as long as the process remains in-control.” Steps 1 and 2 make sure the “data points” describe the process, not the measuring.

What a gage R&R measures and what it leaves out

A gage R&R study measures two parts of measurement precision: repeatability and reproducibility. It does not measure whether the gauge reads true, whether it reads true across the range, or whether it stays the same over months. Those are separate studies.

Minitab’s documentation on interpreting a crossed gage R&R study gives short definitions. Repeatability is “the variability in measurements when the same operator measures the same part multiple times.” Reproducibility is “the variability in measurements when different operators measure the same part.” Total gage R&R is the sum of the two variance components.

The NIST/SEMATECH e-Handbook chapter on gauge R&R studies frames the subject more widely. Its list of basic issues is repeatability, reproducibility, stability and bias. Its other goals include testing resolution and linearity, estimating differences among gauges and operator biases, and feeding the findings into an uncertainty budget.

Calibration is not a gauge study

A calibration certificate is often taken as proof that a gauge is fit for SPC. The handbook’s page on analysis of bias explains why it is not: “Calibration relates output to ‘true value’ in an ideal environment. However, it may not assure that the gauge reacts properly in its working environment.” It names temperature, humidity, operator and wear as sources of bias at the point of use, and says “the gauge study is intended to uncover biases in the measurement process.” You need both: calibration for accuracy against a reference, and a gauge study for precision where the parts are actually measured.

MSA and gage R&R are not the same thing

Measurement systems analysis (MSA) is the whole discipline. A gage R&R is one study within it. AIAG’s manual on the subject is titled Measurement Systems Analysis, and its 4th edition is the one AIAG lists for sale as of November 2026. AIAG describes its one-day MSA course as taught “within the context of IATF 16949:2016.”

Study The question it answers When you need it
Resolution check Can the gauge see differences small enough to matter? Before any other study
Bias Does the average reading match a reference value? At calibration and after repairs
Linearity Is the bias the same across the measuring range? When parts span a wide range
Stability Does the gauge read the same reference the same way over time? Ongoing, with a reference part
Gage R&R How much do repeat readings and different operators vary? Before SPC and capability, and after changes
Attribute agreement Do inspectors agree with each other and with a standard? For pass or fail and visual checks

Check resolution before you run the study

Resolution is the smallest change the measurement system can detect and indicate, and it is the first thing to check. A gauge that cannot see the differences between your parts makes every later number meaningless.

The handbook’s page on resolution takes its definition from the AIAG MSA manual: “the ability of the measurement system to detect and faithfully indicate small changes in the characteristic of the measurement result.” It adds two warnings worth printing above every inspection bench. First: “The number of digits displayed does not indicate the resolution of the instrument.” Second: “No useful information can be gained from a study on a gauge with poor resolution relative to measurement needs.”

The same page notes that a manufacturer’s stated resolution “should be checked in the laboratory under actual conditions of measurement.” It describes a practical method: measure pairs of reference artifacts with known values, from far apart to close together, until a pair repeatedly gives the same result. The difference between that pair estimates the resolution.

Resolution in an automated data path

When readings travel from a gauge to software, resolution can be lost on the way. A gauge that resolves 0.001 mm may feed a PLC that stores the value as a whole number of hundredths, or a spreadsheet column formatted to two decimals. The record then looks precise, with a fixed number of digits, while the steps between values are ten times coarser than the gauge. Check resolution where the data is used, not only at the gauge’s display.

The number of distinct categories

Gage R&R software reports a second resolution check: the number of distinct categories (ndc). Minitab’s methods page gives the formula as the standard deviation for parts divided by the standard deviation for the gauge, multiplied by 1.41, then truncated. It describes ndc as “the number of groups within your process data that your measurement system can discern.” In its guide to the gage R&R output, Minitab reports that the AIAG manual treats 5 or more categories as acceptable. It adds its own note that below 2, the measurement system “is of no value for controlling the process.”

Designing the study: parts, operators and trials

A good gage R&R study uses enough parts to represent the process, enough operators to represent the people who measure, and enough repeats to estimate repeatability, all measured in random order so that drift and memory do not bias the result. The most common design is crossed: every operator measures every part.

Minitab’s data considerations for a crossed gage R&R study set out the minimums:

  • At least 10 parts. If you have no historical estimate of process variation, Minitab suggests “using 15 to 35 parts should result in a much better estimate than if you used 10 parts.”
  • Parts that span the process. Select from the whole range: “do not measure consecutive parts, parts from a single shift or a single production line, or parts from the reject pile.”
  • At least 3 operators, and “for the best results, include 3 to 5 operators,” chosen to represent everyone who uses the gauge, not the best or the worst.
  • At least 2 measurements of each part by each operator, in random order within each replicate.

The NIST/SEMATECH handbook’s design considerations agree in substance and add cases the shop floor meets. Use more than two artifacts. If only a few operators know the gauge, include all of them; if the study represents a large pool, choose more than two at random. “If there is only one operator for the gauge type, that operator should make measurements on K (K > 2) days.” If the plant has several gauges of the same type, include all of them when they are few, or a random sample of more than three when they are many.

A procedure you can run on one shift

  1. Pick the characteristic and the gauge you plan to chart, and confirm the gauge is calibrated and its resolution is adequate.
  2. Select the parts across the process range, and number them where operators cannot see the numbers.
  3. Choose the operators who actually use the gauge, across shifts.
  4. Generate a random run order for each replicate, so no operator measures the parts in the same sequence twice.
  5. Measure, with each operator working alone and not seeing others’ results.
  6. Record each reading with part, operator, trial, gauge ID and time, directly into the analysis file or form, not on scrap paper.
  7. Repeat for the second and any further trials.
  8. Analyze with the ANOVA method, and look at the graphs before the percentages.
  9. Decide and write it down: accept, accept with conditions, or improve and re-study.

Short studies and long studies

A study run in one afternoon captures short-term precision and operator differences. It does not capture what happens over days and months. The handbook’s page on time-related sources of variability separates three levels: measurements over a short time, over days, and over runs months apart. It says “Two levels should be sufficient for characterizing most measurement systems,” and three are recommended “where sources of error are not well understood.” The ongoing check described later in this article covers the longer levels at low cost.

Reading the results: four numbers and their denominators

A gage R&R report gives four headline figures, and each compares the gauge with something different. %Contribution and %Study Var compare it with the total variation in the study. %Tolerance compares it with the specification width. The number of distinct categories compares the part spread with the gauge spread. Knowing the denominator tells you which number answers your question.

Minitab’s methods for the gage R&R table define them:

Figure How it is calculated Adds to 100? Use it for
%Contribution Variance component divided by total variance, times 100 Yes Seeing where variation comes from
%Study Var Standard deviation times 6, divided by total study variation, times 100 No Comparing gauge spread with process spread
%Tolerance Study variation divided by (upper minus lower specification), times 100 No Judging part acceptance near the limits
ndc Part standard deviation divided by gauge standard deviation, times 1.41, truncated Not a percentage Checking the gauge can separate parts

Two details trip up readers. First, Minitab notes that “%Study Var is the square root of the %Contribution,” so the AIAG 10 percent study variation line equals 1 percent of contribution, and 30 percent equals 9 percent. Second, the multiplier is 6 by default. Minitab explains that a multiplier of 5.15 covers 99 percent of a normal distribution instead of about 99.73 percent, so check which one a report used before comparing it with another.

Small studies give rough estimates

A study of 10 parts, 3 operators and 2 trials produces 60 readings, but far fewer independent pieces of information about each variance component. Reproducibility rests on only three operators. The handbook’s page on analysis of repeatability warns that a standard deviation from a handful of repeats “is not a reliable estimate of the precision of the gauge,” and recommends pooling over days, runs and check standards.

Expect two quirks in the output. Minitab’s documentation states that a negative variance component is reported as zero, and that its ANOVA drops the operator by part interaction when that term’s p-value is 0.05 or higher. Neither is an error. Both are reminders that a result near a threshold, such as 28 or 32 percent, does not settle which side of 30 the gauge really sits on.

Pick the denominator that matches the use

If the readings will drive control charts, you care about the process: use %Study Var, or %Process when you enter a historical process standard deviation. If the readings decide whether parts ship, you care about the tolerance: use %Tolerance. A gauge can pass one test and fail the other, and the worked example below does exactly that.

Look at the graphs before the percentages

Minitab’s guidance on the graphs is a useful checklist. The range chart by operator should be in control, showing consistent repeat readings. The X-bar chart by operator should show “most points fall beyond the control limits,” because the study parts should differ more than the gauge does. Lines on the operator-by-part interaction graph that cross mean “an operator’s ability to measure a part consistently depends on which part is being measured.” A percentage can hide all three.

Two schools of acceptance: AIAG guidelines and Wheeler’s classes

There are two widely used ways to judge a gage R&R result, and they disagree. The AIAG guidelines classify by the share of study variation taken by the gauge. Donald Wheeler’s Evaluating the Measurement Process (EMP) approach classifies by the intraclass correlation, which describes how much a control chart’s signals are weakened. For the same data, the EMP verdict is usually kinder.

Where the 10 and 30 percent figures come from

The AIAG figures come from the AIAG Measurement Systems Analysis Reference Manual, 4th edition (2010), which is sold rather than published free. The figures quoted here are as reported by two clearly attributed sources. Minitab’s page Is my measurement system acceptable? cites the manual and gives:

  • Less than 10 percent of process variation: “The measurement system is acceptable.”
  • Between 10 and 30 percent: acceptable “depending on the application, the cost of the measurement device, cost of repair, or other factors.”
  • Greater than 30 percent: “not acceptable and should be improved.”

The same page gives the variance-component version (under 1 percent, 1 to 9 percent, over 9 percent) and states that the number of distinct categories “should be greater than or equal to 5.” The SPC for Excel article quotes a caution from page 78 of the same manual: “the use of the GRR guidelines as threshold criteria alone is NOT an acceptable practice for determining the acceptability of a measurement system.” The manual itself, in other words, does not intend the bands as a pass or fail switch.

Wheeler’s four classes

Minitab’s page also sets out Wheeler’s classes, citing EMP III (2006). They use the intraclass correlation: the share of total variance that comes from the parts. First class monitors run from 0.80 to 1.00, second class from 0.50 to 0.80, third class from 0.20 to 0.50 and fourth class below 0.20. For each class, the table gives the attenuation of process signals and the probability that a control chart warns of a large shift in the process mean. Minitab’s summary: “The classifications for Wheeler’s EMP studies are less strict than the classifications for gage R&R studies that follow the AIAG methodology.”

SPC for Excel goes further. It argues that the AIAG percentages are ratios of standard deviations, which “are not additive,” so they are presented like shares of a whole when they are not. Its conclusion is blunt: “you should NEVER use the acceptance criteria listed above.” That is one publisher’s view, and many automotive customers still require the AIAG figures. But the arithmetic behind it is not in dispute.

AIAG guidelines Wheeler EMP classes OK Conditional Not acceptable, improve First class Second class Third 4th 0 10 30 45 71 89 100 Before: 39.9% After: 21.2% Gauge standard deviation as a percent of total study variation (%Study Var)
Band edges from Minitab Support, "Is my measurement system acceptable?" (AIAG MSA Reference Manual, 4th edition, 2010, and Wheeler, EMP III, 2006, converted by Minitab to approximate percent of process variation), checked November 2026. Markers show this article's fictional bore gauge example.

How to choose between them

Use the criteria your customer requires for the report, and use the question you are asking for the decision. If an automotive customer’s PPAP requirements name the AIAG figures, report them. For the internal decision about whether a gauge can run a control chart, the EMP class tells you how much the chart will be weakened and whether you need extra detection rules. For the decision about whether parts near a limit can be accepted on one reading, look at %Tolerance. Reporting all three takes no extra measuring, because they come from the same data.

A worked example: one bore, two verdicts

The example below runs a full study and shows how the same data can be “not acceptable” under one reading, borderline under another and “first class” under a third. It uses the same specification as the default example in the process capability calculator, so you can follow the capability effect in the next chapter.

Example (fictional). A fictional machine shop plans to chart a 10.00 mm bore on a turned part, with limits of 9.95 and 10.05 mm (a tolerance of 0.10 mm). The bore gauge reads to 0.001 mm. The team selects 10 parts from a week of production across both shifts, and 3 operators measure each part twice in random order: 60 readings. The ANOVA results are:

Source Standard deviation (mm) %Contribution %Study Var %Tolerance
Repeatability 0.0040 10.2 31.9 24.0
Reproducibility 0.0030 5.7 23.9 18.0
Total gage R&R 0.0050 15.9 39.9 30.0
Part to part 0.0115 84.1 91.7
Total variation 0.0125 100.0 100.0

The number of distinct categories is 1.41 x 0.0115 / 0.0050 = 3.2, truncated to 3. The intraclass correlation is 0.0115 squared divided by 0.0125 squared, or 0.84.

Read against each standard, the same study says:

  • AIAG, study variation: 39.9 percent is above 30, so “not acceptable and should be improved.”
  • AIAG, tolerance: 30.0 percent sits exactly on the edge between “conditional” and “not acceptable.”
  • Number of distinct categories: 3 is below the 5 that the AIAG manual treats as acceptable, as reported by Minitab.
  • Wheeler EMP: an intraclass correlation of 0.84 is a first class monitor, with attenuation of process signals of less than 11 percent according to Minitab’s table.

What the shop decides

The verdicts do not contradict each other. They answer different questions. The chart will work: a first class monitor detects large shifts reliably with the basic limit rule. But parts measured close to a limit carry real doubt, and the operators disagree more than they should, since reproducibility is more than half the size of repeatability.

Example (fictional). The shop starts collecting subgroups for the control chart and fixes the measurement in parallel. It writes a work instruction for how deep to insert the gauge and how many readings to take while rocking it, and adds a setting ring check at the start of each shift. Until then, any part read within 0.010 mm of a limit gets a second reading on the coordinate measuring machine. A re-study with the same parts gives repeatability of 0.0020 mm and reproducibility of 0.0015 mm, a total gage R&R of 0.0025 mm. That moves %Study Var to 21.2 percent, %Tolerance to 15.0 percent, ndc to 6 and the intraclass correlation to 0.95. The control limits are then calculated from subgroups measured after the fix.

What measurement error does to control charts and Cpk

Measurement error inflates the standard deviation used for both control limits and capability. The effect is modest for a good gauge and large for a poor one, and it grows as the process improves, because the gauge’s share of the total rises. You can estimate it directly from the gage R&R result.

Continue the fictional example. The process capability calculator’s default inputs are the same bore: limits of 9.95 and 10.05 mm, a mean of 10.012 mm and a within-subgroup standard deviation of 0.012 mm. Those give a Cp of 1.39 and a Cpk of 1.06. Suppose that 0.012 mm was measured with the original gauge, whose gage R&R standard deviation was 0.005 mm. If the gauge error is random and rides along in every reading, the process itself varies by the square root of 0.012 squared minus 0.005 squared, which is 0.0109 mm.

Standard deviation used Value (mm) Cp Cpk
Observed with the original gauge 0.0120 1.39 1.06
Observed after the gauge fix 0.0112 1.49 1.13
Process alone (gauge error removed) 0.0109 1.53 1.16

The improved gauge recovers most of the difference without touching the machine. If the customer’s requirement sits between 1.06 and 1.16, the gauge decides whether the part passes the capability review. That is a reason to run the study before reporting Cpk, not after a disappointing number.

This calculation is a simplification. Reproducibility, the operator effect, may sit partly between subgroups rather than within them, and then it widens the overall spread more than the within-subgroup spread. Treat the figures as an estimate of direction and size, not a correction to apply to the report.

The effect on the chart

On the chart, limits calculated with the original gauge are about 10 percent wider than limits for the process alone, because 0.0120 divided by 0.0109 is 1.10. A process shift has to be about 10 percent larger to produce the same signal. Wheeler’s classes describe the same effect as attenuation of process signals: less than 11 percent for a first class monitor and 29 to 55 percent for a third class one, per Minitab’s table.

Minitab notes that for third class measurement systems “the typical analysis adds tests to the control chart to increase the probability to detect a shift in the process mean.” That links the gauge result to the choice of alarm rules, which the Western Electric and Nelson rules article covers. The chart rules and the gauge class should be decided together.

Improvement makes the gauge look worse

When a process improves, its variance falls and the gauge’s share of the total rises, even though the gauge has not changed. SPC for Excel’s table of Wheeler’s classes includes a column on each class’s ability to track process improvements for this reason. Plan a re-study whenever a project significantly reduces process variation.

When gauges send data automatically

When gauges send readings straight to software, the operator often drops out of the measurement, and other sources of variation take the operator’s place. The gauge study, the gauge’s identity and its calibration status then need to live in the data, not in a binder. This is where an automated SPC system either earns trust or quietly charts a faulty gauge.

Replace “operator” with what actually varies

For an in-process probe, a vision system or an air gauge on a fixture, the reproducibility factor is no longer people. It might be the fixture, the station, the gauge head or the part’s temperature when it reaches the gauge. Minitab’s expanded gage R&R study is meant for these designs: more than two factors, fixed factors, a mix of crossed and nested factors, or an unbalanced design. The handbook’s list of bias sources includes “differences among gauges” and “differences among geometries,” which covers several gauges of one type and several fixture positions.

Put the gauge in every record

For automated SPC to be traceable, each reading needs these fields alongside the value, the characteristic and the time:

  • Gauge ID, for the physical instrument, not just the gauge type.
  • Fixture or station, where several exist.
  • Calibration status at the time of reading: due date and whether the gauge was in date.
  • The gauge study that covers it: study ID, date and result.
  • Resolution as delivered to the software, after any scaling in the PLC or gateway.

With those fields, a gauge found out of calibration on Friday can be traced to every reading it produced since its last good check. Without them, the only safe answer is to distrust every chart that might have used it.

If you are connecting gauges and machine controllers to software, list each gauge output in the same signal inventory as the machine signals, with its units, range and resolution. The machine connectivity page describes how that inventory and its per-signal test record are built.

Run a check standard every shift

The handbook builds its gauge studies around check standards: reference items “of a type that are typically measured with the gauges under study.” An automated system makes the longer-term version cheap. Measure the same reference part at the start of each shift, chart those readings like any other characteristic, and you have an ongoing stability and day-to-day check that covers the second and third time levels the handbook describes.

Triggers for repeating the study

Write the re-study triggers into the procedure and, where possible, into the software as reminders:

  • The gauge is repaired, rebuilt or replaced.
  • The gauge or fixture is moved to a different machine or environment.
  • The gauge software, probe or scaling in the data path changes.
  • New operators or a new shift start using a manual gauge.
  • The process improves enough to change the gauge’s share of variation.
  • The check standard chart signals.
  • A set interval passes, chosen by quality and recorded in the gauge register.

For high-mix shops, where one gauge serves many part numbers, the study should cover the size range the gauge will see. The SPC for short runs article explains how charts combine part numbers, and the machine shop overview describes how setups and first articles fit with machine data.

Attribute gauges, visual checks and destructive tests

Not every measurement fits a crossed gage R&R. Pass or fail gauges, visual inspection and destructive tests each need a different study design, though the purpose is the same: know how much of what you record comes from the measuring.

Pass or fail and visual checks

Minitab’s attribute agreement analysis assesses “whether appraisers are consistent with themselves, with one another, and with known standards.” It handles binary ratings, ordinal scales and nominal categories. For a binary gauge such as a go and no-go plug, the same page points to an attribute gage study instead. In both cases, include parts close to the limits, where disagreement lives, rather than only clear passes and clear fails.

Destructive and one-shot tests

When a test destroys the part, no operator can measure the same part twice, and the crossed design breaks. Minitab’s nested gage R&R study is meant for the case where “every operator cannot measure all parts,” for example, each operator measuring their own set of parts. A practical precaution is to give each operator parts that are as alike as possible, such as consecutive parts from one batch, so that part differences do not pass for measurement error.

A start-up checklist before the first control chart

Use the table to turn a gage R&R result into an action, then work through the checklist for each characteristic you plan to chart. The aim is to start SPC with a gauge whose contribution you know, recorded in a way that lets you trace it later.

What the study showsWhat it usually points toBefore SPC starts
ndc below 2, or a fourth class monitorThe gauge cannot separate partsDo not chart; change the gauge or the measuring method
Repeatability is the largest part of gage R&RThe instrument, fixture, contact force, temperature or resolutionFix the equipment or method, then re-study
Reproducibility is the largest partOperators differ in technique, setup or readingWrite a work instruction, add a fixture or setting check, re-study
Crossing lines on the operator by part graphSome operators struggle with some parts, often at the extremesFind the parts and the technique; train or fixture
High %Study Var but low %ToleranceStudy parts too alike, or a very capable processCheck part selection; use a historical process standard deviation
Low %Study Var but high %ToleranceTight tolerance relative to the gaugeFine for charting; re-measure parts read close to a limit
Low on every measure, ndc of 5 or moreA gauge fit for SPC on this characteristicCollect subgroups and calculate limits
Decision table compiled for this article from the result interpretation in Minitab Support (crossed gage R&R key results and data considerations) and the NIST/SEMATECH e-Handbook section 2.4, checked November 2026. Actions are recommendations, not a published standard.

Checklist for each characteristic

  1. Name the gauge by ID, confirm its calibration is in date, and record its resolution as delivered to the software.
  2. Check resolution against the tolerance and the process spread, using the handbook’s warning that displayed digits are not resolution.
  3. Design the study: at least 10 parts across the range (15 to 35 if you lack a historical standard deviation), 3 to 5 representative operators or the factors that replace them, and at least 2 trials in random order.
  4. Run and analyze it with ANOVA, reading the graphs first.
  5. Report the figures your customer requires, and record the EMP class and %Tolerance alongside them.
  6. Decide and record the decision, any conditions and the re-study triggers.
  7. Set up the ongoing check with a reference part each shift.
  8. Collect subgroups, calculate limits and confirm stability before reporting Cp and Cpk.
  9. Re-study when a trigger fires, and recalculate limits if the gauge changes materially.

OpenGXT builds, hosts and maintains cloud software for manufacturers. Its quality data service records measurements against the same line, shift and machine data as production, and writes chart choices and calculation methods into the data dictionary before the first chart is drawn. For the capability arithmetic after the gauge is settled, use the process capability calculator, and if you want to plan SPC on one line, you can contact the team.

Working on this at your plant?

If this article describes a problem on one of your lines, tell us about it. We start with one line, its signals and the question you ask after every shift.