Go-live readiness checklist for plant floor software
Sixteen items to confirm before the old way of recording stops and the new software becomes the record for a line.
For: Plant project owners, production supervisors, maintenance and IT/OT leads

Checklist
Go-live is the day the software becomes the record. The shift report goes to the plant manager, supervisors stop filling in the paper downtime sheet, and decisions start to rest on the new numbers. Going live too early is costly in a specific way: the first time a supervisor finds a count that is plainly wrong, trust in every other number drops with it. This checklist is the last look before that day.
When to use it
Use it at the end of the Pilot stage, as part of the pilot review against the acceptance measures agreed in the pilot plan, and again for each line in the Roll out stage. The project owner on the plant side holds the list and works through it with OpenGXT, the supervisors from each shift, maintenance and IT.
Why each group matters
Data
This group asks whether the numbers deserve to be trusted. Every tag in the signal inventory should read a value at its expected rate, and machine states should match what operators saw for a full shift, not a ten-minute test.
Count reconciliation is the item to give the most time. Agree the tolerance in the pilot plan, before anyone sees the numbers, then compare with the line counter or the ERP production report. Differences often have ordinary causes, such as rejects counted at a different station or cases booked at the end of the shift, but each one is explained before go-live, not after. Shift calendars and breaks sound administrative, yet a missing break turns planned time into downtime and pulls OEE down for a reason nobody on the line recognizes.
People
Train every shift at the line, including nights and weekends, and make sure supervisors can correct a mislabeled stop, because the first weeks will contain some. A named super-user on each shift answers most questions before they become support requests.
Operations
This group covers what people notice on day one: a screen that cannot be read from the operator position, a shift report that arrives after the morning meeting, an alert that goes to someone who left last year. Test each alert all the way to the phones and inboxes of the people who will receive it, not the project team’s.
Safety net
This group proves that a bad day is survivable. Restart the application once on purpose and check that the gateway sends the readings it buffered in the meantime; restart the gateway and confirm it reconnects to every machine. Keep the previous way of recording downtime running in parallel for a period agreed in advance, so any difference can be traced before the old method stops.
Example (fictional). Before Line 2 at a fictional beverage bottler goes live, the team checks one full first shift, 06:00 to 14:00, against the supervisor’s notes. The software shows the break from 10:00 to 10:30 as planned time, because the shift calendar is configured, and three unplanned stops: the bottle feed jam at 07:41 (11 minutes), waiting on caps at 10:41 (26 minutes) and the changeover to 1-liter bottles at 12:18 (38 minutes). All three match what the operators recorded. The count of 41,212 bottles, 40,580 of them good, is compared with the filler’s own counter and the ERP production report against the tolerance written in the pilot plan. With the data group ticked, the open items are a training session for the night shift and the restore test.
Acting on what is not ticked
Not every open item blocks go-live, but decide which ones do before you start. Data items are blockers: going live on numbers that do not reconcile spends trust you will need later. Some people and operations items can be dated follow-ups, such as a refresher session for a shift that was short-staffed during training. Record each decision with an owner and a date in the downloaded CSV, and keep it with the pilot review.
Common mistakes
- Validating on the day shift only.
- Reconciling counts for one good shift and calling it done.
- Ending the parallel run before the differences are explained.
- Testing alerts with the project team instead of the people who will receive them.
- Never restarting anything until the first real outage.
After go-live
Go-live starts the Run and support stage: monitoring, updates, changes and a monthly health summary under support and maintenance. The operator quick guides and the administrator runbook come from documentation and onboarding. For the whole sequence from survey to go-live, see how we work, compare engagement types, or follow one fictional line in the example project.