Choosing a pilot line that can scale past the pilot

The reader questionWhich line or area should a plant pick for its first monitoring pilot, and how do we decide whether to scale it?

A tiny gardener planting one seedling in a taped plot of soil on an empty concrete floor, with more empty taped plots beside it.

Pick the line where a known, costed problem shows up every week, whose machines and controllers look like the rest of the plant, that has a named owner on every shift, and where some existing record (paper shift sheets, machine counters, ERP output) lets you check the new data. Before anything is connected, write down what success means, how many shifts and production events the pilot will cover, and who decides. Then end with a go, change or stop review against those written measures. A pilot chosen as a showcase on the newest line tends to prove only that the newest line can be connected, which is how plants end up in pilot purgatory.

“Pilot purgatory” is the common name for a digital project that keeps running as a pilot without anyone deciding to scale it or stop it. Most of what ranks for the term explains why that happens. This article covers the decisions that prevent it: the five tests for a candidate line, how to score candidates, the measures to write before go-live, how long to run, and the review at the end.

A disclosure first. OpenGXT builds, hosts and maintains cloud software for manufacturers and distribution centers, and every engagement starts with a pilot line, so we have an interest in pilots that end in a clear decision. The method below works with any vendor or with an in-house team.

Why pilots get stuck in pilot purgatory

Pilots stall when nobody can say, at the end, whether they worked. That traces back to the choice of line and to measures that were never written down. The technology can work and the pilot still stall, because there is nothing to decide against.

The public sources describe the pattern from different angles:

  • IndustryWeek (2019). In Getting Your IIoT Project out of Pilot Purgatory, Stephan Liozu argues for a formal ranking of pilot candidates “based on pre-established criteria: speed, quick win, time of gestation, scalability, readiness to invest, strategic alignment,” and for a pilot playbook that “defines pilot success KPIs, financial and resource commitments, and scaling plans.” His advice is written for manufacturers piloting IIoT offers with customers, but the logic carries to a plant choosing its own first line. He also warns that uncertain standards raise “the level of uncertainty in pilot projects and reinforces the need for long pilots.”
  • World Economic Forum. The Forum’s Global Lighthouse Network page says the majority of organizations in manufacturing and supply chains are struggling to capture the gains of technology “through scaling technology adoption throughout their operations.” In June 2026 the Forum added 15 sites, bringing the network to 238. Those are large, well-funded sites; the lesson for a small plant is that scaling, not piloting, is the hard part.
  • A small-plant study (2024). Kamble and colleagues at Aston University describe digitalizing one hand press at a UK springs and pressings maker, presented at the LoDiSA 2024 conference. Direct hardware cost was £92.80, with £10,400 for research and staff time. The authors list the limits plainly: the microcontroller’s longevity is “a concern,” missing documentation “makes long-term maintenance challenging,” and the database structure “needs to be redefined” when more sensors are added.

Read together, they suggest four ways pilots stall. This is our editorial reading of the sources, not a survey finding:

Stall pattern What it looks like Test that prevents it
No costed problem The data is interesting, but no loss is big enough to justify the next line Test 1
Unrepresentative equipment The pilot line’s controllers appear nowhere else, so the next line is a new project Test 2
No owner off day shift Nights and weekends never enter reasons, and the report is half empty Test 3
No baseline and no written measures Nobody can say whether the new numbers are right, or better Tests 4 and 5, and the measures written before go-live

The fix starts with being clear about what a pilot is for. A monitoring pilot answers one question: does this work on our equipment, with our people, well enough to extend? Everything in the plan should serve that question. A pilot that also tries to prove a return on investment, train the whole plant and test three vendors at once usually answers none of them.

The five tests for a candidate pilot line

A good pilot line passes five tests: a known and costed problem, equipment that represents the plant, a named owner on every shift, existing data to compare against, and access you can actually get. A line that fails two of them should not be the first one, however visible it is.

Test What to check Evidence to collect Red flag
1. A known, costed problem A loss people already argue about, with a dollar figure per shift or week Downtime logs, scrap reports, overtime records, a first cost estimate “Let’s see what the data shows”
2. Representative equipment Controller families, protocols and machine ages that recur across the plant A first signal inventory of the line and a count of the same types elsewhere The newest line, where everything already speaks OPC UA, or a one-off machine
3. An owner on every shift A named person per shift, nights and weekends included, who will look at the report A roster with names, agreed by their supervisors Owners only on day shift
4. Data to compare against An existing count, log or report that covers the same shifts Paper shift sheets, HMI counters, ERP production postings No independent record at all
5. Access you can get Planned stops, a controls engineer’s time, an IT/OT approval path, a network drop Production calendar, names, a first network sketch The line never stops, or nobody can approve a firewall rule

Test 1: a known, costed problem

Start where the plant already loses money it can name. A changeover that runs long every week, a filler that jams, a compressor that trips on hot days. The pilot’s job is to show the size of that loss and its causes clearly enough to act, which gives the review a decision to make.

Test 2: equipment that represents the plant

Each new machine type brings its own connection questions, so the pilot should teach you the connections you will repeat. If most lines run the same PLC family with a few Modbus meters, the pilot line should too. The chapter on representative equipment below shows how to check.

Test 3: an owner on every shift

Data that nobody reads on second and third shift does not get reasons entered, and in a three-shift plant a report built on day shift alone describes a third of the running hours. Name an owner for each shift before go-live, and make sure their supervisor agrees to the time it takes.

Test 4: data to compare against

The first question at any review is whether the new numbers are right. A paper count, a machine counter or an ERP posting for the same shifts is how you answer it. Without one, the pilot spends its time arguing about the data instead of the line.

Test 5: access you can actually get

The gateway goes in during a planned stop, the controls engineer confirms what can be read, and someone approves the network path out. A line that never stops, or a plant where no one can approve a firewall rule, will spend the pilot waiting. The network design for that path is in connecting plant equipment to the cloud with outbound-only links.

Line, cell or area

The pilot unit does not have to be a production line. It should be the smallest unit that contains the costed problem and the equipment you want to learn from. Three shapes are common:

Pilot unit Example Strength Watch for
A line A filler, capper and case packer that feed each other Shows how one machine’s stops starve or block the next Many machine types at once
A cell of similar machines Four CNC mills run by two operators One connection method, repeated; easy to compare machines Losses often sit in setups and programs, not in the machines
An area or utility Compressors and meters, a cold room, a sortation zone Energy and runtime data with few operators involved Fewer people own the report, so test 3 needs care

Choose the shape that matches where the money is lost. A plant whose biggest argument is about compressed air does better piloting the compressor room than a line.

When the obvious candidate fails a test

Sometimes the line with the biggest problem fails one test. Before switching lines, ask whether the failure can be fixed before go-live. A missing night-shift owner can usually be named; a line that never stops can often be connected at the next planned outage; a missing baseline can be started with a paper count a few weeks ahead. A line whose equipment matches nothing else in the plant cannot be fixed, and neither can a problem nobody can cost. Those two failures should move the pilot elsewhere.

Costing the problem before you choose

Put a dollar figure on the problem before choosing the line, because the review at the end will ask whether the problem is worth fixing on more lines. A rough, defensible figure is enough; the pilot will refine it.

The arithmetic is simple. Lost output is minutes lost times the rate the line would have run. Its cost is the contribution margin on the units not recovered, plus idle labor during the stop, plus overtime to make the output up later. The downtime cost calculator does this with your own figures.

Its default inputs are a fictional example: 14 hours of unplanned downtime in a period, a production rate of 2,700 units an hour, a contribution margin of $0.42 a unit, 5 people idle at a loaded labor rate of $34 an hour, 40% of lost output made up later at a 50% overtime premium. With those inputs it returns $13,334 for the period, or $952 per downtime hour. The calculator notes that this is conservative: it leaves out scrap at restart, expedited freight, missed orders and repair parts.

Example (fictional). A fictional beverage bottler is choosing its first line. Before any pilot, it knows Line 2’s losses only from the paper shift sheet, where stops are written in free text, but two of them come up at every morning meeting: waiting on caps from the warehouse, and size changeovers that overrun their 25-minute standard. The team puts the plant’s own margin and labor figures into the downtime cost calculator and brings a first cost per shift to the selection meeting. The pilot later measured one first shift, 06:00 to 14:00 with a planned 30-minute break: the filler lost 75 minutes to unplanned stops, including a bottle feed jam at 07:41 (11 minutes), waiting on caps at 10:41 (26 minutes) and a changeover to 1-liter bottles at 12:18 that took 38 minutes, 13 over standard. OEE for that shift was 75.1%. The full shift is worked through on the example line page.

Two cautions keep the figure honest. Use contribution margin, not selling price, because materials not consumed are not lost. And cost only the minutes that are really lost: output that overtime recovers costs the overtime premium, not the margin.

Then put the problem’s cost next to two other figures: what the pilot will cost, and what each further line would cost to connect and support. The first tells you whether the pilot is worth running. The second, which the pilot itself should sharpen, tells you whether the rollout will be. A loss of a few hundred dollars a month on a line that is expensive to connect is a poor first pilot, however tidy the data would look.

Representative equipment: making the connection lessons transfer

Choose a pilot line whose controllers, protocols and machine ages look like the rest of the plant, so that every connection problem you solve once is solved for the rollout. The newest line is the easiest pilot and often the least useful one.

Do a quick count before choosing. List every line’s main machines with their controller family, the interface each one offers (OPC UA, Modbus TCP or RTU, MTConnect for CNCs, or none), and its approximate age. The signal inventory worksheet is a convenient place to start the list, and the machine connectivity checklist covers what to confirm on each machine.

Example (fictional). The bottler’s quick count covers three lines and the palletizing area. Line 1 is two years old and every machine offers OPC UA. Lines 2 and 3 each have a filler PLC that offers OPC UA, a capper torque monitor and meters on Modbus TCP or RTU, and at least one signal that needs an added sensor wired to a small I/O module. The palletizer is a one-off with its builder’s own controller. Line 2 covers every connection route the plant needs except the palletizer’s. Line 1 would connect fastest and teach the least.

Four rules of thumb help:

  • Include one hard machine. If most of the plant includes older machines without a modern interface, the pilot should include one, so the retrofit route (an added sensor, current transformer or I/O module) is proven early. The options are compared in getting data from older machines without OPC UA.
  • Avoid one-offs. A machine that exists once teaches a lesson you will not reuse.
  • Prove the pattern you will copy. Kamble and colleagues found that their low-cost single-press setup would need a redesigned database to add sensors. A pilot built to be copied should use the data model, naming and connection pattern intended for the whole plant from day one.
  • Check the network, too. The pilot line’s network drop, switch and route to the firewall should be like the ones the other lines use. A line that happens to sit next to the server room hides the cabling and network questions the rest of the plant will raise.

Wiring and panel work, where a sensor or meter must be added, is done by the plant’s electricians or a licensed contractor. Plan their time into the pilot, not after it.

People: a named owner on every shift

Name one person who owns the pilot and its decision, and one owner on each shift who checks the report and makes sure reasons get entered. Without them, the system records stops nobody explains and produces a report nobody reads.

Role Who, typically What they do in the pilot
Pilot owner Plant manager or operations lead Approves the pilot plan, chairs the review, makes the go, change or stop decision
Shift owner (one per shift) Shift supervisor or lead operator Checks the shift report, chases missing reasons, notes when the timeline disagrees with what people saw
Controls engineer In-house or the plant’s integrator Confirms what can be read without program changes; approves any change that is needed
IT/OT lead IT generalist or network owner Approves the gateway’s network path and adds it to the asset inventory
Maintenance lead Maintenance supervisor Confirms fault codes and stop categories; uses the data for the costed problem
Operators Every crew on the line Enter stop reasons in their own words; report when the board is wrong

People’s reactions matter as much as the roster. The Aston study reports that “shop floor employees may perceive the technology as a threat, especially when manual hand machine outputs are monitored,” and that management must explain the purpose and benefits to win buy-in. Say at the start what the data is for (finding losses on the line) and what it is not for, and keep to it.

The shift owner’s routine should be short enough to survive a busy night. At the end of each shift: open the report, check that every long stop has a reason, correct any stop the crew says is wrong, and write one line on anything the board missed. If that routine does not fit in the shift, the pilot has a staffing problem that will be worse on every later line, and the review should hear about it.

Training each shift on its own screens is a subject of its own, covered in training operators on new shop floor software across every shift. For choosing the line, what matters is that every shift has someone who will be trained and who has the time to use what they learn.

Scoring candidate lines

Score each candidate against the five tests, weight the two that matter most, and discuss the scores in the room rather than accepting the totals. The scoring makes the trade-offs visible; the conversation makes the decision.

Liozu’s advice for ranking pilots applies directly: the key is “to select the right criteria, to use the right weighting mechanism, and to have candid scoring interactions.” For a first monitoring pilot, we weight the costed problem and representative equipment double, because they decide whether the pilot leads anywhere. The other three tests can often be fixed with effort; those two cannot.

Test (weight)Line 1, new canning lineLine 2, bottle fillerLine 3, older bottle linePalletizing area
Known, costed problem (x2)1322
Representative equipment (x2)1321
Owner on every shift (x1)2312
Data to compare against (x1)2321
Access you can get (x1)3223
Weighted total (maximum 21)11201312
Fictional example: scores from 1 (weak) to 3 (strong) for a fictional beverage bottler choosing its first pilot. Weighting is the editorial method described in this article; the idea of ranking pilots on pre-set, weighted criteria comes from IndustryWeek, "Getting Your IIoT Project out of Pilot Purgatory" (June 24, 2019).

Example (fictional). Line 1 scores best on access, because its new machines are easy to reach and it stops often, but it has no argued-about loss and its equipment matches nothing else in the plant. Line 3 has a night shift without a supervisor, so test 3 would need fixing first. The palletizing area is a one-off. Line 2 scores 20 of 21; its only weak point is access, because the filler stops for planned sanitation only once a week. The team accepts that and schedules the gateway connection for a sanitation stop.

Write the success measures before anything is connected

Write two kinds of measures into the pilot plan before the gateway goes in: measures that prove the data can be trusted, and measures that show whether the costed problem is now visible enough to act on. Agree how each will be checked and who checks it.

Data-trust measures answer “are the numbers right?” They are checked against the independent record from test 4. The fictional example line uses six, including good and total counts that agree with the filler’s HMI counter within 0.5% at the end of each shift, every stop over 2 minutes having a reason by the end of the shift, and no data lost during a deliberate internet outage.

Business measures answer “is this worth more lines?” Keep them honest. A pilot of a few weeks rarely proves a lasting improvement, and promising one invites a fudge. Better measures ask whether the loss is now measured, explained and owned:

Measure Type How it is checked Baseline from
Counts agree with the machine counter within the stated tolerance Data trust Supervisor’s end-of-shift reading against the report HMI counter
Stops over the threshold have a reason by end of shift, on every shift Data trust and adoption Stop list in each shift report None before; this is new
Machine states match what operators saw Data trust Shift log compared with the timeline, stop by stop Paper shift sheet
The costed problem is measured per shift, with its causes Business Review of the report against the plant manager’s question Paper logs and memory
At least one decision is taken from the report Business Minutes of the weekly production meeting None
The rollout cost per line can be estimated Business Signal count, connection work and configuration time from the pilot Survey estimate

Every number needs a written definition. If OEE is in the report, define it the way the Lean Enterprise Institute does: “Availability Rate x Performance Rate x Quality Rate = OEE.” Then write down what counts as planned time and which rate is the ideal rate, because those choices move the result more than the formula does.

Leave some measures out on purpose. An OEE target (“raise OEE by five points”) is a poor pilot measure, because a short pilot cannot separate a real gain from a different product mix or a quiet month, and because the first honest measurement often comes out lower than the figure people believed. Screen counts, logins and dashboard views measure attention, not use. Use the reasons entered and the decisions taken instead.

Add one technical measure that protects the plant: the first connection is made during a planned stop, and nothing changes on a controller without the controls engineer. NIST SP 800-82 Rev. 3 is blunt about testing on production equipment: “The live operational systems should never be used for testing” (NIST SP 800-82 Rev. 3, Appendix C.2.2, Table 16). A read-only gateway is not a test of controller changes, but scheduling its first connection for a stop costs nothing.

Set the length in shifts and events, not in hopes

Fix the pilot’s length before it starts, and define it by what the pilot must see rather than by a calendar month. Every shift pattern, enough repeats of the costed problem, and each main product family should appear before the review.

A useful way to write it:

  1. Every crew, more than once. Each shift crew, nights and weekends included, works the line with the new board at least twice, so the second time shows whether they kept using it.
  2. The problem, several times. If the costed problem is changeover overruns, the pilot runs until a stated number of changeovers have happened, including the hard ones.
  3. Each main product family. Rates and reasons often differ by product. A pilot that runs one product says little about the others.
  4. One planned outage test. Disconnect the internet link during a planned stop and check that buffered data arrives without a gap. How gateways buffer is covered in store and forward at the edge.
  5. A midpoint check and a fixed review date. The midpoint check fixes data problems early; the review date does not move.
Survey and plan Connect Configure and test Run: first shift Run: second shift Run: night shift Events in the run Review and decide one planned stop Yellow dots: the six changeovers the plan requires. Red dot: planned uplink test. Dashed line: midpoint check.
Fictional example: the sequence of a pilot plan for one line, drawn to show events rather than dates (not to scale). The run ends when every shift and the required events have been covered, and the review date is fixed in advance. Editorial method; outage test as in the fictional example line.

Liozu’s article ends with the same instruction in a different setting: “Design this strategy with the exit of the pilot or POC mode in mind.” An end date that slides because the data is “almost there” is one of the simplest ways a pilot becomes permanent.

Sometimes the problem refuses to appear. If the changeover that overruns every week happens to run on time during the pilot, do not extend the run in the hope that it fails. Review on the planned date, record that the data-trust measures were or were not met, and decide whether the cost case still stands on the evidence from before the pilot. A good data trail of normal running is still a result.

Running the go, change or stop review

Hold the review on the date in the plan, with the evidence prepared in advance, and end it with one of three decisions written down: go to more lines, change something and run again, or stop. Each decision is legitimate, and each has rules agreed before the pilot started.

The evidence pack

  • The pilot plan, with its measures and their targets.
  • For each measure: the result, how it was checked, and by whom.
  • The costed problem as the pilot measured it, by shift and by cause.
  • The list of fixes made during the pilot, from the change log.
  • An estimate for the next line: signals, connection work, configuration, training.
  • Open issues and what each one would take to close.

Who is in the room

The pilot owner chairs and decides. The shift owners attend, nights included, because they know whether the board was used and where it was wrong. The controls engineer and the IT/OT lead speak to the connection and the network path, maintenance speaks to the costed problem, and the vendor presents the evidence and answers questions. Whoever approves the money for the next lines should hear the evidence first-hand rather than in a summary.

Decision rules

Decision When it fits What happens next
Go Data-trust measures met; the costed problem is measured and owned; the next line’s cost is known and acceptable A rollout plan naming lines in order, owners and go-live criteria
Change Data trust met only after fixes, or one shift not yet using the board, or the costed problem unclear A short, written second run with the specific changes and a new review date
Stop Data cannot be trusted after fixes, or the loss is too small to justify more lines Close the pilot; keep the documents and an export of the data; record why

After a go, the rollout plan should list the lines in order, the signals for each, the access windows that fit production, an owner for each area, the onboarding sessions and the go-live criteria for each line. Reuse the pilot’s definitions and reason list unchanged unless the review agreed to change them, so the lines can be compared from the first day.

“Change” must not become a polite word for drifting. Allow one change cycle, with a written list of what changes and a fixed date, and treat a second “change” as a stop unless the plan is rewritten from scratch.

Stopping is cheaper when the exit was agreed at the start. Make sure the pilot agreement says you keep the documentation and a full export of the pilot data in open formats, whoever the vendor is. What to ask for is set out in data ownership and exit terms. In OpenGXT’s case, the pilot ends at the decision point in the written pilot plan, and if you stop, you keep the documents and an export of the data, as described on how we work.

What to settle during the pilot so the rollout is a copy

Use the pilot to settle everything the next lines will reuse: the data model and naming, definitions and reason lists, the connection pattern and its security arrangements, documentation and the support model. If these are settled on the first line, the second line is a copy rather than a rebuild.

The data model and naming. Place the line in a hierarchy the whole plant can share, such as site, area, line, cell and asset, and name signals the same way everywhere. A line named on the fly will have to be renamed later, along with every report built on it.

Definitions and reason lists. Write the data dictionary during the pilot: what counts as planned time, which rate is ideal, when a short stop becomes downtime, and the stop reasons in operators’ words. The next line starts from that list instead of a blank page.

The connection pattern. Settle how the gateway reaches the hosted software and record it as the pattern for every line. The outbound-only design and the questions to ask a vendor are in the outbound-links article. If anyone outside the plant will need remote sessions, set up the access path now; the procedure is in giving vendors remote access without opening the door.

Security housekeeping. Add the gateway to the asset inventory. CISA’s asset inventory guidance (August 13, 2025) describes an inventory as “an organized, regularly updated list of an organization’s systems, hardware, and software.” Ask the vendor the procurement questions in CISA’s Secure by Demand guidance (January 13, 2025), and write down who is responsible for patching, monitoring, logging and recovery. NIST’s September 2026 draft of SP 800-82 Rev. 4 puts it this way: these responsibilities “may be shared among OT, IT, cloud providers, SaaS providers,” integrators and equipment vendors. A pilot is the cheapest time to find out who does what.

Documentation and support. By the end of the pilot you should hold a signal inventory, a data dictionary, a data-flow and network diagram, quick guides for each screen and a change log, in editable formats. Decide who answers the phone after go-live and how changes are requested. The go-live readiness checklist covers the checks before each new line goes live.

The cost of the next line. Record what the pilot actually took: how many signals, how many needed an added sensor or meter, how many hours of controls engineer and IT time, how many training sessions per shift. Those figures, not the survey’s first guess, are the basis for the rollout budget.

Small manufacturers do not have to do this alone. NIST’s Manufacturing Extension Partnership serves small and medium-sized U.S. manufacturers “through state-designated MEP Centers located across the U.S. and in Puerto Rico,” with “nearly 1,400 trusted manufacturing advisors and experts at more than 450 MEP service locations.” A state MEP center can be a neutral second opinion on the selection and on the business case.

A pilot-line checklist for the planning meeting

Bring this list to the meeting where the first line is chosen. If an item cannot be ticked, write down who will close it and by when, before the pilot plan is signed.

  • The costed problem is named, with a first figure per shift or week.
  • A quick count shows the line’s controllers and interfaces recur across the plant.
  • A named owner exists for every shift, nights and weekends included.
  • An independent record (counter, paper log or ERP posting) covers the same shifts.
  • Planned stops, the controls engineer’s time and the IT/OT approval path are confirmed.
  • Data-trust and business measures are written, with how each will be checked.
  • The pilot’s length is defined in shifts and events, and the review date is fixed.
  • The decision rules for go, change or stop are agreed, including what you keep if you stop.
  • The data model, naming and connection pattern are the ones intended for every line.

The six stages OpenGXT works through, from the equipment and data survey to run and support, are on how we work, and the pilot line engagement, with what you provide and receive, is on engagements. If you have a line in mind and want a second pair of eyes on the choice, you can plan a pilot line with us.

Working on this at your plant?

If this article describes a problem on one of your lines, tell us about it. We start with one line, its signals and the question you ask after every shift.