A line needs fewer downtime reason codes than most plants start with: somewhere between 10 and 25 for the whole line, arranged in two levels so the operator never sees more than about eight choices at once. The machine should record when it stopped, for how long and in what state (running, starved, blocked, faulted or in a planned stop), and the operator should add only what the controller cannot know, which is why. Stops that nobody explains go into a visible “Unassigned” bucket, and a monthly review retires codes nobody uses and splits codes that swallow too much of the lost time.
The sections below work through each part of that answer. The worked examples are fictional and labeled; several use the Line 2 filler at a fictional beverage bottler that also appears in the example project and the OEE calculator.
How many downtime reason codes a line needs
Keep the full list for one line between about 10 and 25 reasons, and design it so an operator makes no more than two choices of about eight options each. The published rules of thumb look like they disagree, but most of the gap disappears once you notice they are counting different things.
| Source | Rule | What it counts |
|---|---|---|
| Vorne, a monitoring vendor | Capture up to 25 down reasons, “even if you have the capability to capture more reasons” | The whole list for a process, with detail at the constraint |
| Another vendor’s reason code guide | 10 to 20 per line is typical; more than 30 makes operator selection unreliable | The whole list for a line |
| The same vendor’s packaging line guide | About 8 groups for the whole plant and fewer than 10 reasons per machine and group | What one operator sees on one screen |
| Our production monitoring practice | Usually 10 to 20 reasons in two levels, written with your supervisors | The whole list for a line |
Two different limits are at work. The first is the operator’s screen: how many options a person can scan in a few seconds with gloves on and a jam waiting. The second is the analysis: how many bars a Pareto chart can have before the losses are spread so thin that no bar stands out. The 25 limit and the 10 to 20 range are about the second limit. The “fewer than 10 per screen” rule is about the first. A two-level tree satisfies both: six categories with three or four reasons each gives a line about 20 reasons in total, and the operator still makes two short choices.
Why long lists fail
Vorne’s guidance describes the failure plainly: when people are presented with hundreds of reasons, “most people select the most convenient reason (so that they get back to running the machine), rather than the correct reason.” Its second argument is about analysis. A long list spreads the lost minutes across many small bars, and the chart no longer points at anything. The same company’s OEE.com FAQ lists “a bewildering array of downtime reason codes” among the biggest OEE mistakes and closes the point with “Collect less; do it well.”
A long list also decays faster, because each new code makes the old ones harder to find. The support and maintenance page describes the end state most plants recognize: a list that grew from 15 entries to 60, with half the stops landing in “Other”.
Detail where it pays
Vorne adds a useful way to keep the count down: put the detail at the constraint. Its worked case is a process with four machines. Ten reasons on each machine gives 40 reasons. Ten reasons on the constraint and one generic reason for each other machine gives 13. If a non-constraint machine starts stopping the constraint, you add a couple of reasons for it until the problem is fixed, then remove them.
On a filling line that usually means the filler gets its own reasons, and the capper, labeler and case packer each appear as a single reason under an upstream or downstream category. When the case packer becomes the problem, it earns two or three temporary reasons of its own.
A starting size
For a first line, a reasonable starting point is 12 to 18 reasons under five to seven categories, plus a planned category filled from the shift schedule rather than by the operator. That leaves room to add reasons during the first months without crossing 25. If the first draft from your supervisors has 40 reasons, it usually means three things are mixed together: machine states, fault codes and real reasons. The next two sections separate them.
What the machine can record without anyone typing
The machine can record the start time, end time and duration of every stop, the state it was in (running, starved, blocked, faulted, stopped by an operator, or in a planned mode) and, on many controllers, the first fault that tripped it. None of that should be on the operator’s reason list. Asking a person to pick “Machine stopped” or “Blocked” wastes a choice on something a tag already knows.
What the standard state models provide
Packaging machines built to PackML already publish most of this. PackML was developed by OMAC and adopted by ISA as TR88.00.02; ISA’s listing describes the technical report as defining standardized machine states, modes and PackTags. The OPC Foundation’s OPC UA for PackML companion specification (OPC 30050) models those states and tags and describes them in useful detail:
- Execute means the machine is carrying out the selected mode; in production mode, it is making product.
- Suspended means the machine is paused waiting for external process conditions, such as faults on upstream or downstream equipment. The specification calls the downstream case “blocked” and the upstream case “starved”.
- Held means the machine is paused waiting for internal conditions to clear, such as low levels of materials or other minor issues that need operator service.
- Stopped and Aborted cover a controlled stop and a rapid safe stop after an Abort command or a machine fault.
- EquipmentBlocked and EquipmentStarved are flags that say processing is suspended because downstream equipment cannot receive material or upstream equipment cannot send it.
- StopReason is a structure that is “typically used for ‘First Out Fault’ Reporting”. The specification describes it as “the first event captured during an abort, held, suspended or stop event.”
Machines described with the OPC Foundation’s OPC UA for Machinery building blocks (OPC 40001-1) can expose a simpler state model. It separates OutOfService (available but unable to work for “a technical reason originating from within” the machine, such as an error) from NotExecuting (available and functional but not working for “an organizational reason originating from outside”, such as waiting for an order). That split is the first level of a reason tree, delivered by the machine. The same specification defines operation modes (Processing, Setup and Maintenance) and notes that the mode “may not be known by the MachineryItem itself”, in which case it has to come from an external source “like an MES system or the operator.”
| Generic state on the shift board | PackML state or flag | OPC UA for Machinery state | Who supplies the reason |
|---|---|---|---|
| Running | Execute | Executing (mode Processing) | Nobody: no reason needed |
| Idle, starved | Suspended with EquipmentStarved | NotExecuting | Operator says why upstream had nothing |
| Idle, blocked | Suspended with EquipmentBlocked | NotExecuting | Operator says why downstream was full |
| Down, faulted | Aborted or Held, with StopReason | OutOfService | First-out fault, confirmed by the operator |
| Down, changeover | Depends on mode and the machine’s program | Mode Setup, if the machine knows it | Product change from the recipe or order; operator picks the type |
| Planned stop | Not a production state | Mode may come from an external source | The shift schedule |
Machines without a state model
Most plants have machines that publish neither model. They can still give a run signal, a count and a fault word, which is enough to build the same states: running while the count moves, stopped when it does not, faulted when the fault word is nonzero. Which signals exist on which machine is a question for the equipment and data survey, and the gateway work that reads them is described under machine connectivity. For a detailed comparison of paper logs, operator entry and automatic state capture, see our companion article on manual and automatic downtime tracking.
Fault codes are not reasons
A fault code is evidence, not a reason. Vorne gives the standard trap: an operator opens a guard to clear a material jam, and the controller logs “Machine Stop” and “Guards Open”. The reason you want on the report is “Material Jam”. Controllers often raise several faults for one stop, and the last fault raised is frequently a consequence of the first.
Three rules keep fault codes useful:
- Use the first-out fault, not the list of active faults. If the controller has a first-out register (PackML’s StopReason, or a first-out word written by the controls engineer), read that.
- Map fault codes to reasons in a lookup table. Hundreds of fault codes collapse into a handful of reasons. “Infeed photo-eye blocked”, “Star wheel overload” and “Bottle down at infeed” might all map to Equipment, then Bottle feed jam.
- Keep the fault code on the stop record next to the reason. When a reason grows, the fault codes under it show where to split it.
What only a person can add
The operator adds the cause the machine’s sensors cannot see. A filler knows it is starved; it does not know whether the caps are late because the warehouse did not deliver them, because the cap sorter upstream is jammed or because the wrong caps were staged. A machine knows it is stopped; it does not know that it is stopped because the quality technician placed the product on hold or because nobody is available to run it.
The usual list of things only a person can say:
- Material problems that start outside the line: not delivered, wrong material, material out of specification.
- People: no operator available, operator moved to another line, waiting for a technician to respond.
- Quality decisions: a hold placed by quality, a fill level adjustment after a check, a first-piece approval wait.
- Changeover type, when the machine cannot read it from the recipe: a size change, a flavor change, a label change.
- Context for a fault: the first-out fault says where it stopped; the operator can confirm or correct what actually happened.
Ask for symptoms, not root causes
Operators are good at describing what they saw and where. They are rarely in a position to name the root cause while the line is down and the supervisor is waiting. Vorne’s guidance is to capture “the most common symptoms”, which “broadly describe the area of the machine that has the problem”, with “Infeed Problem” and “Material Jam” as examples. Root cause belongs to the problem-solving work that follows the Pareto chart, not to the reason list.
Ask at the right moment
The operator’s job during a stop is to restart the machine. The shift board can show the stop as soon as it starts, but it should not demand an answer until the machine is running again or the stop has clearly become long. A prompt that appears when the machine restarts, with the machine’s own state and first-out fault already filled in, takes two taps. A form that must be completed before the restart button works will be answered with whatever is quickest.
Example (fictional). On first shift the Line 2 filler at a fictional beverage bottler stops at 07:41. The controller reports the state “down” and the first-out fault for the bottle infeed. The fault code maps to Equipment, then Bottle feed jam, so the shift board shows that reason as a suggestion. The operator clears the jam, restarts the filler at 07:52 and confirms the suggested reason with one tap. At 10:41 the filler goes idle with the infeed full and the cap chute empty. The machine can say it is starved of caps, not why, so the operator picks Material, then Caps not delivered. At 12:18 the filler stops for a size change to 1-liter bottles; the operator picks Changeover, then Size change, and the stop is timed against its 25-minute standard.
A two-level code tree sized for the operator screen
Build the first level around who has to act and the second level around what the operator saw. A first level of “Equipment”, “Material”, “Upstream”, “Downstream”, “Changeover”, “Quality” and “People” tells the supervisor whom to call. The second level tells that person where to look.
Categories that match who responds
The table below is a starting set of first-level categories for a packaging or assembly line. Each one has an owner and maps to one OEE loss, so the reason report and the OEE report agree. The loss names follow the six big losses as OEE.com describes them, and the Lean Enterprise Institute’s OEE definition groups the same losses under availability, performance and quality.
| Category | Who acts first | Typical second-level reasons | OEE loss |
|---|---|---|---|
| Equipment | Maintenance | Jam by area, a named fault, a broken part | Availability (equipment failure) |
| Material | Materials handler or warehouse | Not delivered, wrong material, out of specification | Availability (unplanned stop) |
| Upstream | Line lead | Starved by a named machine | Availability (unplanned stop) |
| Downstream | Line lead | Blocked by a named machine | Availability (unplanned stop) |
| Changeover | Setup technician | Size change, flavor change, label change | Availability (setup and adjustments) |
| Quality | Quality technician | Quality hold, adjustment after a check | Availability (the stop); the rejects count against quality |
| People | Supervisor | No operator available | Availability (unplanned stop) |
| Planned | Scheduler | Break, meeting, scheduled sanitation | Excluded from planned production time |
The last row does not belong on the operator’s screen. Breaks and scheduled sanitation come from the shift calendar, and whether a given stop belongs in that row at all is a separate decision that changes the OEE number. Our article on what counts as planned downtime in OEE works through it stop by stop.
The Line 2 tree
Example (fictional). The Line 2 data dictionary, written with the supervisors in their own words, has 12 rows: Equipment (Bottle feed jam, Capper fault, Filler valve fault), Material (Caps not delivered, Bottles not delivered), Downstream (Case packer blocked), Changeover (Size change, Flavor change), Quality (Quality hold, Fill level adjustment), People (No operator available) and Planned (Break or sanitation, filled from the shift schedule). The operator therefore chooses from six categories and then from at most three reasons. The three Equipment reasons are suggested from fault codes and confirmed by the operator. The capper and the case packer each appear as one reason, because the filler is the machine the line’s OEE is measured on.
The Line 2 list is short because the machine does half the work: there is no “Filler stopped” or “Starved” on it, because the state model already says those things.
Writing reasons that three people would pick the same way
A reason is well written when three different operators, shown the same stop, would pick it. Vorne states the test directly: “It should be impossible for three different people to select a different reason for the same stop.” Most bad reason lists fail it in a few predictable ways.
Rules for each reason
- Mutually exclusive. “Jam” and “Infeed problem” overlap: an infeed jam fits both. Pick one axis (where on the machine, or what happened) and use it for every reason in the category.
- In the operator’s words. If the floor says “bottle down at the star wheel”, the reason should not say “container orientation fault”. Vorne adds that this may mean providing reasons in a second language.
- A symptom, not a diagnosis. “Capper fault” can be confirmed by anyone standing at the capper. “Worn chuck inserts” needs a technician and a teardown.
- A condition, not a person. Vorne advises against reasons that point at people, such as “Waiting for Engineer”, because they are “rarely accurate and rarely create a positive working environment.” “No operator available” describes the line’s condition; “Operator late” describes a person.
- One loss per reason. A reason should never mix a stop and a reject, or a planned and an unplanned event. “Changeover or cleaning” makes the planned stops decision impossible to apply.
- No states. Anything the machine already reports (stopped, starved, blocked, faulted) is not a reason.
- A stable code behind every label. The screen shows “Caps not delivered”; the database stores a code such as MAT-02. Labels can be reworded for clarity without breaking last month’s chart.
Bad and better reasons
| Weak reason | Problem | Better |
|---|---|---|
| Machine down | A state, already known | The first-out fault, confirmed |
| Misc | Absorbs everything | Other, with a comment required |
| Maintenance | Names a department, not what happened | Equipment, then the area that failed |
| Waiting for Joe | Names a person | People, then No operator available, or Equipment, then the fault |
| Jam or misfeed | Two symptoms in one | Two reasons, or one with a clear definition |
| Changeover and cleanup | Mixes a setup with a sanitation decision | Changeover, then the type; sanitation from the schedule |
Write one line of definition for each reason
Every reason gets a one-sentence definition and an example stop in the data dictionary, next to its code and category. “Caps not delivered: the filler is ready and the cap chute is empty because no caps reached the line; not for a jam in the cap sorter, which is Capper fault.” Definitions like this settle most arguments before they reach the shift meeting, and they are the text a new operator reads in the quick guide.
To test a draft, take ten stops from last week’s paper log, read each description to three supervisors separately and ask each to pick a reason. Where they disagree, the reason is ambiguous or missing.
Which stops should ask for a reason
Ask for a reason only for stops longer than a threshold you write down, and let shorter stops count as slow running. OEE.com’s page on the six big losses recommends setting the threshold “based on your policy for tracking reasons”, and gives the example of a policy that “any downtime longer than two minutes should have a reason associated with it”. The Line 2 data dictionary uses that 2-minute threshold.
The threshold decides which OEE factor a stop lands in. A stop above it is downtime and lowers availability. A stop below it stays inside run time and lowers performance. That matches the Lean Enterprise Institute, whose performance rate covers operating speed losses including “stoppages lasting a few seconds.” On the same six big losses page, idling and minor stops are described as stops of “typically a minute or two” that are usually “well under five minutes” and do not need maintenance personnel.
Setting the threshold
- Too low and the operator spends the shift answering prompts. The OEE.com FAQ warns against thresholds “so low that operators spend as much time collecting data as running machines.”
- Too high and real stops hide inside performance, where nobody is asked about them.
- A practical test: look at a week of stop durations from the machine’s state signal. If most stops are under a minute and a few are over five, a 2-minute threshold separates them well. If the line has many stops between two and four minutes, try a lower threshold on one shift and ask the operators whether the prompts are bearable.
Short stops still deserve attention. The machine can count them and group them by first-out fault without asking anyone, which is often enough to find the chronic jam that costs more than any single breakdown. How well each tracking method catches these short stops is covered in our companion piece on manual and automatic downtime tracking.
Two more rules to write down
Merging stops. A machine that restarts for 20 seconds and stops again for the same fault produces two events where the operator sees one. Decide how long it must run before a new stop counts as separate.
Planned stops. Breaks and scheduled sanitation come from the shift calendar and never ask the operator. Decide whether an overrun past the planned window becomes a stop with a reason.
The rule for unassigned stops
Every stop over the threshold that still has no reason at the end of the shift must stay visible as “Unassigned”, get a supervisor’s attention before the report goes out, and never be quietly folded into “Other”. Unassigned time is a measure of how well the reason process works, and it should be on the chart like any other bar.
Unassigned is not the same as Other
The two look similar on a report and mean opposite things.
- Other means an operator looked at the list and nothing fit. That is useful information about the list: something is missing. Require a short comment with every “Other”.
- Unassigned means nobody answered. That is information about the process: the prompt came at the wrong time, the screen is in the wrong place, or the operator was away dealing with something else.
Vorne recommends keeping an “All Other Losses” reason and breaking it apart when it becomes your top loss. The same logic applies to Unassigned, with a different fix: you do not add reasons, you fix how and when people are asked.
A rule that works on most lines
- Create the stop as Unassigned the moment it crosses the threshold, with the machine’s state and first-out fault already attached.
- Suggest a reason where the fault code maps to one, and ask the operator to confirm it when the machine restarts.
- Ask once more at the next natural pause if the operator skipped the prompt, and show the count of open stops on the shift board.
- Before the shift report goes out, the supervisor reviews every stop still marked Unassigned and either assigns a reason or leaves it as Unassigned. Nobody picks “Other” on an operator’s behalf.
- Log every correction with who made it, when and what it replaced. A supervisor changing “Capper fault” to “Caps not delivered” the next morning is useful; a silent change is not.
- Set a target for unassigned stop minutes in the definition sheet and report against it weekly. A starting target of 5% of stop minutes is a reasonable house rule; tighten it once the board has been in use for a few months.
Example (fictional). Suppose that on the Line 2 shift the operator restarts the filler after the 26-minute cap wait at 11:07 and is pulled straight to a case packer alarm without answering the prompt. The shift board shows one open stop: idle, starved of caps, 26 minutes, no reason. The supervisor’s end-of-shift review at 14:00 assigns Material, then Caps not delivered, after checking with the warehouse. The stop record keeps both facts: the reason, and that it was assigned by the supervisor after the shift. If the 26 minutes had been left unanswered, the shift report would have shown them as Unassigned, a third of the shift’s 75 stop minutes, which is exactly the kind of gap the weekly target is meant to catch.
The monthly review: retire, split and merge codes
Once a month, rank the line’s stop minutes by reason, retire codes nobody used, split any code that absorbs a large share of lost time but has more than one fix, and add a reason when “Other” or its comments show a gap. Then record every change in the change log with the date it takes effect.
The ranking is a Pareto chart. ASQ describes a Pareto chart as a bar graph whose bars “represent frequency or cost (time or money)”, arranged longest to shortest so the chart “visually depicts which situations are more significant.” For downtime, build it twice: once by minutes and once by number of stops. Minutes show where the time went. Counts show where the operators are interrupted most often, which is usually where the chronic short-cycle problems live.
The review, step by step
- Pull the month’s stop list for the line: every stop over the threshold, with its reason, minutes, start time, state and first-out fault.
- Rank by minutes and by count. Note the top three by each.
- Check Unassigned against its target. If it is above target, the fix is in the process: the timing of the prompt, the place of the screen, the training on one shift.
- Read every “Other” comment. If the same words appear several times, add a reason for them. Vorne’s rule is to add reasons until “All Other Losses” is not in the top ten losses.
- Look for codes to split. A code is a candidate when it holds a large share of stop minutes (20% is a reasonable trigger) and its stops have more than one fix. The fault codes, comments and durations under it usually show the split.
- Look for codes to merge. If supervisors keep relabeling stops between two reasons, the two are not mutually exclusive. Merge them or rewrite both definitions.
- Retire codes nobody uses. A code with no stops in three monthly reviews comes off the screen, unless it covers a rare but serious event the plant wants recorded the same way every time.
- Record every change in the change log with its effective date, and update the operator quick guide and the data dictionary the same day.
Example (fictional). The Line 3 bagger at a fictional snack maker lost 2,975 stop minutes in a month. Film splice is the top bar at 610 minutes, 20.5% of the total, so it is checked for a split. The stop list shows two groups: 24 stops of about 9 minutes when a film roll runs out, and 14 stops of about 28 minutes when the film breaks mid-roll. The first is a roll change technique problem for the operators; the second points at film tension or a material issue for maintenance and purchasing. The code becomes two reasons, Roll change splice and Film break mid-roll. Unassigned is 380 minutes, 12.8% of the total and far above the 5% target; most of it falls on second shift, where the board sits behind the case packer, so the screen is moved. The “Other” comments mention the date coder six times, so Date coder fault is added under Equipment. A label applicator reason has had no stops for three months because the applicator was removed, so it is retired. The list goes from 15 to 16 reasons.
Never rename a code in place
When a reason splits, the old code is retired and two new codes are created, with a note in the change log saying which old code they replace. If you simply rename “Film splice” to “Roll change splice” and add “Film break mid-roll”, last month’s 610 minutes appear under the new name and the comparison is wrong. Keeping the mapping between old and new codes lets the trend chart line up months across the change.
To decide which reason to work on first, put a price on it. The downtime cost calculator turns stop hours into lost margin, idle labor and recovery overtime, so the top two reasons can be compared in dollars as well as minutes.
Rolling the list out to more lines and shifts
Keep the first-level categories the same across the plant and let the second-level reasons differ by line. Shared categories let a plant manager compare “Material” minutes on every line in one chart; line-specific reasons keep the operator’s screen short and in the words of that line.
What stays the same and what changes
| Part of the list | Shared across lines? | Why |
|---|---|---|
| First-level categories | Yes | Plant-wide charts and the same response owners everywhere |
| Planned category and its rules | Yes | The same OEE definition on every line |
| Threshold for asking a reason | Usually | Different only where a line’s cycle time makes the shared value unworkable |
| Second-level reasons | No | Each line has its own machines, materials and words |
| Fault code mapping | No | Each controller has its own fault list |
| Unassigned target and review cadence | Yes | The process is the same on every line |
Start on one line
Write the first list for one line, run it for a month on every shift and hold the first monthly review before you copy anything. The first review almost always changes three or four reasons. Copying an untested list to ten lines multiplies those changes by ten.
On a filling line in a food or beverage plant, the first month also tends to show how much of the downtime starts upstream or downstream of the measured machine: the labeler that starves the case packer, the filler waiting on the capper. Our page on food and beverage lines describes how machine states across the chain separate those stops from the measured machine’s own faults, and how scheduled sanitation stays out of the losses.
Train every shift on the same definitions
The same list means nothing if first shift picks “Material” for a starved filler and second shift picks “Upstream”. A one-page operator quick guide with each reason and its one-line definition, kept next to the board, does more for consistency than any software setting. During a pilot, someone should sit with each shift for its first few stops and compare what the operator picked with what happened.
Checklist for your first reason code list
Use this list when you write the first version for one line, and again at each monthly review.
Before the first shift
- The machine states the line can report are listed, with the tag or node for each: running, starved, blocked, faulted, planned.
- The first-out fault is identified on the controller, and a lookup table maps fault codes to reasons.
- First-level categories are named after who responds, and there are no more than about eight of them.
- Each category has no more than about eight reasons, and the whole list for the line is under 25.
- Every reason has a stable code, a one-line definition and an example stop.
- No reason is a machine state, a person’s name or a combination of two symptoms.
- The threshold for asking a reason is written down, along with the rule for merging short restarts.
- Planned stops come from the shift calendar and do not appear on the operator’s screen.
- The unassigned rule is written: who reviews, when, and the target share of stop minutes.
At each monthly review
- Pareto charts by minutes and by count are pulled for the month.
- Unassigned minutes are compared with the target, and the cause is found if they are above it.
- Every “Other” comment is read.
- Codes over the split trigger are checked for more than one fix.
- Codes unused for three reviews are retired.
- Every change is in the change log with an effective date, and the quick guide is updated.
To see how a reason list fits into the full arithmetic of a shift, run one shift’s minutes through the OEE calculator, then follow the fictional Line 2 from its first signal to its first shift report in the example project. Our production monitoring service builds the reason tree with your supervisors during the survey and keeps its change log after go-live. If you want to try it on one line first, you can plan a pilot line.