Exclude from planned production time only the time when the line was never meant to produce: unstaffed breaks and meals, scheduled meetings, holidays, shifts with no orders, and named events such as scheduled sanitation that the shift calendar sets aside before the shift starts. Everything that happens while the line is scheduled to run stays in OEE as a loss, including changeovers, setup adjustments, preventive maintenance done during production hours, material shortages, a missing operator and quality holds. The test is simple: if there was demand and the line could have been producing in that window, the stop counts against availability.
That rule follows the Lean Enterprise Institute, which measures availability against scheduled time, and the definitions on OEE.com, which keep changeovers and other planned events inside OEE. It also matches the OEE calculator on this site. The sections below give a decision table for the common cases, show how each choice moves the headline number on one fictional shift, and end with a one-page definition sheet that lets shifts and plants compare like with like.
Where planned production time starts and stops
Planned production time is the time the line is scheduled to make product. OEE measures losses inside that window and nothing outside it. The Lean Enterprise Institute defines the availability rate as downtime losses “as a percentage of scheduled time”, and OEE.com’s glossary defines planned production time as “the total time that equipment is expected to produce”, calculated by subtracting schedule loss from all time.
The time ladder for one shift has four steps:
- Shift time, or all the time you look at.
- Planned production time: shift time minus the excluded time. OEE.com calls the excluded time schedule loss, “the time when the plant is not scheduled for production (e.g., plant shutdown, no orders, breaks and lunches).”
- Run time: planned production time minus stop time. OEE.com defines stop time as “all time where the manufacturing process was intended to be running but was not due to Unplanned Stops (e.g., breakdowns), or Planned Stops (e.g., changeovers).”
- Fully productive time: run time minus the time lost to slow running and to rejects.
The same words mean opposite things
The phrase “planned stop” causes most of the confusion. On OEE.com a Planned Stop is an event like a changeover, setup or make-ready that happens while the process “is scheduled for production”. It stays in planned production time and lowers availability. On many shop floors, and in the input labels of our calculator, “planned stops” means breaks and meetings, which are taken out of planned production time and do not lower availability.
Both usages are common, so the words alone settle nothing. What matters is which side of the line each kind of time falls on. In this article:
- Excluded time is time taken out before OEE is calculated: the first input in our calculator, labeled “Planned stops (breaks, meetings)”.
- Stop time is every stop inside planned production time, planned or not: the second input, labeled “Unplanned stops (breakdowns, jams, waiting, changeovers)”. A changeover goes here even though everyone knew it was coming.
A plant’s definition sheet should use two names like these and list what belongs under each by name.
Why exclude anything at all
OEE is meant to measure how well the equipment uses the time the business asked it to run. Whether to staff a third shift, run on Saturdays or keep the line busy when orders are thin are business decisions, and they are judged with different numbers: capacity, utilization, cost. Excluding unscheduled time keeps those decisions out of the line’s score. The trouble starts when the same reasoning is stretched to cover stops that happen inside the scheduled window, because those are exactly the losses OEE exists to show.
The decision table: where each kind of stop goes
Most stops fall clearly on one side once you ask two questions. First, was the line scheduled to produce in this window, with demand for what it makes? If not, the time is excluded. Second, if it was scheduled, could work on the line, its materials, its staffing or its schedule shorten or remove this stop? If so, the stop stays in as a loss, even when it was planned.
| Kind of time | Excluded or loss | Factor it lowers | Notes |
|---|---|---|---|
| Breaks and meals the line does not run through | Excluded | None | Our calculator’s default. OEE.com treats including them as best practice where they take time from production (see below) |
| Breaks the line runs through with relief operators | Not excluded | None, if it keeps running | The line was scheduled to run, so the time stays in |
| Shift-start meetings and scheduled training | Excluded, by name | None | Only if on the calendar before the shift; minutes still reported |
| Holidays, plant shutdowns, unstaffed shifts | Excluded | None | OEE.com: plant shutdown “is excluded from OEE calculations” |
| No orders for this line | Excluded | None | OEE.com counts lack of demand as not scheduled time |
| Changeovers and setups | Loss | Availability | One of the six major losses; measured last good piece to first good piece |
| Adjustments, warm-up, first-piece inspection | Loss | Availability | OEE.com lists cleaning, warm-up, planned maintenance and quality inspections with setups |
| Preventive maintenance during scheduled production | Loss | Availability | OEE.com: “Probably” include, when it takes time that could be used for production |
| Preventive maintenance in an unscheduled window | Outside OEE | None | The line was not scheduled; the time shows in utilization |
| Scheduled sanitation or CIP | Excluded by name, or loss | None, or availability | A documented choice; overruns past the window count as a loss |
| Engineering trials and new product runs | Excluded by name, or loss | None, or availability | Exclude only if scheduled in advance as non-production use |
| Material shortage, waiting on upstream | Loss | Availability | An unplanned stop even when the warehouse “planned” the delay |
| Blocked by downstream equipment | Loss | Availability | Same as starved |
| No operator when there is demand | Loss | Availability | OEE.com: treat it as downtime |
| No operator because there is no demand | Excluded | None | Not scheduled time |
| Quality hold | Loss | Availability | The rejects themselves count against quality |
| Short stops under your reason threshold | Loss | Performance | Counted inside run time as slow running |
Where the sources disagree
The sources agree on changeovers. The OEE.com FAQ says changeover time “should be included in OEE (specifically, it should be included in Availability)”, and the Lean Enterprise Institute’s entry on total productive maintenance lists changeover time among the six major losses, with downtime, minor stops, speed losses, scrap and rework.
They differ on breaks. The OEE.com FAQ answers “Should lunches and breaks affect my OEE score?” with “Probably”, notes that “most companies choose not to include lunches and breaks as an OEE loss”, and argues that including them exposes time a plant could recover with relief operators or longer material feeds. Our calculator follows the common practice and excludes breaks. Both positions are defensible as long as every shift and every line does the same thing, and the excluded minutes are still reported.
Edge cases supervisors ask about
The decision table covers the common cases. These are the ones that come up in the first month of reporting, with the answer we recommend and the reason for it.
The line finished its order early and sat idle. If the scheduler had nothing else for the line and released it before the idle time started, the rest of the shift is excluded: there was no demand. If the line sat waiting for the next order to be released, the paperwork or the materials, the time is a loss. PackML has a state for the first case: Complete, which OPC 30050 describes as the process having “come to its defined end.” The machine can tell you the order finished; only the schedule can tell you whether another one should have started.
We ran through lunch with a short crew at reduced speed. The time stays in, because the line was running. The lower speed shows as a performance loss. The OEE.com FAQ handles the related case of a line short an operator: when there is full customer demand, treat the shortage as an OEE loss and “do not change the Ideal Cycle Time.”
No operator turned up. The FAQ gives a two-part answer that works well in a definition sheet. If there is demand and the line should have been running, it is downtime. If the line had no operator because there was no demand, or because the work was moved to another line by plan, it is not scheduled time and is excluded.
A power or compressed-air failure stopped the whole plant. Keep it in, with a Utilities reason. OEE measures what the equipment lost, not who is to blame. A plant that excludes every stop it does not control ends up with an OEE that describes the operators rather than the line.
A fire drill or a safety stand-down. A drill on the calendar before the shift is excluded by name, like a meeting. An unplanned evacuation is a stop with a reason.
Start-up and shutdown at shift change. If the line is scheduled to run across the change, any minutes it sits stopped during handover are a loss. If the plant deliberately schedules a gap between shifts, that gap is excluded time and belongs on the calendar.
Waiting for quality release of the first piece. A loss. OEE.com’s six big losses page lists quality inspections among the planned stops counted under setup and adjustments, and a long first-piece wait is often the easiest part of a changeover to shorten.
How each choice moves the headline number
Exclusions only ever move availability. Performance and quality do not change when time is excluded, because they are calculated from run time and counts, which exclusion does not touch. Every minute moved from stop time to excluded time therefore raises availability, and OEE with it, without a single extra bottle being filled.
The size of the effect is easy to estimate. OEE equals fully productive time divided by planned production time, as the OEE.com calculation page shows with its “simple” formula: good count × ideal cycle time ÷ planned production time. On a shift with 450 minutes of planned production time and an OEE near 75%, each minute taken out of the denominator adds about 0.17 points. A 38-minute changeover is worth about 7 points.
Example (fictional). The Line 2 filler at a fictional beverage bottler runs first shift, 06:00 to 14:00, 480 minutes, with a 30-minute break from 10:00 to 10:30. It stops three times: a bottle feed jam at 07:41 (11 minutes), waiting on caps from the warehouse at 10:41 (26 minutes) and a changeover to 1-liter bottles at 12:18 (38 minutes, against a 25-minute standard). At an ideal rate of 120 bottles per minute it fills 41,212 bottles, 40,580 good. With the break excluded and all three stops counted, planned production time is 450 minutes, run time 375 minutes, availability 83.3%, performance 91.6%, quality 98.5% and OEE 75.1%. Now classify the same shift differently and recalculate:
| How the shift is classified | Planned production time | Availability | OEE |
|---|---|---|---|
| Break counted as a loss | 480 min | 78.1% | 70.5% |
| Break excluded (calculator default) | 450 min | 83.3% | 75.1% |
| The changeover’s 25-minute standard excluded | 425 min | 88.2% | 79.6% |
| Cap wait called “not scheduled” | 424 min | 88.4% | 79.8% |
| The whole changeover excluded | 412 min | 91.0% | 82.1% |
| Changeover and cap wait both excluded | 386 min | 97.2% | 87.6% |
Performance stays at 91.6% and quality at 98.5% in every row. The line filled the same 41,212 bottles in the same 375 minutes of run time each time.
The spread is 17 points, from 70.5% to 87.6%, for one shift on one machine. That is larger than the gap most improvement projects close in a year, and it comes entirely from definitions. Two plants that report OEE without writing down their exclusions cannot compare their numbers, and one plant that changes its exclusions mid-year cannot compare itself with last year.
Changeovers stay in, and the case against a standard allowance
Changeovers stay inside planned production time and count against availability, measured from the last good piece of one run to the first good piece of the next. The Lean Enterprise Institute defines changeover time exactly that way: “the time elapsed between the last piece in the run just completed and the first good piece from the process after the changeover.” On a molding floor the same rule becomes last good shot to first good shot, as on our page for plastics and packaging plants.
The standard allowance compromise
A common compromise is to exclude each changeover’s standard time and count only the overrun. On the Line 2 shift that means excluding 25 of the 38 changeover minutes and counting 13. It feels fair, because the operators are judged only on what they control. It moves OEE from 75.1% to 79.6% on this shift, and it has three costs.
- Improvement below the standard disappears. Under the allowance, a changeover that takes 25 minutes and one that takes 20 both show zero changeover loss. A setup reduction project that cuts the size change from 25 to 15 minutes leaves the report unchanged, so the standard becomes a ceiling instead of a starting point.
- The cost of the schedule disappears. If planning moves from two size changes per shift to six, the extra changeover time is excluded at the standard rate and OEE barely moves. The OEE.com FAQ raises the same issue from the other side when it asks whether it is “meaningful to compare a production line that has twelve changeovers per day with a production line that has two changeovers per day.” The time spent on the extra changeovers is real, and it follows from a scheduling decision the report should show.
- The standard stops being reviewed. A standard that is subtracted from OEE stops being questioned, because shortening it would lower the reported number.
The Lean Enterprise Institute’s entry on single minute exchange of die describes the aim of setup reduction as “reducing changeover times to a single digit, or less than 10 minutes.” A reporting method in which nothing below 25 minutes can be seen works against that aim.
Keep the standard, report it separately
The fair part of the compromise is worth keeping, outside OEE. Report each changeover with its type, its actual minutes, its standard and the minutes over standard, as a separate changeover report. On the Line 2 shift the report says the size change took 38 minutes against 25, 13 over. That is the number the setup crew owns. OEE keeps all 38 minutes as availability loss, and the shift report can lead with the 13 minutes over standard as the first action, without changing the definition of OEE.
Planned maintenance, sanitation and trials: the hard cases
Planned maintenance, sanitation and engineering trials are planned, they often take the line for a fixed window and they are sometimes required by rule. Each one needs a written decision, and the decision should depend on when the work happens.
Preventive maintenance
OEE.com answers “Should preventative maintenance affect my OEE score?” with “Probably”: if it “takes away time that could otherwise be used for value-added production”, it belongs in availability. A useful way to apply that:
- Maintenance during scheduled production hours is a loss. If the line was scheduled to run and maintenance took it for two hours, availability shows two hours lost. The time is real, and moving the work to an unscheduled window is one of the ways to recover it.
- Maintenance in a window where the line was not scheduled is outside OEE. A weekend with no production scheduled is excluded time anyway. The maintenance work there does not change OEE, and it does not need to.
- Record it as its own category either way. Planned maintenance should be visible as planned maintenance, not mixed with breakdowns. The maintenance team needs that split to judge whether the preventive work is reducing failures, which is the subject of our maintenance software service.
Example (fictional). Press 12 at a fictional injection molder runs three shifts a day, five days a week, with 450 minutes of planned production time per shift after breaks: 6,750 minutes a week. Every Wednesday the maintenance team takes the press for a 240-minute preventive maintenance window on first shift. Other stops cost 910 minutes in the week, so run time is 5,600 minutes. If the Wednesday window is excluded, planned production time is 6,510 minutes and availability is 5,600 ÷ 6,510 = 86.0%. If it counts as a loss, availability is 5,600 ÷ 6,750 = 83.0%. The 3-point gap is the question the plant should be asking: could the same work be done on Saturday, when the press is not scheduled? If it could, the press gains 240 minutes of production a week and its availability rises to 86.0% for a real reason. Excluding the window would have shown the same 86.0% without the extra production, and the question would never have come up.
Sanitation and clean-in-place
Food and beverage plants often have sanitation that the food safety plan requires at fixed intervals. Our page for food and beverage lines treats scheduled sanitation and CIP cycles as named planned stops left out of planned production time, still recorded in minutes, with the treatment of overruns written down as a separate decision. OEE.com’s six big losses page lists cleaning among the planned stops that count under setup and adjustments. Both are workable. Excluding sanitation keeps OEE focused on production losses while the minutes stay visible; including it treats sanitation length as an improvement target in its own right.
Whichever you choose, write down three things: the named sanitation events and their scheduled windows, whether minutes past the window count as a loss (we recommend yes, so a growing sanitation shows in OEE), and the separate report that tracks sanitation minutes by line and by week.
Trials and engineering runs
A trial of a new product or a new material takes the line out of normal production. Exclude it only if it was scheduled in advance as non-production use, by name, with its own window. Count any product made during the trial separately. A trial that “happens” during a production shift because a scheduled run went badly is not a trial; it is a loss.
Why a high OEE usually means an exclusion problem
When a line reports an OEE in the high 80s or above, check the exclusions before celebrating. The OEE.com FAQ calls 85% “absolutely a notable and noteworthy accomplishment” for most discrete manufacturers and warns that a plant new to OEE “may very well find yourself starting with an OEE score of less than 50%.” The same company’s practical OEE page puts the temptation plainly: “A lot of companies exclude bits and pieces of time from OEE”, and its advice is “Don’t give into temptation.”
On the Line 2 shift, two reasonable-sounding exclusions (the changeover and the cap wait) take a 75.1% shift to 87.6%. Neither exclusion changed what the filler did.
Red flags to check
- Availability above about 95% on a line with changeovers and recorded stops. Possible on a dedicated line; unusual on a mixed one.
- Planned production time that changes from day to day when the shift schedule did not change. Someone is moving stops into excluded time.
- Excluded minutes rising month over month, or a category such as “Planned other” with no definition.
- OEE rising while good output per scheduled hour stays flat. Real improvement shows in output; definitional improvement does not.
- Performance above 100%, which points at the ideal rate rather than at exclusions. Our article on setting ideal cycle time covers that case.
A quick audit
Calculate two numbers for the last month alongside OEE: excluded minutes as a share of shift minutes, and good units multiplied by the ideal cycle time, divided by total shift minutes. The second number cannot be moved by exclusions. If OEE rose and the second number did not, the improvement is in the definitions.
For example, suppose a line’s monthly OEE rose from 72% to 79% over a quarter while its shift-based figure stayed at 66% and its excluded minutes grew from 7% to 15% of shift time. Nothing about the line improved. Someone started recording changeovers, or waits for material, as planned. The fix is not a lecture: it is moving those events back to stop time, restating the quarter under the written definition and showing the corrected trend.
Keep the excluded time visible: utilization and TEEP
Excluding time from OEE does not mean ignoring it. The excluded minutes belong in a second measure, so the plant can see how much of the calendar its equipment works. OEE.com’s glossary defines TEEP (total effective equipment performance) as a measure that “takes into account equipment losses (as measured by OEE) and schedule losses (as measured by Utilization)”, calculated by multiplying OEE by utilization, and utilization as “the percentage of calendar time that is used for production.”
Example (fictional). On the Line 2 shift, fully productive time is 338.2 minutes. Against planned production time (450 minutes) that is the OEE of 75.1%. Against the full 480-minute shift it is 70.5%, the same figure as the “break counted as a loss” row above, because counting the break as a loss is the same as measuring against the whole shift. Against the whole 24-hour day (1,440 minutes), with Line 2 running only first shift, it is 23.5%. The three numbers answer three questions: how well the line runs when scheduled, how much of the shift is productive, and how much of the day the equipment is earning.
Utilization is a planning and capital question, not a line question. A plant considering a second shift or a new line needs it. A supervisor trying to recover the 13 minutes on Tuesday’s size change does not. Reporting both, with clearly different names, keeps each audience on the number it can act on.
The same logic applies to the excluded minutes themselves. Report them by name each week: break minutes, meeting minutes, sanitation minutes, trial minutes. A sanitation that grows from 90 to 120 minutes over a quarter should be visible even though it never touches OEE.
Writing the one-page OEE definition sheet
Put every decision from the sections above on one page, sign it, and keep it in the data dictionary with a change log. The sheet is what lets a plant compare second shift with first, Line 2 with Line 4, or this year with last year.
There is no single international formula that all plants follow. The OEE.com FAQ answers “Is there an international standard for the OEE calculation?” with “not really”, and cites an OEE guidebook from SEMATECH (1995) and an AFNOR standard (E60-182, 2002) among publications that specify the calculation. ISO’s ISO 22400-2:2014 specifies a selected set of key performance indicators for manufacturing operations management with their formulas and elements; ISO lists it as under revision. If your company reports against a corporate KPI framework, map your sheet’s terms to it. Either way, the sheet is what makes your own numbers comparable.
What the sheet contains
| Item | What to write | Line 2 entry (fictional) |
|---|---|---|
| Measured machine | The machine OEE is calculated on, usually the constraint | Filler |
| Formula | Availability × performance × quality, per the Lean Enterprise Institute | As stated |
| Shift calendar | Shift times and the source of the schedule | 06:00 to 14:00, 480 min |
| Excluded time, by name | Each event, its window and its maximum length | Break, 10:00 to 10:30 |
| Overruns | Whether time past a window counts as a loss | Counts as a stop, reason required |
| Stop time | Everything else inside planned production time, including changeovers | All stops over the threshold, by reason |
| Reason threshold | Stops shorter than this count as slow running | 2 minutes |
| Ideal rate | Source and value for each product | 120 bottles per minute |
| Good count | First pass only, and where it is counted | Filler good count, rework not good |
| Aggregation | Sum minutes and counts first, then calculate | Never average percentages |
| Change control | Who approves a change, and its effective date | Plant manager; logged |
The aggregation rule matters more than it looks. The OEE calculator page warns against averaging OEE percentages across shifts or lines: add up the minutes and counts first, then calculate once. An average of percentages gives a short shift the same weight as a full one.
The measured machine matters too. The OEE.com FAQ recommends measuring OEE at the constraint, because “the performance of your constraint IS the performance of your line.” Stops on other machines then appear on the constraint’s record as starved or blocked time, which keeps them inside OEE without counting them twice.
Changing the sheet
Definitions will change: a new sanitation regime, a decision to run through breaks, a new product family. When one does, give the change an effective date, run the old and the new definition side by side for at least a month so the size of the step is known, and mark the step on every trend chart. Do not recalculate history silently. A trend line that jumps 4 points on the day the definition changed, with no note, will be read as an improvement by everyone who did not attend the meeting.
Stop names that match the sheet
The reason list on the shift board should use the same split as the sheet. Excluded events come from the calendar and never appear on the operator’s screen; every reason the operator can pick is a loss. Our article on designing downtime reason codes shows how to build that list so the planned category is filled from the schedule and not by a tap.
Capturing planned stops from the schedule, not the operator
A stop is excluded only if it was on the calendar before it started. That single rule removes most of the drift. If an operator or a supervisor can mark any stop as “planned” after the fact, excluded time grows every month, because every stop has a plausible story.
Where the data comes from
- The shift calendar supplies shifts, breaks, meetings, holidays, sanitation windows and scheduled trials. Monitoring software should read it from one place, not from each operator.
- The production schedule supplies the product on each run, so a product change can open a changeover automatically and close it at the first good count.
- The machine supplies its own state. Machines built to the OPC UA for Machinery building blocks (OPC 40001-1) can expose operation modes named Processing, Setup and Maintenance. The specification notes that the mode “may not be known by the MachineryItem itself”, in which case it has to come from “an external source like an MES system or the operator.” Where a machine does report Setup or Maintenance, it confirms the calendar; it does not replace it.
- PackML machines report a mode as well as a state. The OPC UA for PackML specification gives “Producing, Maintenance, Manual, Clean, Calibration” as examples of unit modes, and notes that the states available depend on the mode: the Suspended state exists in producing mode but not in maintenance mode. A filler that switches to a clean mode at the scheduled sanitation time confirms the calendar entry; one that switches to it at 11:00 on a production day shows a sanitation that was not planned.
Check the calendar against the machine
Once both sources are in the same system, compare them every week. Each excluded event on the calendar should match a period when the machine was not producing, and each period of a non-production mode should match a calendar event. A break that shows the filler running through it is a break the line does not need to exclude. A clean mode with no calendar entry is a loss that should have a reason.
Late changes
Plans change. A meeting is called at 09:00 or a trial is moved up a day. Allow a supervisor to add an excluded event before it starts, with a name and a reason, and log the change. Do not allow anyone to convert a stop that already happened into excluded time. If a stop turned out to be unavoidable, that belongs in the reason, not in the definition of planned production time.
Our production monitoring service sets up the shift calendar and the definition sheet with your supervisors before the first shift report, and logs every change to them afterward.
What to do next
- List every kind of non-running time your line had last month, from the shift log or the machine’s state history.
- Put each one in the decision table, using the two questions: was the line scheduled, and could work on the line shorten this stop?
- Run one week through both ways you are tempted to report it, as in the Line 2 table, so the people who approve the definition see what each choice does to the number.
- Write the one-page sheet, have the plant manager sign it, and put it in the data dictionary with a change log.
- Move excluded events into the shift calendar and stop accepting “planned” as a reason for a stop that was not on it.
- Report excluded minutes by name every week, beside OEE, so nothing disappears.
To see the effect on your own numbers, enter one shift into the OEE calculator twice: once with only breaks and meetings as planned stops, and once with the exclusions your plant uses today. To price the stop minutes that remain, carry them into the downtime cost calculator. If you want the calendar, the definition sheet and the shift report set up on one line first, you can plan a pilot line.