Set each preventive maintenance task’s frequency in five steps: start from the manufacturer’s interval, convert it to run hours or cycles where wear follows use, set inspection tasks from the P-F interval, weight the result by how critical the asset is, and then lengthen or shorten every interval on a fixed review cycle using what technicians actually find. No interval is correct on the day you write it. It is a starting estimate, and the as-found record is what confirms or corrects it.
This article walks through the five steps with worked examples, shows the as-found log that makes the review possible, explains why mean time between failures is a poor way to pick an interval, and notes where lockout steps belong in the task. It is written for planners and maintenance managers who already have a PM schedule and want to defend each number on it.
The five steps at a glance
Preventive maintenance frequency should come from the failure mode the task addresses, the way that failure develops, and the consequences if the task misses it. The five steps below turn those three questions into an interval you can write into a CMMS and revisit.
- Start from the maker’s interval and write down where it came from and what duty it assumes.
- Convert to run hours or cycles where the wear follows use, and keep a calendar ceiling where deterioration continues while the machine sits.
- Set inspection intervals from the P-F interval, the time between the first detectable sign of a failure and the failure itself.
- Weight by criticality. Critical assets get a larger safety margin, not a different physics.
- Review on a fixed cycle, using as-found codes on every PM close-out and failures between PMs, and lengthen, hold or shorten each interval.
The method separates two kinds of task that schedules often mix. A service or replacement task (change the oil, replace the filter, swap the wear strip) restores something that wears out. An inspection task (check the temperature, measure the belt, listen to the bearing) looks for the early sign of a failure, so the repair can be planned while there is still time. The first kind follows the wear rate. The second follows the P-F interval. Step 3 applies only to the second kind.
Step 1: start from the manufacturer’s interval and record why
The manufacturer’s interval is the right starting point because it is the only number with any engineering behind it on day one. Treat it as an assumption about duty, not as a fact about your plant, and record that assumption next to the interval.
NASA’s Reliability-Centered Maintenance Guide for Facilities and Collateral Equipment (September 2008) says PM task intervals “should be set based on location, application, and operating environment,” and that “maintenance schedules should be modified for remote locations where parts and service are not readily available.” A manual written for a clean, single-shift installation does not describe a dusty, three-shift, washdown area. The interval may still be the right starting point, but the record should say what it assumed.
For each PM task, record:
- Source. Manual title, section and page, or “technician experience” or “similar equipment,” with a name.
- Assumed duty. Shifts per day, load, environment. If the manual does not say, write “not stated.”
- Failure mode covered. “Gearbox oil degradation,” not “gearbox PM.” A task without a named failure mode cannot be reviewed, because nobody can say what it was meant to find.
- Task type. Service or replacement, inspection, or functional test.
- Warranty condition. Whether coverage depends on following the manual’s interval. If it does, keep the maker’s interval until the warranty ends or the maker agrees to a change in writing.
Where there is no manual (old equipment, a machine built in-house, a supplier long gone), start from the interval used on similar equipment, or from the senior technician’s judgment, and mark it as such. Start on the conservative side, which means shorter, and let Step 5 lengthen it. Lengthening an interval with evidence is easy to defend; explaining a failure on an interval nobody can justify is not.
Grouping matters as much as the individual numbers. NASA’s description of age exploration, its method for adjusting intervals, includes task grouping: “Tasks with similar periodicity are grouped together to minimize the amount of time spent on the job site and reduce outages.” If three tasks on one machine come out at 450, 500 and 550 run hours, set all three to 500 and do them on one stop. The small loss of precision is worth one lockout instead of three.
Step 2: convert to run hours or cycles where wear follows use
Where wear follows running, an interval in run hours or cycles tracks the wear better than the calendar does. Two identical machines on different shift patterns wear at different rates, and a calendar PM over-serves one and under-serves the other.
The federal definitions already allow for this. The DOE Federal Energy Management Program’s O&M guide, as summarized by PNNL, defines preventive maintenance as “actions performed on a time- or machine-run, time-based schedule” that “detect, preclude, or mitigate degradation.” NASA’s guide says PM “schedules periodic inspection and maintenance at pre-defined intervals (time, operating hours, or cycles).”
Which tasks to convert:
- Convert tasks where the failure mode is driven by running: lubrication of rotating parts, wear strips and belts, filters on running equipment, chains, cutting and forming tools, contactors and valves that wear with each operation.
- Keep on the calendar tasks where deterioration happens with time whether the machine runs or not, such as corrosion, aging of seals and hoses, and battery checks, as well as anything a regulation, code or insurer sets by date.
- Use both where both apply, with “whichever comes first.” A gearbox oil change at 2,000 run hours or 12 months covers a busy machine and an idle one.
You do not need a connected plant to start. Many CMMS packages can generate work orders from meter readings; the DOE O&M guide (Release 3.0) lists “calendar- or run-time-based preventive maintenance work order generation” among the typical functions of a computerized maintenance management system. The meter reading can come from an hour meter on the motor starter, the hour counter on the machine’s HMI read weekly by an operator, or a run signal read automatically from the controller. Manual readings are fine for intervals of hundreds of hours. They become a burden, and a source of typing errors, when there are dozens of meters or the intervals are short.
The counts must be trustworthy. Run hours should accumulate only while the machine is actually running, and cycle counts need protection against resets and rollover. Our article on usage-based maintenance from runtime and cycle counts covers where those counts come from and how to reconcile them with the CMMS meter so each PM fires once.
Example (fictional). A fictional bottler’s manual for a conveyor gearbox says “change oil every 2,000 operating hours or 12 months.” Line 2 runs two shifts, five days a week, and its machine-state signal shows the conveyor running about 70 hours a week, so it reaches 2,000 hours in about 29 weeks. Line 4 runs one shift and its conveyor runs about 32 hours a week; it would take about 63 weeks to reach 2,000 hours, so the 12-month ceiling governs. Under the old calendar schedule both gearboxes had their oil changed every six months. After conversion, Line 2’s interval barely changes, and Line 4’s oil change moves from twice a year to once a year.
Step 3: set inspection intervals from the P-F interval
Inspection tasks should run often enough that a developing failure is caught after its first detectable sign (P) and before it becomes a functional failure (F), with enough time left to plan and do the repair. The interval between P and F, not the calendar, sets the frequency.
The P-F interval is a core idea of reliability-centered maintenance. Sandy Dunn of the consultancy Assetivity, in an introduction to the PF interval, describes point P as the moment a technique can first detect that an item is about to fail at the alarm level set for it, and F as the moment of functional failure. Her example is a bearing: P is when its temperature first reads at or above the alarm level, and F is when it seizes.
The half P-F rule and its limits
The common rule of thumb is to inspect at half the P-F interval. Gary West, writing in Reliabilityweb, states it this way: “Conventional RCM wisdom suggests that it is usually sufficient to select a task interval equal to half of the P-F interval.” The logic is that even if one inspection happens just before P, the next one still falls at least half a P-F interval before F.
Both sources caution against applying the rule mechanically:
- Response time matters more than the fraction. Dunn says the task interval “must be the PF interval minus that response time,” where response time is how long it takes to act once the sign is found: get the part, schedule the stop, do the job. She calls the half rule something that “may or may not be appropriate.”
- The P-F interval is usually an estimate. West points to John Moubray’s “rational approach” for estimating P-F intervals “on the basis of judgment and experience” where no measured data exists. An estimate of six weeks may really be three. Dunn adds that the technique only works if the P-F interval is reasonably consistent: if “sometimes it’s a day and sometimes it’s a month,” look for another technique.
- High consequences need a smaller fraction. West writes that for “high stakes failure modes (e.g., safety, environmental and even high impact operations consequences),” a smaller fraction of the P-F interval may be appropriate.
For the high-stakes cases, West cites the U.S. Naval Air Systems Command’s RCM manual (NAVAIR 00-25-403), which calculates the number of inspections needed inside the P-F interval from an acceptable probability of failure and the probability that one inspection detects the condition: n = ln(Pacc) ÷ ln(1 − θ), and the interval is the P-F interval divided by n. In his worked example, a two-year P-F interval, an acceptable probability of 0.00001 and a 0.90 chance of detection per inspection give five inspections, an interval of 0.4 years: one fifth of the P-F interval, not one half. Few plant tasks need that rigor, but the example shows how quickly the fraction shrinks when consequences are serious and detection is imperfect.
Estimating a P-F interval without data
Most plants have no measured P-F intervals. You can still make a defensible estimate in an hour with the people who do the work:
- Name the failure mode and the technique together. The P-F interval belongs to a pair, not to a part. Dunn’s definition ties point P to “that particular technique” and “the alarm level that we’ve set.” The same bearing gives earlier warning to vibration analysis than to a hand on the housing, so its P-F interval is longer with vibration.
- Pull the corrective work orders for that failure mode from the last two or three years and read the technicians’ notes. Look for phrases like “running hot for a while” or “noisy since last month.”
- Ask the technicians who were there: when this first showed the sign we check for, how long did it keep running? Write down every answer, then use the shortest credible one, not the average.
- Record the basis: “estimate, three technicians, two failures,” with the date. That label tells the next review how much weight the number can bear.
- Check it with as-found records. If inspections at the new interval keep finding the condition well past P, or keep missing it, the estimate was off. Revise it like any other interval.
Every inspection task also needs a stated limit. “Check belt” is not a task a technician can fail. “Belt deflection at midspan no more than 1.0 inch under thumb pressure; re-tension if over” is. Without the limit, there is no P, and no P-F interval to set the frequency from. If the inspection is later replaced by a fixed sensor with an alert limit, the task leaves the PM schedule and becomes condition-based maintenance, a step described in our article on condition-based vs predictive maintenance.
Monitoring points before failure
NASA’s guide adds a complementary rule for monitoring tasks. It recommends “a minimum of three monitoring points” before failure is expected, so a trend “can be established and confirmed,” and says that where failure history gives a feel for when failure is likely, “monitoring periodicity should be selected such that there will be at least three monitoring intervals before the anticipated onset of failures.” It also observes that “the most common practice in industry is to monitor the equipment biweekly or monthly due to a lack of information,” which “often results in excessive monitoring,” and that the interval should be shortened once trending shows signs of impending failure.
Example (fictional). On a fictional bottler’s Line 2, the infeed conveyor’s drive-end motor bearing is checked on a route with a handheld infrared thermometer. The alarm level is set at 30 °F above the baseline reading. From two past failures, the senior technician estimates that a bearing reading above the alarm level seizes in about six weeks. A replacement bearing is on the shelf, but the job needs a planned stop, and the line has one every Saturday, so the response time is up to one week plus a week of margin for a busy schedule: two weeks. Half the P-F interval gives three weeks. P-F minus response time gives four weeks. The planner takes the shorter, three weeks. Because the conveyor stops the whole line and has no backup, the maintenance manager tightens it to every two weeks, which is still a short route, and logs the estimate as “technician judgment, two failures” so Step 5 can revisit it.
Step 4: weight intervals by criticality
Criticality does not change how fast a part wears. It changes how much margin you keep and how deep the task goes. A critical asset gets inspections at a smaller fraction of the P-F interval and a more cautious review; a low-criticality asset may get only route checks, or none, by written decision.
NASA’s guide makes the distinction explicitly: PM criteria “reflect the age-reliability characteristics of the equipment based upon the equipment history. The characteristics are not related to mission criticality.” Criticality decides priority, margin and whether the task is worth doing. PNNL’s summary of reliability-centered maintenance uses a six-level priority scale for the same purpose, from level 1, Emergency (life, health and safety risk), down to level 6, Deferred (“accomplished only when resources allow”).
NASA ties criticality to monitoring frequency with a reliability measure. Bearings, the guide notes, “are normally specified by their B10 life,” the age by which 10 percent of a population is expected to have failed. The guide recommends an initial periodicity “which allows a minimum of three monitoring samples prior to the B10 life,” and says that “in less critical cases, the three monitoring samples should occur prior to the MTBF point,” while “in more critical cases the three monitoring samples should occur prior to the B2 life,” the 2 percent point.
How to rank assets is a subject of its own; our sibling article on ranking equipment criticality in a small plant gives a one-page method with three bands. Once each asset has a band, these starting rules (the editors’ suggestion, not a standard) translate the band into interval choices:
| Criticality band | Inspection interval | Service and replacement tasks | Interval review |
|---|---|---|---|
| High: stops the line or can hurt someone, no backup | A third of the P-F interval or less, and never longer than P-F minus response time | Maker’s interval until as-found records support a change | Every quarter |
| Medium: slows the line, or has a backup | Half the P-F interval, checked against response time | Maker’s interval, converted to run hours or cycles where wear follows use | Twice a year |
| Low: little effect on output or safety | Route checks only where cheap | Consider run-to-failure as a written decision, with a spare on the shelf | Once a year |
Run-to-failure is a legitimate choice for the bottom band when it is made on purpose. NASA’s guide says reactive maintenance “can be used effectively when it is performed as a conscious decision based on the results of an RCM analysis that compares the risk and cost of failure with the cost of the maintenance required to mitigate that risk and cost of failure.”
Step 5: review intervals with as-found evidence
Intervals improve only when every PM close-out records what the technician found, and someone reviews those records on a fixed cycle. Without the as-found record, nobody can tell whether a task is too frequent, too rare or aimed at the wrong failure mode.
NASA calls this process age exploration, defined as “the process of determining the most effective intervals for maintenance tasks.” Its example is a chiller with a vendor-recommended open-and-inspect interval: the technician records the condition of components during each inspection, the condition sheet is correlated with performance, vibration and oil analysis data, and the interval is changed “until monitored conditions indicate degradation has occurred.” The guide says age exploration reviews three things: the technical content of the task, the performance interval, and task grouping.
Use four as-found codes
Keep the codes few enough that technicians use them on every close-out:
- A, as new. No wear, no adjustment needed.
- B, wear within limits. Some wear or drift, still inside the stated limit; minor adjustment made.
- C, beyond limit. Worn or drifted past the limit, corrected during the PM before it failed.
- D, found failed. The item had already failed when the PM reached it.
Add the measured value wherever the task has one (belt deflection, oil condition, temperature rise, chain stretch). Codes tell you the direction; measured values tell you the rate.
| Closed | Asset | Task and interval | Meter at close | As-found | Measured | Action |
|---|---|---|---|---|---|---|
| Mar 03 | Line 2 infeed conveyor gearbox | Oil change, 2,000 h or 12 months | 14,212 h | A | Oil clear, no particles on plug | Changed oil |
| Mar 05 | Line 2 labeler vacuum pump | Inlet filter, 500 h | 6,040 h | B | Filter grey, no tears | Replaced filter |
| Mar 07 | Line 2 case conveyor | Belt tension check, monthly | n/a | C | Deflection 1.4 in, limit 1.0 in | Re-tensioned |
| Mar 12 | Air compressor 1 | Intake filter, 1,000 h | 22,870 h | B | Pressure drop 60% of limit | Replaced filter |
| Mar 14 | Line 2 case conveyor | Belt tension check, monthly | n/a | D | Belt broken at splice | Replaced belt; see corrective order |
Decision rules for the review
Write the rules down before the first review, so intervals move on evidence and not on mood. These starting rules are the editors’ suggestion; adjust them to your plant and keep them fixed once chosen:
- Lengthen by one step (for example, 25%) after three consecutive A results and no failure of the covered failure mode between PMs. Never lengthen past the maker’s limit while a warranty depends on it.
- Hold when results are mostly B. That is the sign of an interval close to right.
- Shorten by one step after a C result, and re-check the P-F estimate if it was an inspection task.
- Shorten and review the task content after a D result or any failure of the covered mode between PMs. A task that keeps finding the item already failed may be the wrong task, not just the wrong interval.
- Change one thing at a time per asset, and log each change with the date, the old and new interval, and the evidence.
- Review on a fixed cycle: quarterly for high-criticality assets, once or twice a year for the rest.
Example (fictional). At its quarterly review, a fictional bottler’s planner looks at three tasks. The conveyor gearbox oil change on Line 2 has four A results in a row and no gearbox failures. The manual’s limit is 2,000 hours, so the planner does not stretch the oil change; instead, an oil sample is added at each change, and the planner asks the gearbox maker in writing whether a longer interval is acceptable with oil analysis. The labeler vacuum pump filter shows B, B, B, A, so it holds at 500 hours. The case conveyor belt tension check shows a C and then a D within one month, and the belt broke at its splice. The planner does not just shorten the check: the review finds the splice, not the tension, is the failure mode, so a splice inspection is added at every tension check, a spare belt is stocked, and the check moves from monthly to every two weeks. Each change goes into the change log with the evidence.
Review mistakes to avoid
- Shortening after every failure without reading it. A failure between PMs is evidence about a failure mode. If the failed mode is not the one the task covers, the interval is not the problem.
- One interval for every identical asset. Two identical pumps on different duties wear at different rates. Let each asset’s records move its own interval.
- Lengthening on silence. No failures and no as-found codes is not evidence that a task can stretch. It is evidence that nobody recorded anything.
- Moving many intervals at once. If five intervals change on one machine in one review and failures rise, nobody can tell which change caused it.
- Keeping tasks nobody can explain. If a task has no named failure mode and nobody can say what it is meant to find, mark it for review rather than carrying it forward another year.
Why MTBF alone should not set an interval
Mean time between failures tells you how often an asset fails on average. It does not tell you when an individual failure is likely, so an interval based only on MTBF is often too early for some units and too late for others.
NASA’s guide is direct about this: MTBF “is often used as the initial basis for determining PM interval,” but “this approach does not provide any information about the effect of increasing age on reliability. It provides only the average age at which failure occurs, not the most likely age.” The guide points to the Weibull distribution, used by the bearing industry to specify bearing life, as a better description, and summarizes the meaning of its shape factor (beta): below 1 the hazard rate decreases, at 1 it is constant, and above 1 it increases. Only failure modes with an increasing hazard rate, true wear-out, benefit from replacing parts at a fixed age.
How common is wear-out? The PNNL summary cites airline, Department of Defense and Navy studies showing that age-related failures “account for less than 20 percent of all failures,” with random failures roughly 80 percent. NASA’s guide reports that “more than 90 percent of the hardware analyzed showed no adverse age-reliability relationship,” and warns that “imposing an arbitrary preventive task often increases the average failure rate through the resetting of ‘infant mortality.’” PNNL’s list of preventive maintenance risks includes “potential for incidental damage to components while conducting unneeded maintenance.” Taking a machine apart to replace a part that was not wearing out can introduce the very failure the task was meant to avoid.
What this means for the schedule:
- Replacement and overhaul tasks belong only on failure modes with a clear wear-out pattern, set at an age or usage before wear-out begins.
- Inspection tasks belong on failure modes that give a warning, set from the P-F interval.
- For random failure modes with no warning, more frequent PM will not help. Either accept the failure with a spare on the shelf, or change the design.
- MTBF is a result to track, not an input to the interval. Use it to see whether the schedule is working.
Example (fictional). A fictional plant’s filler capper turret logged 720 operating hours, 6 failures and 9 hours of repair in a month. The MTBF and MTTR calculator gives an MTBF of 120.0 hours and an MTTR of 1.50 hours. A planner who sets a 100-hour PM to “beat” the 120-hour average learns little: the six failures came from four different failure modes, two of them electrical faults with no wear pattern at all. The better move is to sort the six failures by mode, put inspection tasks on the two modes that gave warning, and track MTBF next month to see whether it moves.
Put lockout steps inside the task
Every PM task that requires work inside a machine’s guarding should carry its energy control steps, or a direct reference to the machine’s written procedure, inside the task itself. Frequency decisions also change how often people are exposed, which is one more reason not to over-maintain.
OSHA’s lockout/tagout standard, 29 CFR 1910.147, “covers the servicing and maintenance of machines and equipment in which the unexpected energization or start up of the machines or equipment, or release of stored energy could cause injury to employees.” It requires an energy control program “consisting of energy control procedures, employee training and periodic inspections,” and says procedures “shall be developed, documented and utilized,” with “specific procedural steps for shutting down, isolating, blocking and securing machines” and “specific requirements for testing a machine or equipment to determine and verify the effectiveness” of the lockout. It also requires a periodic inspection of the energy control procedure “at least annually.”
In the PM task, that means:
- Reference the machine’s energy control procedure by its number, and list the isolation points (electrical, pneumatic, hydraulic, gravity, stored energy) in the task steps.
- Include the verification step, the try-start or zero-energy check, as a numbered step, not a note.
- Count lockout and restart time in the task duration, so the planner books a realistic stop.
- Ask your safety lead about tasks that might fall under the standard’s exception for “minor tool changes and adjustments, and other minor servicing activities” during normal production. The standard limits that exception to work that is “routine, repetitive, and integral to the use of the equipment for production” and done with “alternative measures which provide effective protection.” That judgment belongs to the plant’s safety program, not the PM planner.
This is not legal advice; it is a reminder that a PM task is a work instruction, and the safety steps belong in the instruction where the technician reads them.
Measuring whether the schedule holds
A frequency is only as good as the plant’s ability to do the work on time. Track PM compliance against a fixed window, late and missed work orders by asset, and the preventive share of maintenance hours, and check whether interval changes have made the schedule too heavy to complete.
The PM compliance calculator takes five counts from one period. In its default example, a fictional team has 120 PM work orders due, completes 102 inside the compliance window and 9 after it, and logs 300 preventive hours against 220 corrective hours. The results: PM compliance of 85.0%, completion including late work of 92.5%, 9 PM work orders missed, and a preventive share of maintenance hours, PM ÷ (PM + corrective), of 57.7%. The calculator’s note asks you to state your compliance window, “for example, completed by the due date, or within 10% of the PM interval,” and keep it fixed so months can be compared.
Interval changes and compliance pull against each other. Shortening intervals adds work orders; if technician hours do not grow with them, compliance falls and the missed PMs land on the assets nobody was watching. Before a review raises the load, add up the hours:
- List every PM task due in a typical four-week period at the new intervals, with its planned duration including lockout.
- Add the hours and compare them with the technician hours actually available for planned work after typical breakdown time.
- If the planned hours exceed what is available, lengthen low-criticality intervals or move them to route checks before you shorten anything else.
Usage-based intervals make this harder to see, because the number of PMs due each month moves with production. A busy month brings more run-hour PMs due. Forecast them from planned production hours, not from last month’s count.
Finally, watch for intervals that are honored on paper only. A PM closed in five minutes on a task planned for an hour, with no as-found code, is a missed PM recorded as compliant. Spot-check close-outs each month against the time booked and the as-found field.
A checklist for your next interval review
Run this list before each review cycle, starting with the high-criticality assets on one line:
- Every PM task names the failure mode it covers and its task type (service, inspection or functional test).
- Every interval records its source, assumed duty and the date it was last changed.
- Tasks driven by running are on run hours or cycles, with a calendar ceiling where time-driven deterioration applies.
- Every inspection task has a P-F estimate, its basis (measured or judgment), a response time, and an interval no longer than P-F minus response time.
- Each asset has a criticality band, and the interval follows the band’s rule.
- Every close-out carries an as-found code and, where possible, a measured value.
- Failures between PMs are linked to the task that was meant to cover them.
- Decision rules for lengthening, holding and shortening are written down and unchanged since the last review.
- The change log records every interval change with its evidence.
- Planned hours at the new intervals fit the technician hours available.
For teams that want a formal reliability-centered maintenance process behind these decisions, SAE publishes JA1011, Evaluation Criteria for RCM Processes, revised in 2009; its public description says it “is intended for use by any organization that has or makes use of physical assets or systems that it wishes to manage responsibly.” For a small plant, the five steps above and an honest as-found log cover most of the ground.
OpenGXT builds, hosts and maintains cloud software that reads machines and meters through open protocols and turns the data into shift-level answers. Its maintenance software counts run hours from machine states, fires usage-based PM triggers with a warning beforehand, and reports PM compliance next to the machine data, working with the CMMS you already have. If you want to walk through one line’s PM schedule with us, contact us.