Ranking equipment criticality in a small plant

The reader questionHow do we rank which machines matter most so maintenance effort, spares and monitoring go to the right assets first?

A three-step podium with a different small machine on each step and a tiny worker in front deciding their order.

Rank equipment by the consequences of its failure, not by its age, its price or how often people complain about it. For each asset, ask two gate questions: could a failure hurt someone or release something harmful, and could it send bad product to a customer without anyone catching it? Then score three production factors: whether a failure stops the line or a backup takes over, what an hour of that downtime costs, and how long it takes to get running again, which usually comes down to spare part lead time. Sort the results into three bands, check them against your work order history, and let the band decide PM depth, spare parts and monitoring.

The method below fits on one page and is sized for a plant with a handful of lines and no full-time reliability engineer. It borrows from three public sources: the prioritization step in NASA’s reliability-centered maintenance (RCM) guide, PNNL’s summary of the same step for the Department of Energy, and a qualitative method published by the Institution of Chemical Engineers (IChemE) for plants short on time for quantitative analysis. Every example number is fictional and labeled. Most examples use Line 2 at a fictional beverage bottler, the same line that appears in our example project.

What equipment criticality means, and what it does not

Equipment criticality is a ranking of assets by how much their failure would hurt the operation: people, product, output and cost. It is about consequences first. How often an asset fails is a separate input that decides the order of work, not how much the asset matters.

The public definitions agree on that core:

Two related terms are worth separating. Failure mode, effects and criticality analysis (FMECA) goes further: NASA’s glossary describes its criticality analysis as charting “the probability of failure modes against the severity of their consequences.” Risk, in most methods, is consequence combined with likelihood. This article keeps them apart on purpose. The band comes from consequences, and likelihood from your work order history sets the order of work inside each band. A small plant has too little failure history per asset to let likelihood move an asset between bands, and the rare failure that would stop the plant for a month is exactly the one that needs a spare and a plan.

Criticality is also not a few things it is often confused with:

  • Not replacement value. An inexpensive date coder can matter more than an expensive palletizer.
  • Not the bad actor list. The assets that eat the most maintenance hours are a separate list, and the method below flags them separately.
  • Not an interval. The IChemE paper by C.J. Atkinson is explicit that criticality ratings “do not represent absolute frequency values for maintenance schedules but are used to assess the frequency of one item relative to others.”

Three public methods and what a small plant can borrow

Three published methods cover most of what a small plant needs: NASA’s ten-level severity and probability tables, the six-level priority matrix that PNNL and DOE adapted from NASA, and Atkinson’s qualitative method for IChemE. Each has a piece worth keeping and a piece too heavy for a plant with a handful of lines.

NASA RCM Guide (2008)PNNL and DOE FEMP priority matrixIChemE qualitative method (Atkinson)
ScaleCriticality and severity ranked 1 to 10; probability of occurrence ranked 1 to 10Weighting 1 (Emergency) to 6 (Deferred)Seven areas, each rated 10, 5 or 1
What is ratedEffect on safety, health, environment and mission; failure rateUrgency and effect on the facility's missionInjury to the public, the environment, people on site; loss of assets or profit; common systems; excessive downtime and maintenance cost; reliability of detection and control
How ratings combineSample FMEA worksheets multiply criticality by probabilityWeightings 1 to 3 get RCM attention firstThe seven ratings are multiplied: 1 to 10 to the 7th power
Who ratesNot prescribed in the tablesFacility and O&M managersA team that knows the plant: plant manager, operating supervisor, plant engineer, maintenance supervisor
Worth borrowingConsequence and probability kept separate; scales meant to be adaptedBands that map directly to actionThree levels per factor; redundancy and statutory checks
Too heavy for a small plantTen levels are hard to agree on in a meetingGives no scoring ruleSeven multiplied factors, several built for hazardous process plants
Sources: NASA, Reliability-Centered Maintenance Guide (September 2008), Tables 4-1, 4-2 and 5-1 and Appendix J; PNNL, An Advanced Maintenance Approach: Reliability Centered Maintenance (May 2022) and Prioritizing O&M Actions; U.S. DOE FEMP, O&M Best Practices Guide Release 3.0 (2010), section 5.6; Atkinson, IChemE Symposium Series No. 144. Assessments in the last two rows are the OpenGXT Editorial Team's. Checked November 2026.

NASA: severity and probability on separate scales

NASA’s Table 4-1 ranks criticality and severity from 1 (“None”) to 10, where 9 and 10 are potential safety, health or environmental issues, with and without warning. Rank 8 is “high disruption to facility function” where all of the mission is lost with a “significant delay in restoring function.” The guide says the table was adapted from the automotive industry, that “it is not the only method available,” and that “the categories can be expanded or contracted to produce a site-specific listing.” Table 4-2 ranks probability of occurrence the same way, using failure rates per operating hour, day or cycle. The sample FMEA worksheets in Appendix J carry three columns, criticality, probability and their product, next to the chosen maintenance approach.

PNNL and DOE: a priority matrix that maps to action

The DOE O&M Best Practices Guide, Release 3.0 (August 2010) and PNNL’s current pages use a six-level matrix adapted from NASA: 1 Emergency, 2 Urgent, 3 Priority, 4 Routine, 5 Discretionary, 6 Deferred. Weighting 1 covers life, health and safety risk to a mission-critical function, and weighting 2 covers equipment whose failure puts the “continuous operation of facility at risk.” PNNL says “those systems having a weighting of 1, 2, or 3 are typically prioritized as holding the greatest RCM potential.” Its page on prioritizing O&M actions adds that “the probability of failure should also be considered” and that “facility managers should determine the scoring and prioritization methodology that is best suited for their facility.”

IChemE: a qualitative method for plants without reliability staff

Atkinson’s paper, A qualitative approach to criticality in the allocation of maintenance priorities to manufacturing plant (IChemE Symposium Series No. 144), was written because quantitative techniques “require specialised skills and are time consuming to apply.” Its method “can be used by plant staff with no formal training in reliability analysis.” A team rates seven areas at 10, 5 or 1. The paper notes that a rating of 7 is possible but that “such nuances are not likely to alter the results obtained in a significant way.” The overall rating is the product of the seven, from 1 to 10 to the 7th power.

Two of its steps carry over directly to any plant. It asks whether redundancy really reduces the consequences, including whether “common mode failure such as a failure of instrument air or electrical power” could take out both the main unit and its backup. And it cross-checks every result against statutory and manufacturer requirements, where “that dictating the more frequent inspection should be adopted.”

Step 1: List the assets and draw the boundaries

Start with a master equipment list for one line or area, at the level where you plan maintenance, and include the shared utilities that feed it. Without the list, the ranking turns into an argument about whichever machine broke last week.

The DOE guide puts this first in its steps for starting RCM: “develop a Master equipment list identifying the equipment in your facility,” then prioritize the components “based on importance or criticality to operation, process, or mission.” In its section on performance trending, it names three tests for that prioritization: equipment “critical to your facility’s operation, important to personnel safety, or can have a significant budget impact (either through failure or inefficient operation).” Atkinson’s first two steps are to define the plant boundaries for the study and the systems inside them. He warns that the boundaries must consider “the effect of plant failures on common systems and common system failures on the plant.”

Three practical rules keep the list usable:

  1. List at the level you plan work. A machine or major subsystem (filler, capper, compressor) is usually right. Break out a component only when it has its own long lead time or its own failure consequences, such as a large gearbox or a drive with no spare.
  2. Include the common systems. Compressed air, chilled water, boilers, refrigeration, electrical distribution and, in a distribution center, the sorter, main conveyors, dock doors and chargers. These are the assets most often missing from a line-by-line list, and the ones that stop more than one line.
  3. Use the names already in your CMMS and your data. If the asset is “Line 2 filler” in the CMMS, in the stop log and in the tag list, the scores can later be joined to work orders and downtime without a translation table. An ISA-95 style hierarchy of site, area, line, cell and asset works well. The same list can carry the criticality field that CISA’s inventory guidance asks for, so maintenance and OT security work from one inventory.

Example (fictional). The maintenance manager at a fictional beverage bottler starts with Line 2, the line from the example project. The list has twelve entries: the rinser, filler, capper, date coder, labeler, case packer and palletizer; the infeed conveyor gearmotor, listed separately because its gearbox has its own lead time; the conveyor chain lube unit; the plant air compressor, which feeds every line; the hot water boiler that feeds the bottle warmer; and a warehouse exhaust fan, added so the team practices scoring something that does not matter much.

Step 2: Score the consequences of failure

Score each asset on what happens when it fails at a bad time, with no warning, under today’s conditions: today’s spares, today’s backups, today’s schedule. Two gate questions come first, then three production factors that multiply into one score.

QuestionScoreGuidance
Gate S: could a failure injure someone or release something harmful?Yes or noPressure, hot water or steam, chemicals, refrigerant, stored energy, falling loads. Yes puts the asset in band A.
Gate Q: could a failure send unsafe or out-of-specification product to a customer without being caught?Yes or noOnly escapes count. Scrap caught inside the plant belongs in the cost score. Yes puts the asset in band A.
Impact (I): what happens to output?0, 1 or 20 no effect; 1 slows the line, or a backup or manual workaround takes over; 2 stops the line, area or building once buffers run out
Cost (C): what does an hour of that stop cost?1, 2 or 3Cost per hour of the line or area the asset feeds, from the downtime cost calculator. Set your own thresholds for low, medium and high.
Restore (R): how long until it runs again?1, 2 or 31 within a shift; 2 one to three days; 3 longer than three days. Include the wait for parts as they stand today.
Production scoreI × C × R0 to 18
BandA, B or CA: either gate is yes, or the score is 8 or more. B: score 3 to 6. C: score 0 to 2.
Method by the OpenGXT Editorial Team, adapted from NASA, Reliability-Centered Maintenance Guide (2008), Table 4-1; PNNL's RCM prioritization step; and Atkinson, IChemE Symposium Series No. 144. The thresholds are starting points for discussion, not values from those sources.

The two gate questions

Safety and environment come first in every public method. NASA reserves its two highest ranks for potential safety, health or environmental issues, PNNL’s weighting 1 is life, health and safety risk, and three of Atkinson’s seven areas concern injury or environmental damage. In this method they are a gate, not a score, for one reason. A multiplied score can let a low production impact hide a safety consequence. A pressure vessel that barely affects output still belongs in band A.

The quality gate asks only about escapes. If a failure produces scrap that inspection catches, that is a cost and belongs in the cost score. If it can send a mislabeled, unsealed, uncoded or unsafe product out the door, the asset is band A whatever its production score. Food plants will recognize this as the same reasoning behind their own food safety controls. This article does not cover those programs; it only makes sure the maintenance ranking does not contradict them.

A gated asset does not always need heavy maintenance. Often the better answer is a detection step. Atkinson rates the “reliability of detection/control systems” as one of his seven areas for this reason, and recommends that high-criticality items found at the design stage be reviewed “to see if it is possible to reduce criticality by using an alternative approach.”

Production impact: does it stop the line, and is there a backup?

On a serial packaging line, almost every machine stops the line once the buffer ahead of it fills or the one behind it empties. An accumulation table buys minutes, not a repair. Score what happens after the buffers are gone, over a realistic repair.

A backup lowers impact only if it is real. A second compressor, a spare pump on a manifold, a rental unit with a delivery agreement or a manual pack-out station all count, if they can carry the load. Apply Atkinson’s common mode test before you take the credit. Two compressors fed from one motor control center, or two pumps behind one strainer, can fail together. NASA’s reactive maintenance priority table puts “redundancy available” at its routine level, two steps below “continuous facility operation threatened.”

Downtime cost per hour

The DOE guide says “it is important to both define the equipment criticality and cost of down-time when determining the optimal mix of maintenance elements.” Work out the cost once per line or area, not per asset. Our downtime cost calculator adds lost contribution margin, idle crew labor and overtime to recover output, and its default fictional example comes to $952 per downtime hour. Its note lists what it leaves out (scrap at restart, expedited freight, missed orders and repair parts), so add those if you track them.

Then set the three cost levels relative to your own plant. For example, suppose a plant’s lines range from about $200 to about $1,000 per downtime hour. It might set level 1 below $250, level 2 from $250 to $750 and level 3 above $750. Atkinson’s paper used fixed loss bands in pounds sterling, but it also says the loss of assets or profit “will have to be assessed on a plant to plant basis.” Use bands that separate your lines. If every line scores 3, the factor tells you nothing.

Time to restore, and the spare lead time behind it

Restore time is the time from failure to running again: diagnosis, parts, repair and restart. In most small plants the parts decide it. NASA’s guide describes what happens in a reactive program: “If the item fails and repair parts are not available, delays ensue. If certain parts are needed to restore a critical machine or system to operation, a premium for expedited delivery must be paid.” Its glossary describes preventive maintenance as aimed at items that, if disabled, would “involve high cost or long lead time for replacement.”

Score restore time with the parts situation as it is today, not as it should be. If the spare gearbox is on the shelf and fits, restore is 1. If it must be ordered from overseas, it may be 3. That makes the ranking a working tool rather than a description: buying the right spare lowers an asset’s score, and the section on spares below shows the arithmetic. Your mean time to repair from past work orders is the best check on the restore score; the MTBF and MTTR calculator computes it from operating hours, failures and repair hours.

Combining the scores

Multiply the three factors. The product approximates the cost of one failure, hours down times cost per hour, scaled by whether output stops at all. An asset with no effect on output scores 0 whatever its lead time. A long restore multiplies an expensive hour. A sum would not behave that way: a machine that never affects output but takes a month to repair would look as important as one that stops the line for a shift.

Scoring as a team

Have each person score an asset silently first, then compare. Where the scores differ by more than one level, ask the highest and the lowest scorer to explain. Usually one of them knows a fact the others do not: a spare that was used last year and never replaced, a near miss on the boiler, a backup pump that has not been started in two years. Record that reason in a notes column. Next year’s review will need it more than the number.

Reading the factors in a distribution center or cold store

The same sheet works for distribution centers and cold storage, with the factors read for equipment rather than production machines.

  • Impact. A single sorter or main trunk conveyor usually stops the building’s outbound flow, so it scores 2. One dock door rarely does, because there are other doors, so it scores 0 or 1. One battery charger out of a bank is a backup situation.
  • Cost. The downtime cost calculator still applies if you treat cases or orders handled per hour as the rate. Idle crew labor and overtime to recover volume are often the largest parts of the cost in a building where people, not machines, set the pace.
  • Gates. Dock levelers, vehicle restraints and lifts get the safety question. So do refrigeration systems that use ammonia, because a release is a hazard to people. In cold storage, a refrigeration failure that lets product temperature rise unnoticed can trigger the quality gate. There, the detection step is temperature monitoring with alarms that reach a person.
  • Restore. Restore time often depends on a qualified technician as much as on parts: refrigeration contractors, door installers, sorter specialists. Score the wait for the person too.

Our pages on distribution center equipment and cold storage describe the signals those assets produce.

Step 3: Check likelihood against your work order history

After the consequence scores, count how often each asset actually failed. Use likelihood to order the work inside each band and to flag bad actors. Do not use it to move an asset between bands.

NASA’s guide ranks probability of occurrence from failure rates and says “historical data provides a powerful tool in establishing the ranking. If historical data is unavailable, a ranking may be estimated based on experience with similar systems in the facilities area.” PNNL’s prioritization page names the same two sources: CMMS data, or operator experience where CMMS data is missing.

Count failures over the last 12 months, using one definition for every asset, for example any unplanned stop that needed maintenance. The same rule is the note on our MTBF and MTTR calculator, and it matters more than the threshold you pick. Then sort assets into three likelihood levels. For example, a plant might call 0 or 1 failure in a year low, 2 or 3 medium, and 4 or more high.

Any asset at the high level gets a root cause review, whatever its band. Atkinson’s paper treats the same idea as its “excessive downtime and maintenance costs” area. A breakdown occurring “more than twice per year” that can lead to a hazard or a major loss of profit gets his top rating, and he recommends an investigation that “may involve replacement especially if the cost of maintenance is greater than the cost of replacement.”

Stop records from the line make the count more reliable than memory. If machine states and fault codes are already captured, a stop that needed maintenance shows up with its duration and reason. Our article on downtime reason codes covers how to make those reasons usable.

Step 4: Sort into bands and test the list

Apply the gates and thresholds, then plot consequence against likelihood and test the result against what the people who run the line already know. A ranking that surprises nobody and separates the assets clearly is the goal.

AssetGateICRScoreFailures, 12 monthsBand
1 FillerNo232125A, bad actor review
2 CapperNo233182A
3 Plant air compressorNo232121A
4 Date coderQuality23164A (gate), bad actor review
5 Hot water boilerSafety03301A (gate)
6 RinserNo23161B
7 LabelerNo23167B, bad actor review
8 Case packerNo13263B
9 Infeed conveyor gearmotorNo23162B
10 PalletizerNo13132B
11 Chain lube unitNo13131B
12 Warehouse exhaust fanNo01102C
Fictional example data for illustration: Line 2 at a fictional beverage bottler, scored with the one-page sheet above. I is impact, C is cost and R is restore time. Bad actor review applies at 4 or more failures in 12 months.
C B A: score 8 or more Line 2 assets: consequence score and failure count 0 3 6 12 18 Production score (impact × cost × restore) 0 2 4 6 8 Failures in last 12 months Bad actor review: 4 or more 1 2 3 4 5 6 7 8 9 10 11 12 Line 2 assets 1 Filler 2 Capper 3 Plant air compressor 4 Date coder (gate) 5 Hot water boiler (gate) 6 Rinser 7 Labeler 8 Case packer 9 Infeed gearmotor 10 Palletizer 11 Chain lube unit 12 Warehouse exhaust fan Band from score Band A by gate question
Fictional example data for illustration: the twelve Line 2 assets from the table above. Shaded regions show bands by production score; red squares are assets placed in band A by a gate question.

Example (fictional). The Line 2 team scores twelve assets. The filler, capper and plant air compressor land in band A on their scores: each stops production, and each takes more than a shift to restore. The capper scores the full 18 because its turret gearbox has a four-week lead time and no spare. Two assets reach band A only through the gates. The date coder is cheap and quick to fix, but a coder fault can send uncoded bottles out, because Line 2 has no code reader. The hot water boiler barely affects output, but it is a pressure system. The labeler stays in band B, but its seven failures in a year put it at the top of the bad actor list, ahead of the filler. The warehouse exhaust fan is the only band C asset, which tells the team that a full plant list will need more honest scoring at the low end.

Then test the list before anyone acts on it:

  1. Ask the floor. Ask operators and mechanics which three failures they fear most. If one of them is not in band A or B, find out whether the team missed a consequence or the fear is out of date.
  2. Look for missing common systems. Compressed air, power distribution, cooling and refrigeration often stop several lines at once and are often absent from line lists.
  3. Retest every backup for common mode. If the backup shares a power feed, a dryer, a control panel or a technician who knows how to start it, it may not count.
  4. Cross-check required inspections. Pressure systems, lifting equipment and other assets with statutory or manufacturer inspection intervals keep those intervals whatever their band. Atkinson calls statutory requirements “the minimum requirement.”
  5. Check the shape. If nearly everything lands in band A, the thresholds are too low or the team is scoring the worst conceivable failure instead of a realistic one. A ranking that does not separate assets cannot allocate effort.

Common scoring mistakes

Most bad rankings come from a handful of habits, and each one is easy to spot once named.

  • Scoring the worst conceivable failure. Score a realistic failure of the kind the asset actually has, not the one-in-a-lifetime event. The gates already catch the rare failures that could hurt someone.
  • Scoring the machine’s reputation. A machine everyone dislikes may be a bad actor without being critical. Keep the failure count in its own column.
  • Taking credit for a backup that shares a weakness. Retest backups for common power, air, controls and know-how.
  • Scoring restore time with the spare you wish you had. If the spare is not on the shelf today, score it as missing, then decide whether to buy it.
  • Letting likelihood leak into consequence. “It never fails, so it is not critical” mixes the two questions. A rarely failing capper still stops the line.
  • Mixing levels. Scoring a whole line as one asset and a single motor as another produces a list nobody can compare. Stay at the level where you plan work.

What each band gets: PM depth, spares and monitoring

The band sets how much effort an asset gets. The failure pattern of each failure mode sets which kind of task to use. A band A asset gets the most effort, but whether that effort is a run-hour PM, a condition check or a redesign depends on how the asset fails.

BandPreventive maintenanceCondition monitoringSpare partsWhen it fails
AFull task list from failure modes and the manufacturer; usage-based triggers where wear follows run hours or cycles; PM compliance reported firstWhere a failure mode gives warning: vibration spectra, current, temperature or process trends, with alerts into the CMMSParts whose lead time exceeds the outage you can accept, on site and verifiedWritten restore procedure; root cause review of every failure
BBasic task list by run hours or calendar; inspections on a routeTrends from signals that already exist: meters, drives, controllersStock when lead time is long compared with expected time between failures and the downtime costRepair with planned priority; review repeat failures
CCleaning and lubrication only where cheap; otherwise noneNone beyond existing signalsBuy on failureRun to failure as a recorded decision
Editorial guidance by the OpenGXT Editorial Team, built on U.S. DOE FEMP, O&M Best Practices Guide Release 3.0 (2010), Table 5.5.1; NASA, Reliability-Centered Maintenance Guide (2008), sections 3.3, 5.1 and 8.3; and PNNL, Prioritizing O&M Actions. Checked November 2026.

The public guides support this split. The DOE guide’s table of RCM element applications assigns reactive maintenance to “small parts and equipment,” “non-critical equipment,” “equipment unlikely to fail” and “redundant systems.” It assigns preventive maintenance to equipment “subject to wear,” “consumable equipment” and equipment “with known failure patterns,” and predictive maintenance to “critical equipment,” equipment “with random failure patterns” and equipment “not subject to wear.” NASA’s guide describes run-to-failure as “a conscious decision” and its candidates as “usually low-cost, easily repaired, and non-critical.” PNNL lists what decides between preventive and predictive maintenance: “whether an effective test or inspection method exists, the cost of the test or inspection,” “the criticality of the system in question” and “how predictably the failure occurs.”

NASA also names the outcome when no task helps. Its RCM analysis has four possible results: interval-based actions, condition-based actions, no action with repair after failure, or redesign or redundancy when no maintenance action will reduce the probability of failure. A band A asset whose main failure gives no warning and does not follow age is a candidate for the fourth.

For monitoring, NASA’s guide says installed data collection sensors “may be justified for high-priority, high-cost equipment or inaccessible equipment,” which is band A plus the band B assets nobody can reach. Which signal to install on a motor-driven asset is the subject of our article on motor current versus vibration. How often each PM should run, and how to move the interval with evidence, is covered in setting preventive maintenance frequency. Triggering PM from real run hours and cycle counts is covered in usage-based maintenance.

Example (fictional). The Line 2 team turns its bands into actions. The filler, a band A asset and a bad actor, gets a review of its five failures; the PM tasks for its fill valves move from the calendar to cycle counts taken from the filler’s own good count. The plant air compressor keeps its manufacturer service plan, and its run and load state and the air flow already measured on the line become a trend the maintenance planner reviews weekly. The date coder does not get more PM. The team proposes a code reader after the coder, because the gate was about an undetected escape, and detection removes that. The hot water boiler keeps its required inspections and nothing else changes. The labeler, band B but the worst bad actor, gets a root cause review before any new PM task is written. The warehouse exhaust fan is recorded as run to failure, with the decision and the date on the asset record.

Spare parts: let lead time and criticality decide the shelf

Stock a spare when the outage it would prevent costs more than owning the part. Criticality narrows the question to the assets where that is likely, and restore time tells you which parts matter. NASA’s guide describes the alternative: “a high percentage of unplanned maintenance activities, high replacement part inventories, and inefficient use of maintenance effort are typical when reactive maintenance is the only type of maintenance practiced.” A ranking lets the shelf hold the right parts instead of many parts.

A simple rule set works for most small plants:

  • Band A: list the parts that decide restore time for each likely failure. Stock every one whose lead time is longer than the outage you can accept. Check that the spare on the shelf fits the installed revision.
  • Band B: compare each long-lead part’s lead time with the asset’s mean time between failures and its downtime cost. Stock it when an outage of that length would cost more than holding the part.
  • Band C: do not stock. Buy on failure.

Example (fictional). The Line 2 capper’s turret gearbox has a four-week lead time and no spare. Suppose Line 2 is scheduled 16 hours a day, five days a week, and the downtime cost calculator, fed with the plant’s own figures, gives about $950 per downtime hour. If no other line can take the volume, four weeks without the capper is 320 scheduled hours, or roughly $304,000. Against that, the gearbox in this example costs $9,000. The plant buys it. With the spare on the shelf, restore time drops from 3 to 1 and the capper’s score falls from 18 to 6, moving it to band B. The score now depends on a decision, so the CMMS gets a minimum stock of one for that gearbox, and the shelf check joins the quarterly PM list.

PNNL lists “spare parts inventory” among the measures used to track failure consequences, with safety, environmental compliance, maintenance backlogs and downtime. If you report spares value by band, you can show whether the money sits behind the assets that matter.

Keeping the ranking current

A criticality ranking is a working document. It goes stale when the plant changes, and it should change only through a deliberate review. NASA describes RCM as a “living system” that feeds results back into maintenance. Atkinson writes that as history builds up, “it may, on evidence, be prudent to increase or decrease the inspection/testing frequency,” and that changes should take place only “on the formal authorisation of a competent person.”

Review an asset’s score when one of these happens:

  • New, moved or rebuilt equipment.
  • A change in product mix, schedule or margin that changes a line’s cost per hour.
  • A failure that surprised the team, in consequence or in timing.
  • A change in a supplier or a lead time, or a spare used and not replaced.
  • A bad actor fixed, which should lower its failure count over the next year.

Beyond those triggers, rescore the whole list once a year with the same team.

Keep the band where the work happens. Store it as a field on the asset record in the CMMS and in the asset inventory, so that work order priority, PM compliance and spare parts reports can be filtered by band. Report PM compliance for band A first; the PM compliance calculator shows the measure and why the compliance window must stay fixed. Our maintenance software fits around that record: it counts run hours and failures from machine data and sends work orders into the CMMS you already use, where the band on each asset can set their priority.

A checklist for the first ranking session

Score one line or area first, with a small team that knows it, and finish with a list everyone can defend. Atkinson’s minimum team for the detailed assessment is the plant manager, an operating supervisor, the plant engineer and a maintenance supervisor. Add someone who can answer the safety and quality gate questions.

  1. Prepare the list. Master equipment list for the line, including common systems, with names matching the CMMS.
  2. Prepare the numbers. Downtime cost per hour for each line or area, failures per asset for the last 12 months, and lead times for the long-lead parts you already know about.
  3. Agree the thresholds. Cost levels, restore levels and the bad actor count, written at the top of the sheet before scoring starts.
  4. Answer the gates. Safety and quality questions for every asset, before any production scoring.
  5. Score impact, cost and restore. Score a realistic failure under today’s conditions, not the worst case anyone can imagine.
  6. Multiply and band. Apply the thresholds, then plot score against failures.
  7. Test the list. Ask the floor, look for missing common systems, retest backups, cross-check required inspections.
  8. Assign actions by band. PM depth, spares to buy, signals to monitor, bad actors to investigate, each with an owner.
  9. Record it. Store the band on each asset in the CMMS, and write down the thresholds and date so next year’s review compares like with like.
  10. Set the review date. Plus the triggers above.

The band A assets of one line are also a sensible place to start connecting machine data, because they are where an early warning or an accurate run-hour count pays off first. Our guide to choosing a pilot line covers that decision. If you want to work through it on your own equipment, plan a pilot line with us.