Condition-based maintenance triggers work when a measured condition, such as a gearbox temperature or a bearing’s vibration level, crosses a limit you have set. Predictive maintenance uses the same kind of measurements but trends them to estimate when the limit will be crossed, so the job can be planned before the alert arrives. The federal guides most plants read treat the two names as near synonyms, so the useful difference lies in what your data does: compare a reading against a limit, or project a date. A small plant can run threshold-based condition monitoring on a handful of critical assets first, and move to prediction once it has months of consistent readings and honest failure records.
This article sets out what the IEC vocabulary, the U.S. Department of Energy’s O&M guide and NASA’s reliability-centered maintenance guide actually say, draws a working line you can write into your maintenance plan, and lays out a four-rung ladder from calendar PM to trend-based forecasts, with the data and the skills each rung needs.
What the standards and federal guides say
The public references do not draw one shared boundary between the two terms. The IEC vocabulary files condition-based maintenance under preventive maintenance, while the DOE and NASA guides use “predictive maintenance” for nearly the same idea. Knowing where each source stands keeps a vendor’s framing from becoming your definition.
IEC. The International Electrotechnical Vocabulary, the IEC’s public terminology database, defines condition-based maintenance (IEV 192-06-07) as “preventive maintenance based on the assessment of physical condition.” A note adds that the assessment “may be by operator observation, conducted according to a schedule, or by condition monitoring of system parameters.” The same vocabulary defines condition monitoring (IEV 192-06-28) as “obtaining information about physical state or operational parameters,” used “to determine when preventive maintenance may be required.” In the IEC’s view, then, condition-based work is a kind of preventive maintenance, and an operator’s walk-round counts as a condition assessment.
DOE. The Federal Energy Management Program’s Operations and Maintenance Best Practices guide, Release 3.0 (August 2010), summarized by Pacific Northwest National Laboratory on its maintenance approaches page, names four approaches: reactive, preventive (“time-based actions”), predictive (“fix it before it breaks”) and reliability-centered maintenance, which combines the other three. It defines predictive maintenance as “measurements that detect the onset of system degradation,” and draws the line against preventive work this way: predictive maintenance “schedules maintenance tasks based on the quantified condition of the equipment,” while preventive maintenance schedules them “solely based on time.” There is no separate condition-based category. What the IEC calls condition-based, the DOE guide calls predictive.
NASA. The NASA Reliability-Centered Maintenance Guide for Facilities and Collateral Equipment (September 2008) defines condition-based maintenance as maintenance “scheduled only when the condition of the facility or equipment requires it,” which “replaces maintenance scheduled at arbitrary time or usage intervals.” Its glossary entry for predictive maintenance simply says “See condition monitoring,” and it defines condition monitoring as monitoring and diagnosis “in order to forecast failure.” Its chapter on predictive testing and inspection (PT&I) opens with “PT&I, also known as predictive maintenance or condition monitoring.”
ISO. Two ISO documents separate the work more cleanly. ISO 17359:2018 “gives guidelines for the general procedures to be considered when setting up a condition monitoring programme for machines.” ISO 13381-1:2015 covers prognostics: guidance “for the development and application of prognosis processes,” with further parts described for trending approaches, “cyclic-driven life usage techniques” and “useful-life-remaining models.” Monitoring and diagnosis sit in one document; estimating what happens next sits in another.
| Source | Condition-based maintenance | Predictive maintenance | What it means for a plant |
|---|---|---|---|
| IEC vocabulary (IEV 192) | Preventive maintenance based on assessing physical condition, by operator observation, scheduled checks or condition monitoring | No separate entry among the maintenance terms checked | Condition-based work is still preventive work; manual rounds count |
| DOE FEMP O&M guide, Release 3.0 (via PNNL) | Not a separate category | Measurements that detect the onset of degradation; tasks scheduled on quantified condition | "Predictive" here means what IEC calls condition-based |
| NASA RCM guide (2008) | Maintenance scheduled only when condition requires it | "See condition monitoring"; monitoring and diagnosis to forecast failure | The two names point at one family of techniques |
| ISO 17359:2018 and ISO 13381-1:2015 | Setting up a condition monitoring programme | Prognosis: trending, usage-driven life and remaining-life models | Detecting a condition and forecasting its course are different jobs |
So the argument over names is mostly a matter of which document you were trained on. The difference that matters on the floor is a difference of method, and you can define it yourself.
The naming does matter in one place: when you buy something. A quote for “predictive maintenance” can mean a box of wireless sensors with alarm limits, a vibration analyst who visits monthly, or software that claims to forecast failure dates. Ask the supplier two plain questions. Does the product compare readings with limits that you set and can read, or does it produce a date? If it produces a date, how wide is the error band, and what record of failures was it checked against? The answers tell you which rung of the ladder below you are actually buying.
A working line: a limit or a forecast
For a plant’s own maintenance plan, the clearest line is this: condition-based maintenance compares a reading with a limit and acts when the limit is crossed; predictive maintenance projects the readings forward and acts on the estimated date of crossing. Both use the same sensors and the same inspection rounds. They differ in the analysis and in how much lead time the planner gets.
That line sits inside a longer list of triggers, and it helps to write all four into the plan so every task says which one it uses:
- Time-based preventive maintenance. The calendar fires the work: every month, every quarter.
- Usage-based preventive maintenance. Run hours or cycle counts fire the work. NASA’s guide describes preventive maintenance intervals as “time, operating hours, or cycles,” so usage-based PM is still preventive maintenance, only with a better clock. Our article on usage-based maintenance from runtime and cycle counts covers the data side.
- Condition-based maintenance. A measured value outside a limit or band, for longer than a set time, fires a work request now.
- Predictive maintenance. A projected date fires a planned job: “at the current rate, this reading reaches its limit in about six weeks, so plan the bearing change for the shutdown in four.”
Condition-based and predictive tasks share one precondition. The failure mode has to give a measurable warning before it becomes a failure. NASA defines a potential failure as “an identifiable condition that indicates a failure is imminent.” Reliability engineers call the time between that first detectable sign (P) and the functional failure (F) the P-F interval. If a failure mode gives no detectable warning, neither approach can see it coming, and no amount of software changes that.
The figure shows why the distinction matters. A limit alert can only give you the time between P and F, which for some failure modes is days. A forecast made from the trend earlier on can give you weeks, which is the difference between an emergency job and a job on the next planned stop. The price is that a forecast is an estimate, and it can be wrong in both directions.
A short comparison you can paste into a maintenance plan:
| Question | Condition-based | Predictive |
|---|---|---|
| What fires the work | A reading outside its limit for a set time | A projected date of reaching the limit |
| Data needed | Current readings and a limit | A history of comparable readings and a trend method |
| What the planner gets | A work request now | A planned job on a date, with a margin |
| Main way it goes wrong | Limit too tight (false alerts) or too loose (late alerts) | Trend changes shape, so the date is off |
| Who can run it | A maintenance tech with a clear limit | Someone who can judge a trend and its spread |
How to run condition-based maintenance on a few assets
To run condition-based maintenance, pick a failure mode that gives a measurable warning, choose a signal that shows it, set a limit and a persistence time, and route the alert to a person who can act. Done on three to five critical assets, that is a complete program, not a pilot of something bigger.
- Pick the asset and the failure mode. Start from the machines whose failure stops a line or hurts someone. A short criticality ranking does this job; our sibling article on ranking equipment criticality gives a one-page method. Name the failure mode, not just the machine: “drive-end bearing wear on the infeed conveyor motor,” not “conveyor.”
- Choose the signal that shows that failure mode. Bearing wear shows in vibration and temperature, a blocked filter in differential pressure, a failing winding in electrical tests, a hot connection in an infrared scan. NASA’s guide lists vibration monitoring, lubricant analysis, thermography, airborne ultrasonics and motor circuit testing among its PT&I technologies. Whether a given motor is better watched through current or vibration is a separate question, answered in our article on motor current or vibration monitoring.
- Set the limit. Use the equipment maker’s limit where one exists. Where none exists, record a baseline at normal load and speed, then set the limit as a margin above it. The baseline matters more than any published table. NASA gives the reason with a simple case: a fan running at an overall vibration level of 0.2 inches per second “is closer to the point of functional failure” than an identical fan at 0.1 inches per second “and should be monitored more frequently.”
- Add a persistence time. Require the value to stay outside the limit for a set number of minutes before an alert is raised. One spike during a start-up or a product change should not page anybody.
- Compare like with like. Stamp each reading with the machine state and the product running. A gearbox runs warmer at full line speed than at half speed; a fan’s vibration changes with its damper position. A limit that ignores the operating context will either cry wolf or stay silent.
- Route and record. The alert should carry the asset, the signal, the limit, the value and how long it was exceeded, and it should land with a named person. When the work is done, the technician records what was found. That as-found note is what tells you, months later, whether the limit was right.
Setting a first limit when there is no published number
Many plant machines come with no condition limit in the manual. In that case, build the limit from your own baseline and write down how you did it, so the next person can repeat it.
- Take readings at one operating condition (same product, same speed, machine warmed up) for one to two weeks.
- Note the highest normal reading and how much the readings spread from day to day.
- Set the alert limit far enough above the highest normal reading that ordinary spread does not reach it. If the readings are numerous and stable, a statistical rule such as the baseline average plus three standard deviations is a reasonable start; with only a handful of readings, a fixed margin chosen by the technician who knows the machine is just as defensible.
- Write the limit, the baseline period, the operating condition and the date into the asset’s record.
- Review the limit after the first three alerts or the first three months, whichever comes first.
A limit set this way detects change from normal, which is what condition-based maintenance needs. It does not tell you how close the machine is to failure in absolute terms; for that, published severity guidance and the equipment maker’s advice still matter.
Manual rounds fit this model. The IEC note on condition-based maintenance allows the assessment to be “by operator observation” or “conducted according to a schedule.” A weekly route with a handheld infrared thermometer and a vibration pen is condition-based maintenance, provided each reading is written against a limit and someone acts on it. Permanent sensors only make sense where the P-F interval is shorter than a practical route interval or where the asset is hard to reach.
Example (fictional). A fictional beverage bottler reads two temperatures on its Line 2 filler. One is the main drive gearbox oil temperature. Over two weeks of normal running at 120 bottles per minute, it sits between 128 °F and 136 °F. The maintenance lead sets a limit of 155 °F, evaluated only while the filler is in its running state, with a persistence time of 15 minutes. On a Tuesday first shift the reading climbs past 155 °F at 08:32 and stays there. At 08:47 a work request reaches the shift technician with the asset, the signal, the limit and the duration. During the planned 10:00 break the technician finds the oil level low and a weeping seal, tops up the oil, and orders a seal for the next planned stop. The as-found note reads “oil level low, seal weeping, no damage found.” The limit did its job: the work happened on a planned stop rather than as a breakdown repair.
What predictive maintenance adds, and what it costs
Prediction adds lead time. To earn it you need repeated, comparable readings, a method for projecting them forward, and the discipline to state how uncertain the projection is. Without those three, a “prediction” is a limit alert with a date attached.
NASA’s guide describes the target with a conceptual degradation graph that moves from detect, to alert, to remove from service, and it is frank about the limits: “Although the actual moment of failure for most systems and components is not known, the fact that failure is imminent is known.” For setting how often to take readings, it recommends “a minimum of three monitoring points” located before failure is expected, because “using three data points, the trend can be established and confirmed.” It also says the monitoring interval should be reduced once trending shows signs of impending failure.
The methods a small plant can use are not exotic. NASA lists the ways PT&I data is used: “trend analysis,” “pattern recognition,” “data comparison,” “tests against limits and ranges,” “correlation of multiple technologies” and “statistical process analysis.” Only the last of these, statistical process analysis, asks for statistical skill beyond what a planner already has. A straight-line trend of a stable reading, a rate of change per week, or a comparison between identical machines on the same duty covers most of what a plant with a few hundred assets will ever need.
Example (fictional). A fictional plant takes monthly overall vibration readings on a roof exhaust fan and has set its own alert limit at 0.30 inches per second. The last four readings are 0.10, 0.11, 0.13 and 0.16. A straight line through all four rises 0.02 per month and reaches the limit about 7.3 months after the fourth reading. A line through the last two readings rises 0.03 per month and reaches it in about 4.7 months. The honest forecast is “somewhere between about five and seven months, and the rise is speeding up.” The planner shortens the reading interval to every two weeks and books the bearing change into the planned shutdown four months out. If the next two readings rise faster still, the job moves earlier.
A forecast a planner can do by hand
The arithmetic in the example takes five minutes with a calculator, and it is worth doing the same way every time:
- List the last readings taken at the same point, by the same method, at the same operating condition. Drop any reading taken just after maintenance on that component.
- Work out the rise per week (or per month) two ways: across all the comparable readings, and across only the last two or three.
- For each rate, divide the distance from the latest reading to the limit by the rate. That gives two estimates of the time remaining.
- Report both as a range, and say whether the recent rate is faster than the long one. A faster recent rate means the curve is bending upward.
- Set the next reading well inside the shorter estimate, and plan the repair on a stop that falls before it.
If the two estimates disagree wildly, or the readings jump around more than they trend, the asset is not ready for forecasting. Keep it on a limit alert and keep collecting comparable readings.
Notice what made the example work. The readings were taken at the same spot, with the fan at the same duty, by the same method. If the measurement point had moved, or the damper had been reset between readings, the trend would have measured the change in method, not the change in the bearing. Most failed prediction efforts in small plants fail here, on comparability, before any question of algorithms arises.
What breaks a forecast:
- A change in operating context. New product, new speed, a different shift pattern. Record the context with every reading.
- Maintenance that resets the trend. A re-grease or an alignment changes the reading. Mark these events on the chart so the next trend starts from them.
- Too few points. Two readings make a line through any two values. NASA’s three-point minimum is a floor, not a target.
- Failure modes that accelerate. Many degradation curves bend upward near the end, so a straight line drawn early tends to forecast late. That is why the interval shortens as the reading rises.
Predictive maintenance also costs more to run. The PNNL summary of the DOE guide lists its risks as “increased investment in diagnostic equipment,” “increased investment in staff training,” and “savings potential not readily seen by management.” None of those are reasons to avoid it. They are reasons to apply it where the lead time is worth the effort, and nowhere else.
The data and skills each approach needs
Each step from calendar PM toward prediction needs more data, kept more carefully, and somewhat more skill to read it. The table below sets out what each approach asks of a small plant before it can work.
| Approach | Trigger data | History needed before it works | Skills | Typical tools |
|---|---|---|---|---|
| Time-based PM | Calendar | None | Planning and scheduling | CMMS or spreadsheet |
| Usage-based PM | Run hours, cycle counts | A few weeks to check counts against reality | Reading machine states and counters | Machine signals, CMMS meters |
| Condition-based | A reading and a limit | A baseline at normal load | Choosing limits and persistence times | Handheld instruments or fixed sensors, alert routing |
| Predictive | A trend of comparable readings | Several readings per asset before failure, and recorded failures | Judging a trend, its spread and its context | Historian or trend charts, the same sensors |
Three kinds of data quality decide whether the upper rows work at all.
Identity. Every reading, work order and failure has to point at the same asset with the same name. If the CMMS calls it “FILLER-02,” the PLC tag calls it “L2_FLR,” and the vibration route calls it “Line 2 filler,” joining them later becomes a manual job. A shared asset hierarchy (site, area, line, machine) settles this before any analysis begins, and it is the same structure that machine connectivity work uses to name signals.
Context. Readings need timestamps, units and the machine state at the time of the reading. A temperature without “running at full speed” next to it is hard to compare with the next one.
Failure records. Prediction is only checked against failures, so failures have to be recorded the same way every time. The note under our MTBF and MTTR calculator puts it plainly: count a failure the same way every time, and write that definition down. Add the failure mode and the as-found condition to each corrective work order, and within a year you will know which alerts were real.
On skills, the gap between rungs is smaller than the marketing suggests. A maintenance technician who already reads a vibration pen and an infrared thermometer can run condition-based maintenance once the limits are written down. Prediction needs one person who looks at trends every week, knows the machines, and is allowed to move a job on the schedule. That is a role, not a data science team.
A ladder for a small plant: what to run first
A small plant should climb from calendar PM to usage-based PM, then to condition limits on its critical assets, and only then to trend forecasts where history justifies them. Each rung keeps the ones below it in place. Most assets in most plants stay on the first two rungs for good, and that is the right answer for them.
Rung 1: calendar PM with as-found notes. You need an asset list, the manufacturers’ manuals and a place to record work. The improvement most plants can make here costs nothing: on every PM close-out, record what the technician found (fine, worn within limits, worn beyond limits, failed). Those notes are the evidence that later lengthens or shortens intervals, a method laid out step by step in our article on setting preventive maintenance frequency. Move up when most PM work orders close with an as-found note.
Rung 2: usage-based PM from machine signals. Where wear follows use, run hours and cycle counts replace the calendar. The data often already exists: the machine state read for production monitoring is a run-hour meter, and the good count is a cycle counter. The hard part is counts you can trust, with resets and rollovers handled, and a single place where the PM fires. Move up when machine meters and CMMS meters agree for a month.
Rung 3: condition limits on critical assets. Pick the three to five assets whose failure hurts most, name the failure modes that give warning, and set limits, persistence times and alert owners as described above. Keep the calendar and usage tasks that cover failure modes the sensors cannot see. Move up when you have reviewed several months of alerts, marked each as confirmed or not found, and tuned the limits.
Rung 4: trend forecasts where history allows. Apply trending to the assets where you have at least several comparable readings before a typical failure, failures recorded with their modes, and a stable operating context. Start with a weekly review of a handful of trend charts by one named person. Add more assets only when the forecasts have been right often enough to trust.
The ladder matches what the federal guides recommend in substance. NASA’s guide says condition-based maintenance “should not replace all interval-based maintenance,” and that interval-based maintenance “is still appropriate for those instances where an abrasive, erosive, or corrosive wear takes place; material properties change due to fatigue, embrittlement, or similar processes; or a clear correlation between age and functional reliability exists.” The PNNL summary of reliability-centered maintenance recommends that implementation “start slowly, and perhaps with a pilot program,” on a system that “has been challenging from an O&M perspective but also has definable success indicators.”
Mistakes that stall the climb
- Buying sensors before naming failure modes. A sensor without a named failure mode and a limit produces data nobody reads. Start from the failure, then pick the signal.
- Sending alerts to a shared inbox. An alert that belongs to everyone belongs to no one. Name a person and a backup per asset and shift.
- Dropping PM tasks because a sensor is installed. A vibration sensor watches the bearing, not the coupling guard, the belt tension or the lubrication schedule. Retire a PM task only when a condition task covers the same failure mode.
- Changing limits without a log. If a limit moves every time it is annoying, nobody can tell later whether an alert was missed or tuned away. Log each change with its reason.
- Treating a supplier’s health score as a failure record. A score is an opinion about condition. A failure record is what actually happened. Keep them separate, and check the first against the second.
Where neither approach fits
Some failure modes are better handled by a calendar task, a usage task, a functional test or a decision to let the item fail. Reliability-centered maintenance exists to make that choice per failure mode instead of per plant, and it is worth knowing its boundaries even if you never run a formal RCM analysis.
No measurable warning. If a failure mode gives no detectable sign before it happens, condition monitoring has nothing to see. NASA’s guide says PT&I “does not lend itself to all types of equipment or possible failure modes and therefore should not be the sole type of maintenance practiced.”
Wear that tracks age or use. For abrasion, erosion, corrosion and fatigue, the NASA guide keeps interval-based tasks. A conveyor belt splice that wears with every revolution, a die that wears with every stroke or a filter that loads with every hour is often handled more simply by a usage-based task than by a sensor.
Cheap, non-critical items. Run-to-failure is a legitimate strategy when it is chosen on purpose. NASA’s examples include “non-critical electric motors less than 7.5 HP, comfort cooling, restroom exhaust fans,” and it says reactive maintenance “can be used effectively when it is performed as a conscious decision” after comparing the risk and cost of failure with the cost of preventing it. Write the decision down and stock the spare.
Protective devices that act only on demand. A low-level switch, a standby pump or a safety interlock can fail without anyone noticing until it is needed. Neither a limit alert nor a trend will see that, because the device produces no reading while it waits. These failure modes need a scheduled functional test. NASA’s RCM analysis considerations list “hidden failure” as its own category for this reason.
Tasks set by someone else. Inspections required by a regulation, an insurer or a code stay on their required interval regardless of what condition data says. Condition data can inform how thoroughly you do them, not whether.
For teams that want to adopt a formal reliability-centered maintenance process, SAE publishes JA1011, Evaluation Criteria for RCM Processes, revised in 2009. Its public description says it “is intended for use by any organization that has or makes use of physical assets or systems that it wishes to manage responsibly.” As its title says, it sets criteria for evaluating an RCM process; it is a reference for choosing a method, not a schedule you can copy.
How to tell whether the change is working
Judge the change by records you can check, measured with definitions that stay fixed: PM compliance, the preventive share of maintenance hours, failures per asset, and, for condition alerts, how many were confirmed and how much warning they gave. If those numbers do not move after two or three quarters, the problem is usually the limits or the follow-up, not the method.
Start with a baseline. The PNNL page on maintenance approaches suggests assigning “the relative percentage of program activity (time or cost)” to reactive, preventive and predictive work, and notes that “an organized O&M program should be able to make decent estimates (within 5% or 10%).” A month of work orders sorted into those buckets gives you the starting point.
Then track four groups of numbers each month:
- Schedule health. PM compliance and completion including late work, from the PM compliance calculator. Its last result is labeled “Preventive share of maintenance hours,” PM hours divided by PM plus corrective hours. Decide in writing where a job raised by a condition alert belongs. Most plants book it as planned corrective work, so it will lower the preventive share even when it is exactly the job you wanted.
- Reliability. Mean time between failures and mean time to repair per critical asset, with failures counted the same way every month. The MTBF and MTTR calculator shows the arithmetic.
- Alert quality. For each condition alert: confirmed (the technician found a defect), not found, or not yet inspected. Track the ratio per asset and per signal. A limit that produces mostly “not found” is too tight; a failure with no alert before it means the limit is too loose, the reading interval too long, or the failure mode invisible to that signal.
- Warning time. For confirmed alerts, the time from the alert (or the forecast) to the as-found inspection, and whether the repair happened on a planned stop. This is the number that tells you whether prediction is buying anything over limits alone.
Example (fictional). A fictional plant’s maintenance team uses the PM compliance calculator’s default figures for one month: 120 PM work orders due, 102 completed inside the window, 9 late, 300 hours of preventive work and 220 hours of corrective work. The calculator returns PM compliance of 85.0%, completion including late work of 92.5%, 9 work orders missed, and a preventive share of maintenance hours of 57.7%. In the same month its five monitored assets raised 7 condition alerts: 5 confirmed, 1 not found, 1 not yet inspected. Three of the five confirmed jobs were done on planned stops. The team leaves the limits alone, chases the uninspected alert, and looks first at the 9 missed PMs.
Do not expect any of these numbers to reach zero failures. Condition limits and forecasts give warning for failure modes that announce themselves; they do not make machines immune to the ones that do not. The goal is more planned work and fewer surprises, measured honestly.
A first month on one line
Start on one line, with three to five critical assets and the people who already maintain them. Four weeks is enough to put the first two rungs in order and set the first condition limits, as long as the work is written down as you go.
- Week 1: list and name. Write the asset list for the line in one hierarchy, with the same names the CMMS uses. Mark the critical assets. For each, list the failure modes that have caused unplanned stops in the last year.
- Week 1: classify every task. Tag each existing PM task as calendar, usage, condition or functional test. Add an as-found field to the close-out form if there is none.
- Week 2: pick the signals. For each critical failure mode with a measurable warning, choose one signal and how it will be read (route or fixed sensor). Record the machine states you can already read, because those give you run hours for free.
- Week 2 to 3: baseline. Take readings at normal load for two weeks. Note the product and speed with every reading.
- Week 3: set limits and owners. Write each limit, its persistence time and the person who receives the alert. Put the definitions in one document so they can be reviewed.
- Week 4: review. Count alerts, confirmed defects and as-found notes. Adjust one limit at a time, and log each change with its reason.
- After three months: decide which assets have enough comparable history to start a weekly trend review.
OpenGXT builds, hosts and maintains cloud software that reads machines and meters through open protocols and turns the data into shift-level answers on output, downtime, quality, maintenance and energy. Its maintenance software counts run hours from machine states, raises condition alerts from limits you set and can read, and feeds work requests to the CMMS you already use; the rules are written down, and they are not failure predictions. If you want to talk through which rung your first line is on, get in touch.